10_-_addendum_1.pdf

PDF 41 KB Posted

Attached to
Buffalo- Jackson USBC Renovation Federal contract opportunity
Solicitation number
47PC1118B0002
Issued by
General Services Administration Public Buildings Service Region 2

About this file

specification addendum

View the file

Other files for this federal contract opportunity

Other files attached to Buffalo- Jackson USBC Renovation, newest first.
File Type Posted
SF_1442.pdf PDF
Answers_to_questions.pdf PDF
SF_30.pdf PDF
Solicitation_Amendment_47PC1118B0002_0002.pdf PDF
10_-_SF_30.pdf PDF
10_-_Jackson_Pre_Bid_Agenda__11-7-17.pdf PDF
10_-_site_visit_sign_in.pdf PDF
Solicitation_Document.pdf PDF
https://www.fbo.gov/index?s=opportunity&mode=form&id=63d4c16b720feb3c07b1a836d0a05c82&tab=core&_cview=1 —
Solicitation_Agreement.pdf PDF
SF_1442.pdf PDF
Document_Security_Notice.pdf PDF
GSA_527.pdf PDF
Reps_and_Certs.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

Project: Robert H. Jackson USBC Build Out Federal Office Building and US Courthouse Buffalo, NY 14202

GSA Project: N1071261 [NKB#12245.33]

A/E Contract No.: GS-02P-10-PW-D-0013

Date of Issue: November 2, 2017

Attachments: None

TO ALL BIDDERS: The following additions, deletions, and/or changes or clarifications to the drawings, specifications, and bidding documents for this project, shall become and are hereby made part of the Contract Documents. They change the original documents only in the manner and to the extent stated. Each bidder shall acknowledge receipt of this ADDENDUM in the appropriate location on the bid proposal form.

This ADDENDUM consists of one (1) page, including this page and no attachments.

All requirements of the original Specifications and Drawings and previous Addendum, if applicable, shall remain in force except as noted by this ADDENDUM.

THE PURPOSE OF THIS ADDENDUM IS TO CHANGE THE FOLLOWING ITEMS:

SPECIFICATIONS

1.1 SECTION 011000, SUMMARY: DELETE para. 1.7a and b and replace with the following:

“7. Sequence of work is in one (1) Phase, consisting of approximately 24,353 SF of total floor area. “

DRAWINGS

1.2 DRAWING G-002, PHASING & STAGING PLAN: Detail 4 – DELETE Phasing Notes including

Phasing Legend – there will only be one phase of work. Note: 2nd Floor Jury Assembly Room “Swing Space” will NOT be in the scope of work.

1.3 DRAWING AE411, LOADING DOCK & MAIL ROOM PLANS: Keyed Note #14 ADD new sentence as follows: “New finishes outside the Mailroom in the corridor to match existing adjacent finishes.”

1.4 DRAWING AE424, 2nd FLOOR CONSTRUCTION PLANS – DELETE work indicated to occur at Door

260 and Wall Type 920a noted as “Temporary Wall and Transaction Counter” shown in Jury Assembly / Swing Space Room 260.

1.5 DRAWING AE427, 2nd FLOOR TEMPORARY SPACE – DELETE this drawing from the bid documents.

1.6 DRAWING AE520, 2nd FLOOR DETAILS - DELETE Detail # 7.

1.7 DRAWING AE820, 2nd FLOOR INTERIOR ELEVATIONS – DELETE Detail #6.

END OF ADDENDUM NO. 1