Question Response
Does this project require any additional clearances other than HSPD-12 included in solicitation?
They need HSPD-12 and they will need to be cleared by the agency as well. All contractors will need to submit additional documentation which will be provided at award that will need to be completed by all personnel requiring access.
The encrypted PDF's provided of the drawings will not open in our estimating software(On Screen). Is it possible for you to send the PDF's not encrypted so that we can do take offs in our software.
No, we cannot send unecrypted drawings.
Please advice if general contractor is allowed to email/distribute bid documents ( drawings, specs, etc ) to their various sub-contractor's.
Yes, as long as they complete the Form B for each contractor and then submit the documents with their offer so we know who received the drawings. The GC also needs to be responsible to collect the drawings at the end of the procurement from all subs.
4 Can the due date be extended by two (2) weeks?
There is no time extension planned at this time for the proposal due date
Please specify the removal of furniture (e.g. the number of desks, chairs, cabinets, shelving, credenzas, office equipment, etc. to be removed) Inventory list provided.
6 What is the extent of the concrete-filled floor cells?
Where partition type A6 crosses a cable distribution cell or trench with metal plate cover, fill the cell or trench with concrete to minimum 6" from either face of partition.
7 Can there be another walkthrough? Not at this time 8 Will there be photographs provided for the space? Yes, uploaded to FBO
Please provide the name and contact information for the Fire Alarm and BMS vendor.
Fire Alarm is Honeywell Michael Gerbasio, Phone: (201) 208-9123, michael.gerbasio@honeywell.com and the BMS Vendor is Siemens (Tele: 1-800-743-6367).
Drawing #A-224, Finish Floor Plan – Level 23 notes indicate “High density files to be installed in this room. Floor finish to be installed over high density filing rails.” Please clarify.
Refer to drawing A-731, Addendum #2, attached to this RFI response for floor finish detail at high-density filing rails.
The revised SF 1442 with pricing sheets has at the end of the pricing sheet: ‘Total Evaluated Offer – Sum of Lump Sum Base Bid Plus all Alternates & Options’. However, there are many cases in the bid form where items are mutually exclusive. Examples include that only Alternate 1C or Alternate 2C could be chosen, or if Option 3 is taken Options 1and 2 are precluded. What is required for the total evaluated offer line or is that summation line to be struck?
Contractor shall provide a total cost for all line items listed on the pricing sheet (i.e. base cost + all options + all alternates). This will provide a total offer price that will be evaluated.
Sheet G-001 lists plan sheets M-401, M-502, E-001, E-002, and E- 300 which were not included in the plan set. Are these references to be struck or will those sheets be provided?
Drawings M-401 & M-502 are not in the last issued set. M-401 (Schedule) is now M-501 (Schedule) & M-502 (Details) now been updated to M-600 series. E-001 is provided in Addendum #2 and E- 002 was provided in the bid package. E-300 is not provided, however, the information is distributed across E-301, E-302 and E-
303. Drawing list will be updated for conformed construction set.
1. Section 01 14 00 Paragraph 1.2.c.7 states that the loading dock is available for deliveries between 7:30AM and 3:30PM on weekdays, and 8:00 AM to 12:00PM on Saturdays. Given the volume of work to be performed can delivery hours be extended?
Yes, but notice needs to be provided at least 5 working days in advance.
During the site visit it was stated that the loading dock would be available to access with a dumpster to remove materials during the demolition that is required during unoccupied hours. Will the loading dock be available to allow for demolition debris removal off hours?
Yes, but notice needs to be provided at least 5 working days in advance.
Plans were provided for asbestos abatement in the plan set but no specification was included. Will an asbestos abatement specification be provided?
See attached for asbestos specifications.
16 No asbestos report was provided. Will a report be provided?
A copy of Limited Hazmat Survey Report is attached. This report is for information purposes only.
Do any of the safes that are scheduled to be removed, contain asbestos? Per the tenant agency there is no ACM in the safes.
No information was provided with regard to PCBs or Mercury. Are any quantities to be assumed to be removed with this project for PCBs or Mercury, and if so, in what products?
