This commissioning report summarizes the results of commissioning activities for mechanical systems installed as part of a laboratory renovation project at a federal building. Systems commissioned include air handling units, terminal units, laboratory hoods, hot water heat exchangers, pumps, exhaust fans, and energy recovery units. Construction was completed in early 2018 in five phases. Commissioning activities included developing checklists, functional tests, site observations, and verification testing. Several issues were identified and resolved during the process related to controls programming, sensor calibration, and seasonal testing. The report provides an overview of each mechanical system and recommendations for future re-commissioning, sensor recalibration, and operations and maintenance. Appendices include supporting documentation from the commissioning process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
DEA Lab Upgrades
GSA Project # GS-05-P-16-FB-C-7002 GSA Contract #GS-05-F-16-FB-C-7003
HVAC Equipment Submittal
March 26, 2018 Submittal # GS05F16FBC7003-019113.01
Owner General Services Administration
Federal Building 536 South Clark Street Chicago, Illinois 60605
Architect JLK Architects
230 West Huron, Suite 510 Chicago, Illinois 60654
Engineer
AEI
10 South LaSalle Street, Suite 2700 Chicago, Illinois 60603
Prime Contractor Monaco Mechanical, Inc.
1971 University Lane Lisle, Illinois 60532
Sub-Contractor Burns McDonnell
200 West Adams Street Suite 1600
Chicago, Illinois 60606
Supplier
Specification Equipment ID Equipment Manufacturer
019113 Commissioning Report Burns McDonnell
This page has been provided as part of the submittal.
DEA Lab Upgrades at 536 S. Clark
Drug Enforcement Agency and US General Services Administration
Project No. 96992
Revision 2 02/02/2018
DEA Lab Upgrades at 536 S.
Clark prepared for
Chicago, IL
Project No. 96992
Revision 2 02/02/2018 prepared by
Burns & McDonnell Engineering Company, Inc.
Chicago, IL
COPYRIGHT © 2015 BURNS & McDONNELL ENGINEERING COMPANY, INC.
DEA Lab at 536 S Clark 2017 Revision 2 Commissioning Report and Executive Summary
TABLE OF CONTENTS
Page No.
1.0 COMMISSIONING REPORT AND EXECUTIVE SUMMARY ........................... 1-2
1.1 Construction and Testing ..................................................................................... 1-3
1.2 Commissioning Team .......................................................................................... 1-4
1.3 Lessons Learned ................................................................................................... 1-4
1.3.1 Reheat System and Phasing .................................................................. 1-4
1.3.2 Automation and Controls Testing ......................................................... 1-5
1.3.3 Freeze Protection .................................................................................. 1-5
1.4 Basic Operations and Maintenance ...................................................................... 1-5
1.4.1 Re-commissioning Schedule ................................................................. 1-6
1.4.2 Sensor Re-Calibration Schedule ........................................................... 1-6
1.5 Systems Descriptions ........................................................................................... 1-7
1.5.1 Lab Air Handling Units ........................................................................ 1-7
1.5.2 Lab Space Terminal Units and Lab Hoods ........................................... 1-9
1.5.3 Office Air Handling Units .................................................................. 1-10
1.5.4 Hot Water Heat Exchangers and Pumps ............................................. 1-10
1.5.5 Exhaust Fans ....................................................................................... 1-11
1.5.6 Energy Recovery System .................................................................... 1-12
2.0 FINAL ISSUE RESOLUTION LOG ................................................................... 2-1
2.1 Open Issues on 1/02/2017 .................................................................................... 2-1
2.2 Close Issues on 1/02/2017 ................................................................................... 2-2
APPENDIX A - COMMISSIONING PLAN
APPENDIX B - COMPLETED CHECKLISTS
APPENDIX C - FUNCTIONAL TESTS
APPENDIX D - MEETING MINUTES
1.0 COMMISSIONING REPORT AND EXECUTIVE SUMMARY
Commissioning (Cx) is a quality oriented process designed to verify the constructed systems meet the owner’s expectations for operability, maintainability, and energy efficiency. To obtain these goals, Burns and McDonnell (BMcD) performed the following scope of work activities
1. Developed Cx plan and schedule
2. Conducted a construction phase Cx kickoff meeting
3. Developed Pre-Functional Checklists
4. Developed Functional Performance Tests for systems to be commissioned
5. Performed site visits, attended construction phase meetings, and delivered follow-up reports
6. Witnessed Functional Performance Testing performed by Siemens
7. Maintained Cx Issues Log
8. Compiled Cx Report
The commissioned systems include the following list
System Estimated Quantity
Sampling Rate
Air Handling Units, Return Fans 8 100% Energy Recovery Units and Exhaust Fans 8 100% Supply VAVs, Exhaust VAVs, Air Valves 133 100%* Steam to Hot Water Heat Exchangers 6 100% Reheat, Preheat, and Energy Recovery Pumps 10 100% Finned Tube Radiators 20 100% 100% Control System Graphics/Alarms/Trending N/A 100%
*Lab spaces were tested with 100% sampling rate. Office spaces were sampled at a 20% rate as required by the specification, however to do complications throughout the project, almost all the terminal units were tested
