10_-_addendum_1.pdf
PDF 41 KB Posted
- Attached to
- Buffalo- Jackson USBC Renovation Federal contract opportunity
- Solicitation number
- 47PC1118B0002
About this file
specification addendum
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF_1442.pdf | ||
| Answers_to_questions.pdf | ||
| SF_30.pdf | ||
| Solicitation_Amendment_47PC1118B0002_0002.pdf | ||
| 10_-_SF_30.pdf | ||
| 10_-_Jackson_Pre_Bid_Agenda__11-7-17.pdf | ||
| 10_-_site_visit_sign_in.pdf | ||
| Solicitation_Document.pdf | ||
| https://www.fbo.gov/index?s=opportunity&mode=form&id=63d4c16b720feb3c07b1a836d0a05c82&tab=core&_cview=1 | — | |
| Solicitation_Agreement.pdf | ||
| SF_1442.pdf | ||
| Document_Security_Notice.pdf | ||
| GSA_527.pdf | ||
| Reps_and_Certs.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 1
Project: Robert H. Jackson USBC Build Out Federal Office Building and US Courthouse Buffalo, NY 14202
GSA Project: N1071261 [NKB#12245.33]
A/E Contract No.: GS-02P-10-PW-D-0013
Date of Issue: November 2, 2017
Attachments: None
TO ALL BIDDERS: The following additions, deletions, and/or changes or clarifications to the drawings, specifications, and bidding documents for this project, shall become and are hereby made part of the Contract Documents. They change the original documents only in the manner and to the extent stated. Each bidder shall acknowledge receipt of this ADDENDUM in the appropriate location on the bid proposal form.
This ADDENDUM consists of one (1) page, including this page and no attachments.
All requirements of the original Specifications and Drawings and previous Addendum, if applicable, shall remain in force except as noted by this ADDENDUM.
THE PURPOSE OF THIS ADDENDUM IS TO CHANGE THE FOLLOWING ITEMS:
SPECIFICATIONS
1.1 SECTION 011000, SUMMARY: DELETE para. 1.7a and b and replace with the following:
“7. Sequence of work is in one (1) Phase, consisting of approximately 24,353 SF of total floor area. “
DRAWINGS
1.2 DRAWING G-002, PHASING & STAGING PLAN: Detail 4 – DELETE Phasing Notes including
Phasing Legend – there will only be one phase of work. Note: 2nd Floor Jury Assembly Room “Swing Space” will NOT be in the scope of work.
1.3 DRAWING AE411, LOADING DOCK & MAIL ROOM PLANS: Keyed Note #14 ADD new sentence as follows: “New finishes outside the Mailroom in the corridor to match existing adjacent finishes.”
1.4 DRAWING AE424, 2nd FLOOR CONSTRUCTION PLANS – DELETE work indicated to occur at Door
260 and Wall Type 920a noted as “Temporary Wall and Transaction Counter” shown in Jury Assembly / Swing Space Room 260.
1.5 DRAWING AE427, 2nd FLOOR TEMPORARY SPACE – DELETE this drawing from the bid documents.
1.6 DRAWING AE520, 2nd FLOOR DETAILS - DELETE Detail # 7.
1.7 DRAWING AE820, 2nd FLOOR INTERIOR ELEVATIONS – DELETE Detail #6.
END OF ADDENDUM NO. 1
END OF ADDENDUM NO. 1