A copy of Hazardous and Universal Waste Specification is attached.
19 Does any paint in the work area contain lead? For information, refer to Limited Hazmat Survey Report.
Is there any other universal waste that is to be disposed of under this contract?
A copy of Hazardous and Universal Waste Specification is attached.
COILING COUNTER DOORS:1) Counter doors are not noted on the door schedules. I have located two (2) doors from the elevations. 8/A601 and 6/A603. Please provide the quantity, locations-room #’s , and sizes of the rough openings for all of the coiling counter doors.
This RFI is generating reduntant information that is contained in the documents. Per detail 6/A-801, the roller shutters are mounted to the underside of the ceiling to a height of 2'-10" off the floor.
There is (1) located in workroom 6.30 27-170, (1) in workroom 5.35 27-171, 6'-0" wide as indicated in plan. The dimensions of the pass through window in room 27-173 is 6'-0" wide. The dimensions of the pass through window in room 29-205 is 4'-0" wide.
COILING COUNTER DOORS:2) What are the working hours and delivery/loading hours for this trade? Refer to Section 01 14 00 Paragraph 1.2.c.7 for delivery hours
23 MECHANICAL:1) Is a walkthrough of the site available? There will be no additional site visits scheduled.
MECHANICAL:2) Please provide a Division 23 mechanical specification.
Project specifications were included with the submission of contract documents Issued for Bid and included in the FBO posting
MECHANICAL:3) Please provide a written scope of work if available.
Scope of work is defined per the contract documents. Contractor should familiarize themselves with the extent of work per the contract documents issued for Bid.
MECHANICAL:4) Please clarify requirements for Testing and Balancing. Are pre-readings available?
Project specifications were included with the submission of contract documents Issued for Bid and included in the FBO posting
MECHANICAL:5) Are existing ducts to be cleaned? If so, please clarify scope Cleaning of existing ductwork is not within current scope of work.
28 MECHANICAL:6) Are building rules and regulations available? Refer to Division 1 of the spec section 29 MECHANICAL:7) Is badging required for this project? Yes
MECHANICAL:8) Are there phases associated with the project? If so, please provide a phasing plan. Yes. The phasing is spelled out in the bid sheet
31 MECHANICAL:9) Will this project will be all on straight time? Yes, except for hot work 32 MECHANICAL:10) What are the normal working hours? 7:30AM - 5:00PM
MECHANICAL:11) Is a schedule available? What is the duration of the project? Milestone dates?
Schedule to be provided by the GC, contract states number of days for each phase
MECHANICAL:12) Please clarify logistics and specifically site access? Please clarify the rigging / delivery path.
Refer to Section 01 14 00 Paragraph 1.2.c.7 for delivery hours, GC to determine rigging/delivery path
MECHANICAL:13) Please confirm if there is a controls contractor on-site. If so, please provide contact information. The base building controls vendor is Siemens.
MECHANICAL:14) Please provide a controls sequence of operations.
Project specifications were included with the submission of contract documents Issued for Bid and included in the FBO posting
MECHANICAL:15) M-223.00: Reference note 6 “Add alternate #2 – Replacement of perimeter induction units. . .” Please provide a mechanical schedule for the perimeter induction units.
Schedule for the existing induction units has been added to the mechanical schedules for reference.
MECHANICAL:16) M-603.00: This drawing did not load properly. It states missing or invalid reference over two of the details, Di-electric break detail and Duct penetration at secure wall types A6A & A6B. Please provide a new version of this drawings with said details included. Drawings were included on the FBO posting.
MECHANICAL:17) Please confirm BIM is not required on this project. Not required
MECHANICAL:18) Please advise if mechanical/HVAC as-builts are available. No
MECHANICAL:19) Will CAD backgrounds be made available for coordination drawings?
Drawings will be provided pending signed electronic use disclaimer.
1) Please advice who is the current DDC control systems maintenance contractor for HVAC for the project area.
HVAC DDC maintenance contractor is Siemens (Tele: 1-800-743- 6367).