1.1 Construction and Testing
The construction phase of the project began in early 2017 and completed in early 2018. In addition to calling into weekly meetings, Burns and McDonnell completed the following activities on-site:
• January 18th, 2017: BMcD Initial Site Walkthrough
• March 3rd 2017, Commissioning Kick-Off Meeting, Functional Test Review
• March 20th -24th: Phase One Testing
• May 8th -9th: Phase Two Testing
• August 28th-30th: Phase Three Testing
• November 3rd, 6th: Phase Four Testing
• December 21st, 22nd: Phase Five initial Testing (Systems were not complete)
• January 30th-31st: Phase Five Final Testing and Issue Resolution
The following table details the equipment included in each phase of the project. Due to the project’s phased nature, during several of the earlier phases, the full mechanical system was not complete and not all the testing could be completed. At later phases, BMcD returned to re-test these items. This included the hot water reheat systems, which was not available until the end of the summer. However, during each phase, the full airside system was tested, including lab pressurization testing so that the DEA could occupy the space, even though the temperature controls were not complete. By the completion of the 5th phase of the project, all systems were commissioned and verified to be operating as designed (with the exception of some outstanding issues)
Phase Equipment Phase 1 AHU-8-4 East Phase 1 Lab 8036 - AHU-4/5 - East Phase 1 Lab 8041 "North Control Zone" - AHU-4/5 - East Phase 1 Lab 8041 "South Control Zone" - AHU-4/5 - East Phase 1 Lab 8050 - AHU-4/5 - East Phase 1 Lab 8051 - AHU-4/5 - East Phase 1 Office VAVs Phase 1 AHU-8-5 Northeast Phase 2 Phase 2 - Office VAVs Phase 2 Phase 2- AHU-8-3 - Northwest Phase 3 Phase 3 - AHU-8-1 Southeast Phase 3 Phase 3 - Lab 8060 "North Control Zone" Phase 3 Phase 3 - Lab 8060 "South Control Zone" Phase 4 Phase 4 - AHU-8-6 South Phase 4 Phase 4 - Lab 8073 - AHU-8-6
Phase 4 Phase 4 - Lab 8074 - AHU-8-6 Phase 4 Phase 4 - Lab 8078 - "East Control Zone" AHU-8-6 Phase 4 Phase 4 - Lab 8078 - "West Control Zone" AHU-8-6 Phase 5 Phase 5 - AHU-8-2 - Office
Tested as Part of Phase 5 ERU-8-1 (EF-234 A,B,C) and associated glycol pumps Tested as Part of Phase 5 ERU-8-2 (EF-567 A,B,C) and associated glycol pumps Tested as Part of Phase 5 Preheat Hot Water System 1 Tested as Part of Phase 5 Preheat Hot Water System 2 Tested as Part of Phase 5 Reheat Hot Water System
1.2 Commissioning Team
TEAM ROLE COMPANY / NAME CONTACT INFO
Owner General Services Administration Sonya.Griffin@gsa.gov Project Manager Sonya Griffin Owner General Services Administration Elvin.Poole@gsa.gov Project Technical Representative Elvin Poole Owner General Services Administration Joshua.Westhouse@gsa.gov Property Manager Josh Westhouse General Contractor Monaco Mechanical rblake@Monacomechanical.com Project Manager Robert Blake 630 484-6886 General Contractor Monaco Mechanical Jeff@Monacomechanical.com Project Manager Jeff Gritzenbach 630 810-8900 Commissioning Services Burns and McDonnell mlchmura@burnsmcd.com Project Manager Mark Chmura 708-217-8112 Commissioning Services Burns and McDonnell mrernst@burnsmcd.com Cx Field Engineer Matt Ernst 312-521-8946 Mechanical Engineer AEI caugustyn@aeieng.com Project Manager Chris Augustyn Controls Contractor Siemens Cruz.laura@siemens.com Project Manager Laura Cruz, Rikki Simms 224.201.5782 Test & Balance Contractor Mechanical Test and Balance bfridono@mechanicaltestandbalance.com Project Manager Bob Fridono, Joel Hoglind 312-320-7148
1.3 Lessons Learned
Overall, the project was successful and did not undergo significant problems that caused delays or quality of service issues. However, there were a few items that BMcD would like to highlight as important items to consider for projects in the future.
1.3.1 Reheat System and Phasing
The hot water reheat distribution piping was one of the few items that was not in scope to be replaced. As the project was phased, it was difficult to fully isolate one phase of system to use it to test the entire system. Also, during a later phase during pressure testing, it was discovered that the HW loop was leaking in a variety of places. This caused some delays in finishing this system and required more work than expected resulting in a change order. It is recommended to pressure test an existing reheat system prior to mailto:Sonya.Griffin@gsa.gov mailto:Elvin.Poole@gsa.gov mailto:Joshua.Westhouse@gsa.gov mailto:rblake@Monacomechanical.com mailto:Jeff@Monacomechanical.com mailto:mlchmura@burnsmcd.com mailto:mrernst@burnsmcd.com mailto:caugustyn@aeieng.com mailto:Cruz.laura@siemens.com mailto:bfridono@mechanicaltestandbalance.com keeping it during a renovation project. Also, if piping is to be reused during renovation, it is recommended to start this work first so that any major issues can be identified early in the project and a plan can be put in place to avoid any delays.
1.3.2 Automation and Controls Testing
The phased approach to the project led to a significant number of items that were left incomplete when moving on to the next phase. This led to a lot of items falling through the cracks and left to be identified by the commissioning agent during functional testing. Ideally during functional testing, the system is
100% complete and this is demonstrated to the commissioning agent (BMcD). However, during many times BMcD would find that 50% or more of the items that needed to be tested were not working correctly. On future projects, it should be stressed that commissioning is intended to be a verification of working systems, not troubleshooting.
1.3.3 Freeze Protection
During the final weeks of the original project schedule, there was a freeze incident that affected many of the reheat coils. Many events lead to the freezing of these coils which could have be prevented. The cold air (below -10 deg F) entered through the AHU and traveled down the ductwork. This occurred during the unoccupied time of the building when no building staff was present. The AHU coils surprisingly froze yet did not burst. The reheat coils froze and burst. The mechanical systems of this phase had yet to be commissioned (the testing was scheduled for the upcoming week) and the proper freeze protection sequence did not work as predicted. However, the other AHUs on the floor did work properly, and none of the other AHUs or reheat coils from the previous phases of work were affected by the colder temperatures. Several of the other AHUs had to shut down, to prevent the coils from freezing, as the equipment was designed and programmed to do. In the future, it is important to stress the importance of coordinating the operating of mechanical equipment prior to commissioning and turnover.
1.4 Basic Operations and Maintenance
The preventative maintenance program onsite will be executed by GSA’s maintenance and operations subcontractor which at this time is CMC, represented by John Krause. During the final stages of the project, Monaco Mechanical gave training on the maintaining the required systems. It is recommended that the maintenance intervals found in the manufacturers’ Operations and Maintenance manuals provided by Monaco Mechanical be followed to maintain performance and longevity of the equipment.
1.4.1 Re-commissioning Schedule
It is BMcD’s recommendation that the equipment be re-commissioned in 5 years (2023) and every 3 years thereafter to validate component and system performance conforms to the design intent and construction documents.
1.4.2 Sensor Re-Calibration Schedule
BMcD recommends recalibration of sensors to verify accuracy and ensure the system is operating as designed. Sensors should be recalibrated based on the environment that they are operating in. For example, sensors operating in an outdoor airflow will get much dirtier than those in a filtered airflow.
Based on this, recalibrate sensors based on the following table.
Sensor Service 1 Years 3 Years 5 Years
AHU Air (Temp/
Humidity/ Pressure /
Safeties)
X
Outdoor Air X
Indoor (Temp/
Humidity/ Pressure)
X
Fluid (HW, CHW
Temp and Humidity)
X
Electrical (Power, Statuses)
X
1.5 Systems Descriptions
The following systems descriptions are intended to provide a general overview of the scope of the project as well as to be used as a training tool to understand how the applicable mechanical systems function.
1.5.1 Lab Air Handling Units
The air handling units that supply the lab spaces draw 100% outside air through a heat recovery coil, hot water coil, chilled water coil, humidification section and supply it to the labs via 2 supply fans. The outside air damper opens and close as the unit is enabled and disabled. The lab space requires a constant static pressure, however the airflow will vary significantly based on the heating/cooling demand as well as the lab hood sash positions. Shown below is a listing of the AHUs as well as a one-line diagram.
Most of the programming is unchangeable via the front-end computer and must be changed by a Siemens technician while connecting directly to the controller. However, there are several setpoint that can be adjusted as necessary if the conditions of the space change over time.
Description Setpoint value Comments
Static Pressure Setpoint:
The supply fans modulate together to maintain this setpoint at all times
1.5” wc (set by the
TAB contractor for each AHU separately)
Adjustable. The lab needs a constantly pressure to the VAVs to maintain a steady space pressurization control.
Heat Recovery Setpoint 52 deg F Hard coded. Under 50 deg F outside air temperature, the HR coil valve modulates to maintain this setpoint as a first stage of heating
Discharge Air Temperature
Setpoint
55 deg F (Some
AHUs use 60 deg F)
The heating and cooling coil valves modulate to maintain this setpoint.
Lab Humidity Setpoint 35% RH Under 50 deg F outside, the humidification valve modulates to maintain the setpoint in the lab space. Humidification steam is valved off.
Shown below is the temporary Siemens Graphics that were used to test during the construction phase
1.5.2 Lab Space Terminal Units and Lab Hoods
Each lab space has a minimum of one supply VAV (with or without reheat coil), one exhaust VAV, one lab hood (and associated flow control damper), and differential pressure sensor. The labs are designed to vary the airflow to the rooms to maintain temperature control as well as room pressurization. Each different lab type has a unique sequence of operation.
Description Setpoint value Comments
Room Airflow
Offset:
Various Adjustable. This setpoint is unique to each area. The TAB contractor and Cx agent set the airflow offset for each room to maintain an average of -0.02”wc of static pressure across the entryway to each space. Some rooms are leakier than others and require a higher offset. It is only recommended to adjust this setpoint if a qualified professional ensures the room stays properly pressurized after any adjustments are made.
Space
Temperature
Setpoint:
72 deg F Adjustable.
1.5.3 Office Air Handling Units
The office air handling units have a similar setup to the lab air handling units, however they draw return air from the space, have economizer dampers and have no heat recovery coil.
Description Setpoint value Comments
Static Pressure Setpoint:
The supply fans modulate together to maintain this setpoint at all times
1.0” wc (set by the
TAB contractor for each AHU separately)
Adjustable. These AHUs serve some lab space as wellThe lab needs a constantly pressure to the VAVs to maintain a steady space pressurization control.