2) Please advice who is the current fire alarm maintenance contractor for the project area.
Michael Gerbasio, Phone: (201) 208-9123, michael.gerbasio@honeywell.com
3) Please advice who is the current electronic security maintenance contractor for the project area. The Tenant Agency maintains their own security equipment.
4) Please advice if government escorts will be required to assist contractor daily to get in and out of the various project floor areas and during hauling of construction waste removal work up to the dumpster located in loading dock area. Yes
5) Please advice if a dedicated elevator will be provided for the contractor as work is in various floors. No
6) Please advice if contractor has to pay any charges for government security personnel’s if the work is performed after regular work hours or weekends. No
7) Please advice if there is any phasing required for the new construction and asbestos abatement work as work is being performed in multiple floors. Refer to the bid sheet and documents for phasing information
8) Please clarify if any fire watch is required during the demolition and construction of wet-pipe sprinkler system and fire alarm work.
Fire watch is typically required during the demolition and construction of the wet-pipe sprinkler system and fire alarm work.
9) As decrypted drawings are not provided we are unable to use the take-off software, contractor and sub-contractors have to do the take-off work manually from all the drawings, this requires a lot more time, so requesting to extend the bid date at least by two to three more weeks. No
10) Spec section 09 51 00 page 10, para 2.7 does not provide manufacturer number for the Armstrong ceiling tile type ACT02, without this number it is difficult to procure quote from thedealers. Manufacturer # 3250
Same thing no number or manufacturer for resilient flooring type RF02 indicated in section 09 65 00 page 5, para 2.4A. RF02 is not used
11) Please provide a detailed list and quantities of all the furniture, shelving’s, file cabinets, etc. which is to be removed and carted out by the contractor. Refer to inventory list provided
54 12) There is no specification section for asbestos abatement work. See attached for asbestos specifications.
13) Drawing A-711, in door schedule there is a material which states “SCL” please advice what is the full form of SCL? Structural Composite Lumber door
14) Does contractor have to submit new calculations for wet-pipe sprinkler work for each floor?
Hydraulic calculations are required with sprinkler shop drawings for each floor. The note on sprinkler drawings referring to the NFPA 13 pipe schedule is an error and shall be disregarded. Pipe size shall be based on hydraulic calculations. The demand area may not be reduced below 1,500 square feet when quick response sprinklers are provided, as indicated in PBS-P100
15) Spec section 01 10 00 page 1 para 1.2B states “The Work includes removal and disposal of existing improvements on the 16th through 21st floors; new fire sprinkler piping and fire alarm systems; new mechanical and electrical distribution systems; new partitions, openings, finishes, and built-in furnishings, including cabinetwork with new sinks, and new equipment”. – Please advice if there is any work on these floors 16 to 21?
SOM will update the specification section to refer to the accurate project parameters for floors 23, 24, 27 and 29. There is no wor on floors 16-21.
16) Please advice if temporary floor protection is required in the outside corridors of each floor’s project area. Does contractor has to daily remove this temporary floor protection? ( say Masonite ) or once protected it can be removed at the completion of the project.
Temporary floor protection is required and contractor can leave the masonite down during the course of construction. However, the contractor shall be responsible for insuring the hallways remain clean throughout the course of construction.
17) Spec section 01 50 00 page 6, para 3.3B states to “Provide insulated, weather-tight temporary offices of sufficient size to accommodate office personnel at the Project site. Include space for meetings” --- Please advice if a meeting space will be provided by government inside the building for contractor’s temporary field office or does contractor have to rent a field office trailer?
The Government will attempt to provide office space within the building to accommodate the Contractor's field office. There is no expectation for the Contractor to provide a site trailer.
18) Spec section 01 50 00 page 8, para 3.4F states to use “Reusable Temporary Partitions” to separate areas occupied by tenants from fumes and noise. --- Please identify the areas on drawings where these partitions are required to be use.
This RFI refers to means and methods. The site will be partially occupied and Contractor is expected to ensure adequate protection to occupants during the duration of construction.