Economizer Setpoint 50 deg F Adjustable. When OAT<RAT, the return air damper modulates to maintain the setpoint
Discharge Air Temperature
Setpoint
55 deg F The heating and cooling coil valves modulate to maintain this setpoint.
Lab Humidity Setpoint 35% RH Under 50 deg F outside, the humidification valve modulates to maintain the setpoint in the lab space
1.5.4 Hot Water Heat Exchangers and Pumps
There are two heating systems that serve the AHU preheat coils and one system serves the hot water reheat coils on the floor. Each system is nearly identical in setup and includes, two steam to hot water heat exchanger (lead/backup), modulating steam valves (1/3 and 2/3) and accessories, 2 inline hot water pumps (lead/backup), air-dirt separator, expansion tank, chemical feed, temperature sensors and differential pressure sensor.
Description Setpoint value Comments
Differential Pressure
Setpoint:
6psi Adjustable. His value is set by the balancer to maintain design flow through the coils at 100% system load. However, this setpoint has since been increased due to some dirty coils not receiving enough flow to produce suitable reheat discharge air temperatures.
Discharge Temperature
Setpoint:
150 deg F @ 32 def
OAT
110 def F @ 60 deg
F OAT
In between 0 and 60 deg F OAT, the setpoint is adjusted linearly
Reset schedule not user adjustable, however change to the programming can be made. The setpoint is user adjustable
Some information may vary between the three systems.
1.5.5 Exhaust Fans
There are two exhaust fan banks each with three strobic fans located on the roof. These systems are controlled by the manufacturer’s local control to maintain a constant pressure setpoint. This system is not controlled by the Siemens system.
1.5.6 Energy Recovery System
The two energy recovery systems are each composed of three separate components. Each system has two energy recovery pumps which supply a water/glycol mix through the energy recovery coils in the air handling units, and then through the energy recovery unit (ERU) coils on the room which are upstream of the exhaust fans. The goal of the energy recovery system is to draw heat from the lab exhaust air stream and use it to pre-heat the outdoor air supplied to the labs by the air handling units.
Description Setpoint value Comments
Pump Speed Setpoint One system requires
100% pump speed, while the other requires 60%
Adjustable. This value is set by the balancer to maintain design flow through the coils at 100% system load.
An example of the Energy Recovery Unit is shown above as well as the energy recovery glycol pumps shown below
DEA Lab at 536 S Clark 2017 Revision 2 Final Issue Resolution Log
2.0 FINAL ISSUE RESOLUTION LOG
2.1 Open Issues on 2/02/2017
See the attached pages for a complete list of open issues that identified by the commissioning agent
(BMcD) and were unresolved as of 2/2/2018 at the completion of functional testing
Item Date Found Status Equipment ID Resolution Date
Issue Recommendation/Solution Created By Responsible Party
Date Corrected Corrected By Comments Verified
5 5/5/2017 Open AHU-8-5 1/31/2018 Item for tracking: 5.5.17 running exhaust fans manually, no software currently linking AHU operation with exhaust fan operation. Will test at a later date upon completion of exhaust system
The design sequence calls for the exhaust fans to prove they are on before the supply fans can start. This programming does not exist yet as the exhaust fan system is under construction. Will test at a later date upon completion of exhaust control system
Matthew Ernst
Siemens 1/31/2018 Matthew Ernst 11.24.17 Update. This programming is still not in place
1.31.18 Udpate: This
programming is in place, however the sequence requires points from the exhaust fan VFDs or Exhaust fan local control panel. The issue was raised on 1.30.18 by
Siemens that the communication to the local control panel is very inconsistent (goes in and out). Using this controller could possible cause the AHUs go be disabled if the programming is in place.
Siemens to continue troubleshooting and when the exhuast fan VFD points are integrated, they will enable this programming
Project Issues
55 11/3/2017 Open Lab 8078 Supply VAV 2 Reheat actuator is broken. Valve is command 100%, and the VAV box produces no heat
Replace actuator Matthew Ernst
Siemens 1.31.18: This reheat valve actuator was replaced and the new one is still not working as of today's testing
57 11/6/2017 Open AHU-8-6, SAT 8078-5:
The reheat valve does not change the discharge air temperature when commanded open or closed
The valve was confirmed to be working by Siemens. It appears this strainer may be plugged. Monaco is aware of this box on 1.31.18
Matthew Ernst
Monaco
58 11/6/2017 Open Phase 4: Biohazard and Trace Analysis Room are not mechanically complete (Room 8070)
The supply VAVs are complete and balanced, however the exhaust is not complete. This work is waiting on a changeorder or further direction per
Siemens/TAB 1.31.18
Matthew Ernst
Monaco
63 11/7/2017 Open All reheat valves on the floor were tested 11.3.17.
This list was updated on
1.31.18 and the fixed valves were removed from this list
SAT-8010A (serves front open office space), No heat -> This is on Monaco's list as a plugged strainer
SAT-8024-1 and SAT- 8025 (Safe Room), No heat -> This is on Monaco's list as a plugged strainer
SAT-8041-2, No heat -> This is on Monaco's list as a plugged strainer SAT-8054 (Hallway outside of RM 8054) No heat -> This is a bad actuator. Siemens to replace and verify operation
SAT-8062 (located in RM8041 serves offices in that corner), No heat -> This is on Monaco's list as a plugged strainer
SAT-8030 (Lab 8030), No
Investigate and fix reheat valve issues
12/21/2017: Siemens reports that all of these valves have been verfied working in the field. It was also reported that some of the coil strainers were cleaned.
Some coils are still not getting heat.
Matthew Ernst
Monaco 11.24.17 BMcD to reset once issues are resolved
1.31.18 BMcD retested
the provided list and added comments
69 12/22/2017 Open 1/31/18 Testing on glycol system
Need to map the VFD points for the VFD power (kW) and the HOA switch status as shown on drawings
Mark Chmura
Siemens 1/31/2018 Matthew Ernst Glycol system was tested by BMcD on 1.31.18, howevever open items are listed
70 1/31/2018 Open X-EV-8073-1 Lab Hoods in Room 8073: The airflow sensor is sending back a signal
(for airflow) less than 1 V, meaning it is sensing 0 CFM. The hoods were partially open. The airflow reading is not accurate and needs to be troubleshot
Lab Hood in 8074: The hood are wired to the supply box. For this room they need to be wired to the exhaust box (EAT- 8042-Gen). Since the design calls for a constant volume supply, and a variable exhaust (based on hood airflow)
Recommend having Siemens lab hood calibration team look at these hoods and all Phase 5 hoods to ensure calibration and wiring
Matthew Ernst
Siemens
71 1/30/2018 Open AHU-8-2: The supply fan VFD speed command does not match the speed shown on the drives.
Rikki to reprogram the span of the command 1.30.18
Matthew Ernst
Siemens
73 1/30/2018 Open AHU-8-2: High and low pressure switches do not shut down the return fan
(only shuts down the supply fan)
Need to add a line of code Matthew
Siemens
74 1/31/2018 Open Exhaust fan setpoint appears to be -2.0" wc.
However the reading appears to be -3.9"wc
(the control is local and Siemens/TAB is not sure if this control is working).
Currently, the exhaust fans are running at 100% and the exhaust system is satisfied. This may be proper operation, however it is unclear how the controller is programmed and what the true setpoint is.
Strobic needs to verify the programming is set up properly
Matthew Ernst
Monaco
75 1/30/2018 Open AHU-8-2: Final Filter pressure sensor does not work. When pressure is applied to the inlet side tubing, the sensor does not close its contacts. It appears to be electrically broken.
May need to replace sensor Matthew Ernst
Siemens
76 1/31/2018 Open Reheat HW System:
Water pressure point does not exist on BAS.
(This is not differential pressure, this is measuring the static pressure before the pumps)
Investigate if sensor is in place and added troubleshoot the sensor is properly connected to controller/BAS front-end
Matthew
Siemens
DEA Lab at 536 S Clark 2017 Revision 2 Final Issue Resolution Log
2.2 Close Issues on 2/02/2017
See the attached pages for a complete list of closed issues that identified by the commissioning agent
(BMcD) and were resolved during the construction process
Item Date Found Status Equipment ID Resolution Date
Issue Recommendation/Solution Created By Responsible Party
Date Corrected Corrected By Comments Verified
1 5/5/2017 Closed AHU-8-4 5/5/2017 AHU-8-4, AHU-8-5:
Preheat leaving coil temperature sensor and freezestat located after the cooling coil (not in between the preheat coil and cooling coil as shown on drawings and graphics).
Matthew Ernst
Chris Augustyn
5/5/2017 Chris Augustyn
AEI answered RFI in Feb 2017 indicating the sensor and freezestat can be located downstream of the cooling coil
X
2 5/5/2017 Closed AHU-8-5 5/8/2017 General Note on all AHUs: The filter rack from the manufacturer was the wrong size upon shipping.
The manufacturer needs to provide a new filter rack add on assembly for the prefilter and final filter pressure sensor tubing (5.5.17)
Matthew Ernst
Robert Blake 5/8/2017 Robert Blake The new filter rack was installed 5.8.17
X
3 5/5/2017 Closed AHU-8-4 5/5/2017 In Unoccupied Mode, the sequence maintains 45 deg F at the discharge air temperature sensor , which is located far downstream of the coil.
For freeze prevention purposes, it is recommended to use a closer DDC temperature sensor
In Unoccupied Mode, the sequence was changed to modulate the heating valve to maintain 45 deg F at the heat recovery leaving temperature, not the discharge air temperature sensor (as found in sequence upon testing)
Matthew Ernst
Siemens 5/5/2017 Siemens Confirm this has been transfered to other AHU programming
X
Project Issues
4 5/5/2017 Closed AHU-8-4 5/5/2017 The freeze protection shutdown sequence and the pressure switch shutdown sequence are the same. The OA damper closes, fans disable, the heat recovery valve opens to 100%, the heating valve opens to 50%, and the chilled water valve opens to 10%
No change, for tracking purposes only
Matthew Ernst
Siemens 5/5/2017 Siemens This is different from sequence in drawings but is acceptable in alarm conditions
X
6 5/5/2017 Closed AHU-8-5 General Note: 5.5.17 AHU Testing: Need to turn on steam during heating mode to test the upper humidification limit
This does not affect the use of the space, however the humidification will have to be tested
Matthew Ernst
Robert Blake 11/24/2017 Matthew Ernst 11.24.17 Heating testing was completed during
November testing
X
7 5/5/2017 Closed AHU-8-5 1/31/2018 When one of the two supply fans is disconnected from power (with the run command being sent), a fan failure is not sent to the BAS.