19) Please advice how many full time key personnel’s are required to supervise this project? Is a full time Project Manager and Project Coordinator (Construction Superintendent) sufficient? Or is there requirement for any other full time or part time personnel to supervise on this project.
Staffing is determined by the GC. However, you have to at least provide the key personnel required in the RFP.
20) The existing furniture, shelving’s, file cabinets, etc has to be moved by contractor out of site, please advice which demolition labor rate Tier A or Tier B has to be used for this moving work?
The contractor is responsible for selecting the applicable wage rate and paying the proper wages to the employee for the removal of furniture, shelving, file cabinets, etc.
21) To review all the drawings, specifications and bid documents we and our subs need more time, can agency please extend the RFI submission date by at least one more week. No
22) Spec section 09 72 00 page 4 para 2.3 indicates wall covering type “WCV01” – but this wall covering could not be found in any of the rooms in finish schedule dwg A-800. Please advice.
This RFI is generating reduntant information that is contained in the documents. Per keynote #1 on the finish floor plans, WCV01 is to be priced as an alternate to the glass panels as indicated in the plans
23) Spec section 09 77 23 page 9, para 2.4 indicates fabric wrapped panel type “FWP01”. -- but this panel could not be found in any of the rooms in finish schedule dwg A-800. Please advice. FWP01 is not used.
24) Spec section 09 30 00 page 11, para 2.7 indicates tile type CT02, but does not specify any manufacturer name, no. and size.
Please advice. CT02 is not used
25) Please advice if any testing and inspection is required by third party for new construction materials and work performed by contractor.
NYC DOB is not the Authority Having Jurisdiction. However, third-party testing must be performed. Tests such as fireproofing, sprinklers, fire alarm and other life safety measure are required.
Contractor to schedule appropriately.
26) Drawing A-129 general note no.3 states Blinds to be provided at all windows, there are no specifications for blinds, neither is any detail provided on drawing.
All windows to receive horizontal metal blinds. Levolor Riviera 1" metal blinds, to be installed on inside of window with a painted metal fascia.
27) The legend on construction plans indicate glass partition and drywall partitions, but it is very difficult to differentiate between the two.
All glass partitions are tagged with the appropriate wall tag. Single glazed demountable partitions are tagged with A5G and double glazed partitions are tagged with A5D
28) Drawing A-123 note no. 7 states to refer to 4/A-702, but this detail 4 is not found on drawing A-702. Number is incorrect. Please refer to A6C/A-702
29) Please confirm the existing/removed fire proofing does not contain asbestos.
Based on our review of prior asbestos reports, ACM fireproofing was abated and the floors were re-sprayed with non-ACM fireproofing. Remnants/debris from original ACM fireproofing may exist in wet chases and within cinder block walls. Such locations are identified on abatement plans and specifications.
30) Drawing A-054 key note no.3 states to remove finish at partition only – Please advice what kind of finish is to be removed. Finish on partition, if any, is to be verified in field.
31) Demolition plans indicate to demolish walls, please clarify if some of these walls are masonry too? If there are any masonry walls to be demolished, then please identify on drawings.
Refer to ASK-01A-D attached for locations of masonry and gyp walls.
32) Interior elevations on dwg A-601 indicates to provide TV and monitors, please advice if contractor has to furnish and install these TV’s and monitor’s. No
33) Demo dwg A-054 does not indicate any work in annex corridor, but on construction plan A-129 it indicates new work ( area is not shaded ) Please clarify. Also advice what new work is to be done in this corridors.
There is no demolition in the corridors. Per keynote 3 on the finish floor plan, the corridor is to be painted to match existing color.
34) Besides work on 23, 24, 27 and 29 floors there is additional work of spray on fireproofing on 28th floor ( dwg A-528 ) and 30th floor ( dwg A-530 ) Also there is work of asbestos abatement on 26th floor ( dwg H-104 ) and 28th floor ( dwg H-106 ) – Please advice if this work of 26, 28 and 30th floor has to be considered in the base bid? 35) Doors 29-38, 29-39, 29-40, 29-41 list no door material, no frame information, no hardware, and no door comments. Are these doors existing to remain or are they new doors? If they are new doors, which hardware sets are they assigned?