Add a virtual fan failure point, when the status of either fan is OFF and the supply fan command is ON, then initiate an alarm (and keep the unit running).
(Existing programming does send an alarm when both fans fail, no changes necessary on that programming). This applies to all AHUs
Matthew Ernst
Siemens 1/31/2018 Matthew Ernst 11.24.17 This programming is still not in place
1.31.18 Update:
Siemens added an alarm for each fan. If the status of the fan (via current transducer) does not match the command, then an alarm will be enabled after a short time delay
X
8 5/5/2017 Closed AHU-8-5 General Note: 5.5.17 Need to test cooling mode for Phase 1 AHUs and control when chilled water is available from the building
Matthew Ernst
Robert Blake 11/24/2017 Matthew Ernst This was tested during a later phase functional testing
9 5/5/2017 Closed HWP-8-6 12/21/2017 The hot water system pumps are currently enabled when the outside air temperature is below 50 degrees. The pump speed is modulated to maintain a differential pressure setpoint at the end of the hot water loop.
Since the AHUs have energy recovery, there can be a situation where the pumps enable below 50 degrees, yet none of the AHU hot water valves open. If that is the case, the hot water pumps would be deadheading because there is no bypass in the system.
On the 5.8.17 walkthrough, we talked about adding programming to only enable the pumps when one of the AHU hot water valves opens past a certain percentage (not enabled on outside air temperature) to prevent this from occuring.
Matthew Ernst
Chris Augustyn
12/21/2017 Mark Chmura 11.24.17 This programming is still not added and needs to be.
Siemens is aware
12/21/2017: Siemens has added programming that polls all of the AHU heating hot water valves associated with the heat exchanger package and totals the command outputs. If the total is less than 20% the pumps will go into a min flow mode ~30% speed.
X
11 5/5/2017 Closed SAT-8041-5 5/8/2017 For a typical lab space with airflow differential control, in full cooling with 80% of the lab hoods open, the general exhaust does not reduce its airflow to maintain the lab differential airflow setpoint.
Siemens is checking on the programming on 5.5.17
Matthew Ernst
Siemens 5/8/2017 Matthew Ernst This only occurs when 75% or more of the hoods are open at the same time, in full cooling mode. This will likely never occur and the system was not designed to handle this particular situation. If it does happen, the room will only go more negative and this does not present any apparent hazards or system issues
X
12 5/8/2017 Closed X-EV-8041-8 5/8/2017 Snorkels missing on applicable BAS graphics
Matthew
Siemens 5/8/2017 Siemens Added to graphics X
13 5/8/2017 Closed AHU-8-4 Airflow measuring stations not calibrated, need information on how to calibrate manufacturer
AFMS on panel. See balancing report
The username and password information for the fan wall controller (user, 0000) was provided. The balancer will coordinate with Siemens to calibrate AFMS
Matthew Ernst
Mechanical
TAB
11/24/2017 Mechanical
TAB
This was completed during a later phase
X
14 5/8/2017 Closed EAT-8050-2 1/31/2018 Snorkel 8050-2 is sized for 450 cfm total. 2 of 3 snorkel fittings are capped at the ceiling. The VAV is trying to pull 450 cfm through one snorkel and getting about 230 cfm with the exhaust VAV
100% open
Change the setpoint if the snorkels will remain capped
Matthew Ernst
Chris Augustyn
1/31/2018 Matthew Ernst All 3 snorkels are installed. The box is exhausting 450 CFM per design with the damper
18% open
X
15 5/8/2017 Closed 12/21/2017 Differential pressure sensor for room 8050 does not work. The sensor reads permanently -0.08 "wc even if the calibration is changed and the tubes are blown into
Replace the DP sensor in room 8050. Siemens is aware of this issue. This is an existing sensor (not installed as part of Phase 1 construction)
Matthew Ernst
Siemens 12/21/2017 Mark Chmura 12/21/2017: The sensor reading seems to be changing as of 12/21.
This sensor is informational and as part of testing the terminal units were setup (with balancer assistance) to maintain the correct negative pressure differential.
16 5/8/2017 Closed 1/30/2018 The lab hood in room 8050 does not change its airflow whether open or closed (approximately
400 cfm). When the lab hood is opened it alarms because it cannot reach 100 fpm as measured by the hood.
Investigate if the lab hood control works and re calibrate the airflow sensor.
Having the correct airflow reading is required for proper room differential pressure control. This issue will likely be solved during the hood recertification process. Until then, it does not cause an hazards or significant system operational issues
Matthew Ernst
Robert Blake 1/30/2018 Matthew Ernst All lab hoods on phases 1 through 4 were calibrated by Siemens prior to 1.30.18. These issues have been resolved
X
17 5/5/2017 Closed SAT-8050 5/8/2017 SAT-8051, when called into cooling does not increase its setpoint above its minimum airflow
Matthew Ernst
Siemens 5/8/2017 Siemens The box had a parameter ("Volume
State") that was set to constant volume (numeral 1). After
Siemens look into it, the control parameter was reset to 3, indicating
VAV control. At this point the damper modulated between min and max setpoints to maintain the room temperature.
5.9.17
21 5/9/2017 Closed SAT-8048 5/8/2017 SAT-8048 (Phase 1 Corridor): When the damper is 100% open, the VAV box airflow measuring station is only reading 220 CFM. The damper appears to work as the airflow changes when the damper is overridden however the calibration must be off.
This VAV should be supplying 665 CFM at least to maintain the positive hallway pressure
Investigate issue and recalibrated AFMS if required. Siemens to investigate and inform
Mechanical TAB if further action required
Matthew Ernst
Siemens 1/31/2018 Matthew Ernst On 1.31.18, this box was supplying 665 CFM with the damper 61% open.
The box was repaired and recliabrated by Siemens and TAB
X
22 5/9/2017 Closed SAT-8072 5/8/2017 SAT-8072 was set up in the BAS controls as a constant volume box.
This is a variable flow terminal unit with a minimum and maximum airflow setting
Matthew Ernst
Siemens 5/8/2017 Siemens The control parameter called "volume state" was changed from 1 to 3, which changes the ability of the VAV box to modulate between its minimum and maximum position
X
23 6/15/2017 Closed 6/21/2017 AHU-8-3 Phase 2 Static Pressure sensor is reading approximately 0 " wc when the duct is pressurized to 2 "wc at the AHU and the VAVs downstream of the pressure sensor are getting full flow.
The pressure sensor may be in a bad location. It is currently on the supply branch downstream of SAT- 8022 on an elbow above the hallway. Siemens checked the digital setup and it appears to be operating properly. Reccomend moving the sensor
Matthew Ernst
Matthew Ernst 6/21/2017 Matthew Ernst The static pressure at the current location was measured with a separate device and appears to be fine. The sensor in question was found to be receiving AC power, when the sensor required DC. This adjustment was made at Siemens' panel, and the sensor appears to be operating properly and reading accurately
24 6/15/2017 Closed SAT-8010A Discharge air temperature sensor was left hanging, not installed in duct
Install in duct work. Work completed on 6.15.17
Matthew Ernst
Siemens 6/15/2017 Siemens X
25 6/15/2017 Closed SAT-8010 SAT-8010 and SAT-8010 space temperature sensors will be programmed together
(common space). SAT- 8010's sensor is reading about 75 when the measured space tempeature is about 74, while 8010a's sensor is about 72. The space does not have a difference in temp from one thermostat to the other.
Recommend controlling the space based on one thermostat
Matthew Ernst
Siemens 9/1/2017 Siemens Siemens added programming to average the two sensors
X
26 6/15/2017 Closed SAT-8019 SAT-8019: Adjusted the thermostat to 70 (below room temp of 74). The box does not go into cooling mode, the damper does not open to max airflow. The max and min setpoints are programmed correctly, but the programming appears to be not working
Investigate and correct programming. Corrected
(airflow was overriden during balancing)
Matthew
Siemens 6/15/2017 Siemens X
27 6/15/2017 Closed General Note for Maintenance: After you override a space temperature setpoint and then release it, the thermostat will automatically go to 62.
Then from the space you have to change it to whatever you want
Just a note to be aware of if the operators are overriding space temperatures
Matthew Ernst
Matthew Ernst 6/15/2017 Matthew Ernst Notes for record X
28 6/15/2017 Closed Room 1532 (Small evidence room) (8025):
The canopy hood does not change its supply flow whether the damper is 100% open or closed
Review with the balancer and Siemens is looking into it
Matthew Ernst
Siemens 6/15/2017 Siemens Siemens found the airflow sensor tubing backwards and the damper wiring backwards (corrected and tested)
X
29 6/21/2017 Closed AHU-8-3 1/31/2018 AHU-8-3 (Phase 3):
Supply air relative humidity sensor reading high (90%), appears to be not functioning properly
Matthew Ernst
Matthew Ernst 1/31/2018 Matthew Ernst 11.24.17 BMcD will verify the sensor is now working
1.30.18 This sensor was
reading 17% RH which was similar to other AHUs supply RH sensors
X
30 6/21/2017 Closed AHU-8-3 12/21/2017 AHU-8-3 (Phase 3) When placed into "servce mode" at the Siemens panel, the supply fans are commanded off, but the return fan continues to run at its minimum VFD speed
Correct programming to send a disable command to both supply and return fans
Matthew Ernst
Siemens 12/21/2017 Mark Chmura 11.24.17 BMcD to retest items from phase 3
12/21/2017: The code has been modified to include the RF in the
"service mode" programming.
31 6/21/2017 Closed AHU-8-3 12/21/2017 Programming for AHU-8- 3 economizer mode not in place. OA damper does not modulate to maintain DAT, when OAT <50 deg
F
Add programming Matthew Ernst
Siemens 12/21/2017 Mark Chmura 11.24.17 BMcD to retest items from phase 3
12/21/2017: Siemens currently has the Office AHUs programmed so that the OA and RA dampers modulate to maintain a mixed air temperature setpoint of 55F. This program seems to work at all OA temperatures.
X
33 6/21/2017 Closed AHU-8-3 12/21/2017 AHU-8-3: relief air pressure control: The PID loop is slow and only opens the damper to 2% after a couple minutes with the pressure around double the setpoint
(0.5"wc)
Recommend speeding up the PID loop to open the damper significantly faster (recommend immediately starting or going to 20%)
Matthew Ernst
Siemens 12/21/2017 Mark Chmura 11.24.17 BMcD to retest items from phase 3
12/21/2017: The relief pressure setpoint was hardcoded in the program to 0.5" w.c..
This was changed to
0.25"w.c. and the damper was able to control to meet the new setpoint.