All abatement activites as identified on H-Series Plans (H-101 thru H-107) is part of the base bid. Based on our review of prior asbestos reports, ACM fireproofing was abated on the 28th floor and no ACM sprayed-on fireproofing exist in the floor areas identified on drawing A-528 to be impacted.The impacted areas of 30th floor identified on drawing A-530 are referred to ANNEX section. Non-ACM fireproofing exist in the ANNEX building. Yes, the work on the 26th and 28th floor should be identified as base bid
36) Door hardware group 016 lists a “Sargent 8415-107 group 1 lock”. This appears to be a Sargent and Greenleaf dial combination lock typically used in safes. Please confirm if this lock should be in this hardware group or if it is a mistake. This lock is required by the tenant
78 1. What is the extent of ceramic tile on the finish schedule?
Per sheet A-602, the ceramic tile is on the backsplash of the pantries. Tile in vestibules of bathrooms 29-217 and 29-221 must match adjacent, existing tile.
1) There are no specs for signage but there is some for glass film under the partitions section. So from what I can glean from the drawings is that the private offices (and a handful of conference rooms) get the room info in vinyl only (sign type 2) in combination with the Fasara privacy film, and the balance of the rooms (where indicated) get a sign type 1. Is that correct?
All glass office fronts (offices, conference rooms, etc) receive the distraction band film per elevatioin 5/A-603 and the film specifications.
The signage plans indicate which rooms receive which signage type
80 2) My concern is that this setup is not code compliant.
The tenant is the authority having jurisdiction and has approved this layout.
3) It is not clear to me which if any other rooms are glass front and get the distraction graphics as well. I don’t see it on the finish details and the only one called out specifically in the elevations is the break room on Floor 23 (see drawing 2, A-603). Problem is that room is supposed to get a sign type 1 which can’t be mounted on glass. Drawing 6,A-602 calls out a pantry wall on Flr 27 but there is no pantry, just a break room, so I’m operating on the assumption that that is what is intended.
This RFI is generating reduntant information that is contained in the documents. All glass office fronts (offices, conference rooms, etc) receive the distraction band film per elevatioin 5/A-603 and the film specifications. Drawing 6/A-602 is an elevation in room 27-163, as indicated on sheet A-127. Per the room signage schedule, room 27-163 is to receive sign type 02.
As per keyed note S6A on drawings E-124, we are to provide panel RP-CP. This note is shown in room 24-113 and room 24-132.
Please confirm that panel RP-CP referenced by this note is actually panel RP24SCIF-A shown in room 24-113 and panel RP-24SCIF-B (sect I & II) in room 24-132.
Yes. Panel names were revised as per GSA reviewer request. E- 124 has been reissued for clarification.
RE: “Notes 24th floor” on drawing E-124: a. As per note 10, installation of all floor mounted telephone, data and power outlets shall not be permitted. On the other hand there are (3) poke-thru’s are shown in room 24-129. Please advise. b. As per note 12, “Contractor as part of its contract shall relocate all existing penetrations thru floor or ceiling slabs”. Please provide quantities, locations and types of existing floor and / or ceiling slab penetrations or provide an allowance for such work. Otherwise it is impossible to put dollar value to such work. c. As per note 26, we are required to provide dedicated 2” conduit from the point of entry into the building and terminating at a designated location at tenant space. Please provide locations, drawings and layout of point of entry into the building and a designated location at tenant space.
Otherwise it is impossible to put dollar value to such work. d. As per note 28.A, we are required to provide dedicated 2” conduit from the roof of the building into a designated location at tenant space.
Please provide locations, drawings and layout of roof of the building and a designated location at tenant space. Otherwise it is impossible to put dollar value to such work. e. As per Lighting Note J, lighting fixtures in open spaces shall run thru Lighting control system on 25th floor. Please clarify the following: i. Location of lighting control system on 25th floor ii. On the other hand Detail LC1 on drawing E401 specifies standalone lighting control system for 24th floor. Please clarify which is correct. f. As per Lighting note K, we are required to provide ¾” conduit for CCTV cameras at any entrance doors. Also we are required to provide 120V circuits to each location. Neither CCTV cameras nor 120V branch circuit are shown on floor plans. Please provide drawing with quantities and locations of CCTV cameras and 120V branch circuits for them.