34 6/21/2017 Closed AHU-8-3 1/31/2018 AHU-8-3: OA flowmeter is not reading accurately
12/14/2017: Need to discuss how can we make sure we're always receiving the minimum outside air flow. Currently Siemens is controlling the OA and RA dampers to a mixed air temperature and has a minimum allowable OA damper position of 35%.
12/21/2017: Spoke with the TAB contractor and they are willing to find a min OA damper setpoint for the AHUs if that is the path forward.
Recommend removing OA flowmeter from sequence logic
Matthew Ernst
Siemens 1/31/2018 Matthew Ernst 11.24.17 BMcD to retest with Siemens
1.31.18: BMcD retested new sequence and described the new operation in the completed functional tests
X
35 6/21/2017 Closed AHU-8-3 Supply air static pressure PID loop. Overshoots setpoint up to 3.5-4 "wc, when trying to ramp up to
2" wc
Slow down PID loop Matthew Ernst
Siemens 8/1/2017 Siemens This was corrected by Siemens
36 6/21/2017 Closed AHU-8-3 1/31/2018 AHU-8-3: humidification sequence not programmed (maintains 35% retrun air relative humidity)
Matthew Ernst
Siemens 1/31/2018 Matthew Ernst 11.24.17 BMcD to retest upon completion
1.31.18 BMcD tested the
sequence and function ofthe valve without steam. No testing will be completed with steam humidification per meeting on 1.30.18
37 6/21/2017 Closed AHU-8-3 AHU-8-3: When the prefilter alarm goes off, the final filter will as well.
This is because the pre-filter low side and the final filter high are piped together. This shouldn't happen in theory, but there may be a leak in the diaphram of one DP switch allowing pressure to flow from the hig side to low side of the prefilter switch
The switches are both set correctly. If a pre filter and final filter alarms are enabled on the front end, note that the prefilter may only be dirty and not both filters
Matthew Ernst
Matthew Ernst 6/21/2017 Matthew Ernst Notes for record X
38 8/28/2017 Closed AHU-8-1 AHU-8-1: No airflow reading (0 CFM) when the fans are running below 50% and a negative airflow reading when at full flow on Siemens control system.
The AHU is reading what appears to be accurately at its control panel.
Siemens is confirgued for reading a 4-20mA signal and interpreting that to read 0 - 15,000 cfm
Reccomend having the AHU startup tech to check the control point from the panel and verify it is sending out what Siemens is expecting
Matthew Ernst
Matthew Ernst This issue was resolved by the manufacturer and
Siemens per Rikki on 11/3/2017
X
39 8/28/2017 Closed AHU-8-1 1/31/2018 AHU-8-1: Glycol heat recovery piping not installed (to be completed with later phases)
AHU-8-1 heat recovery valve to be tested when installed.
Heat recovery system to be tested when whole system is installed
Matthew Ernst
Matthew Ernst 1/31/2018 Matthew Ernst 11.24.17 The heat recovery system will be tested together upon completion
1.30.18: BMcD tested and verified operation of the heat recovery system
40 8/28/2017 Closed AHU-8-1 AHU-8-1: The pre-filter high side probe tubing needs to be tied into the filter rack probe
Cut the tubing and terminate on filter rack.
Matthew Ernst
Robert Blake 9/1/2017 Robert Blake Corrected 9.1.17 X
41 8/28/2017 Closed AHU-8-1 1/31/2018 AHU-8-1: Safety shutdown switch ont installed 8.28.17. To be installed with AHU-8-6.
The DDC control panel needs room, once the devices for the old AHU are removed, the switch will be installed
To be installed at a later date
Matthew Ernst
Matthew Ernst 1/31/2018 Matthew Ernst 11.24.17 BMcD to retest upon completion
1.31.18 BMcD retested
and verified operation
X
42 9/1/2017 Closed Lab 8060 North and South Zones: When lab hoods are opened at full supply and exhaust flow, the roomd differential increases, however the general exhaust does not back off to maintain the differential setpoint. The room gets more negative
Recommend to add additional programming to back off general exhaust in full cooling condition
Matthew Ernst
Matthew Ernst 9/10/2017 Matthew Ernst This does not affect safety of rooms and is recommended to be looked into but not required for completion
X
43 8/28/2017 Closed AHU-8-1 12/22/2017 AHU-8-1: Preheat valve is not wired as of 8.28.17
To be tested at a later date Matthew Ernst
Matthew Ernst 12/22/2017 Siemens 11.24.17 BMcD to retest upon completion
12/22/2017: Valve is wired and has been tested.
44 8/28/2017 Closed AHU-8-1 1/31/2018 AHU-8-1: Steam humidification valve not installed 8.28.17
To be tested in a later phase Matthew Ernst
Matthew Ernst 11.24.17 BMcD to retest upon completion
1.31.18 BMcD tested the
sequence and function ofthe valve without steam. No testing will be completed with steam humidification per meeting on 1.30.18
45 9/1/2017 Closed AHU-8-1 Lab 8060: Room pressure sensor was set up with the wrong range at the lab was reading 0.5"wc positive when it was actually 0.01"wc positive.
This was corrected Matthew Ernst
Siemens 9/1/2017 Siemens X
46 9/1/2017 Closed Lab 8060 Notes: If the North and South Zones are set to a 300 CFM differential, the lab to hallway differential pressure is -0.006"wc. If the differential setpoint is increased to 600 CFM, the lab to hallway differential pressure is -
.015"wc.
The room differential setpoint is…