Answer a)The floor outlets shall be flush mounted in the raised access floor in training room 24-129, conduit shall run between the access floor and the slab to the nearest wall. All data, telephone and power outlets required in the floor will be run from the ceiling down the wall and between access floor and concrete slab to final location. Any area not provided with raised access flooring, that requires a floor mounted data, telephone and power outlet this would be accomplished by running down the wall and chisel through the concrete to final location. Answer b) No foreign systems serving other spaces are permitted in space called "Room 14". Existing incidental systems serving other floors but passing through the "Room 14 area" shall be relocated as a part of this contract. Provide allowance for incidental work as described in the revised note. 25 penetrations. No detail information is available.
Allowance only will only be used when conduit or circuit are to be relocated. Answer c) Refer to revised drawing E-124, disregard note. Answer d) Refer to revised drawing E-124 Answer e) Refer to revised drawing E-124 Answer, disregard note. Answer f) Program requirements note: CCTV cameras will be installed by the tenant outside any entrance door to the tenant space. 3/4"C conduit with pull string and 4"x4" termination boxes for CCTV cameras and electrical power shall be provided. Refer to SE-XXX drawing series for required camera locations. Where designated, electrical power shall be provided.
Keyed note S1 on drawings E-123, E-124, E-127 & E-129 calls to extend to existing Access Control System. Please clarify the following: a. Please provide locations of existing Access Control System on each floor. b. Please provide details on how should we extend to existing ACS i. Quantity and size of conduit required. ii.
Types and quantities of wires required. c. If we are responsible for cabling and tie in into existing Access Control system, please provide contact info for Building Security Vendor.
Refer to detail 1 on E-403. Electrical Contractor is responsible for Access Control rough in. All wiring and devices will be installed by builing/tenant security vendor. GSA to confirm Direction.
Details LC2 on drawing E-402 & detail XIII on drawing E-404 looks very similar. Please advise which detail should take precedence. Use details LC2 on drawing E-402.
With reference to Detail XIV on drawing E-404 and Detail XIX on drawing E-405 we could not find any Fire Smoke dampers on floor plans. Please advise where FSD’s are required. There are no new fire smoke dampers installed in tenant space.
With reference to Detail XV on drawing E-404 we could not find any Emergency Lighting Transfer Relays on floor plans. Please advise where they are required.
Detail is only applicable for cases where lighting fixtures are fed from normal power circuit and transfer to emergency circuits is required at the panel. In our case details describe mini inverter allowing transfer from normal power to emergency battery power.
With reference to Detail XVII on drawing E-404 we could not find any Lighting Contactors and/or Time clocks on floor plans. Please advise where they are required.
Detail XVII on drawing E-404 describes lighting fixtures controlled via contactor as well as lighting control relay panel (Open office spaces).
1. As per Note 8 on drawing E023 “Any core drilling or future utility penetrations for 23rd floor space are not allowed”. On the other hand multiple recessed poke-thru are shown on 23rd and 24th floor electrical and architectural power plans. Please clarify.
In general no core drilling is allowed in "Room 14" areas (23rd and 24th floors). Floor mounted telephone, electrical or data outlets shall not be permitted. All power shall be fed from wall or overhead. The GSA project manager will be the final Authority and will provide the direction in the field. In other tenant spaces the preferred option is to bring power to the furniture clusters by utilizing column or walls mounted junction boxes. If this is not feasible, another option is to use overhead poles or to partially reuse the exisiting in slab cell system for power connection and overhead poles for low voltage system. In this case the overhead conduit for power shall be routed to the closest wall and extended to the cell system. Core drilling of the slab and running conduit through another tenant space will not be permitted.
2. Please confirm that all telephone and data cabling, equipment and terminations will be provided by GSA under separate contract and we are only responsible for cable tray, boxes, stub ups and empty conduit as shown on E-series drawings.
Electrical contractor is responsible for raceway for telephone/data/security cabling infrastructure only.
3. Please confirm that all Security Systems (Access Control System, Intercom System and CCTV system) cabling, equipment and terminations will be provided by under separate contract and we are only responsible for cable tray, boxes, stub ups and empty conduit as shown on E-series drawings.
Electrical contractor to provide all raceways, cables and equipment as indicated on SE-xxx series drawings.
92 4. Drawings E001 and E002 are missing from electrical set. E-001 & E-002 are included and uploaded to FBO.
5. There is no specifications for lighting fixture type FC that is shown in equipment rooms 23-202, 24-113, and 24-132
High output LED luminaire for pendant, surface recessed or in-wall installation. Basis of design cat. No.: VIA5PD_HLO-LED-80-500- 3000k-LENGTH_UNIV-D1-*-*-AL as manufactured by LumenWerx or approved equal.
6. Lighting inverters are shown on E-227 in room 27-195 and E-229 in room 29-194. We cannot find any specifications for those inverters.
Disregard keynote "L5" on E229. As per note #2 on E-402 all fixtures marked with "EM" & "EM/NL" shall be provided with 90 minute NYC approved battery back-up. For LED lighting fixtures mini-inverters compatible with specified lighting fixtures to be used.
7. As per note 2 under “Lighting fixture List” on drawing E-402, all EM and EM/NL designated fixtures to be provided with 90 min battery backups. On the other hand as per note L5 on E-299 all EM and EM/NL designated fixtures to be connected to lighting inverter.
Please clarify which statement is correct.
Both statements are correct. Base building "Emergency" power is not available for the tenant. (Tenant optional standby generator is being used in some instances, but ...) To comply with code battery backup (90 minutes) is required to be provided for lighting fixtures.
All lighting fixtures are LED type. For LED lighting fixtures mini-inverters compatible with specified lighting fixtures to be used.
8. It is very unclear which lighting fixtures (if any) needs to be provided with 90 min battery backup. Please clarify
Lighting fixtures marked "EM" shall be provided with 90 min.
backup regardless whether these lighting fixtures are connected to "tenant generator" or not.
9. Please clarify if MC Cable is allowed for branch circuit wiring above drop ceiling and inside sheetrock walls for lighting and power. Could not find any reference in specs.
All conduits shall be as per building standard and PBS-P100 (2016). "All branch circuits shall be copper in conduit with unshared ground and neutral wire". EMT and surface mounted raceways on all peremeter wall of "Room 14" shall be used. Although Metal Clad (MC) cable is code compliant method of wiring, GSA project manager approval is required before considering this method of wiring in tenant space.
DEMOLITION:1) Please provide contact and rates for debris removal containers at loading dock. Will these containers cart and dispose ACM?
Approx $3000 for ACM 30 yard container. An approximate number is given as the cost of a ACM container goes by weight. A 30 yard container for regular construction waste is $800 per container. Century Waste Services is the hauler that is used. Waste disposal must be coordinated with our janitorial contractor, FEDCAP, even if Century is not used.
99 OPERABLE PARTITIONS:2) Please clarify supports for operable partitions.
Operable partition is constructed directly under the structural beam.
Track shall be connected directly to the building's structure through partition manufacturer's standard components and per manufacturer's recommendations.
HVAC - RFI 01 Could you please provide us with the following information regarding perimeter induction units? Unit schedule with brand and model information, Piping connection detail and balancing valve information, As- Built drawings of perimeter induction unit system.
Perimeter induction units shall be a direct replacement in kind. Plans have been revised to include schedule and additional information.
HVAC- RFI 02 According to HVAC General notes #44 in M-001.00;
all affected systems shall be rebalanced upon completion of installation. Practically water and air distribution systems in the areas that are not in scope, but supplied by the same risers, could be affected by new installations.
All affected systems within scope of work. Refer to response to RFI
Could you please identify all affected systems and provide detailed scope of work for rebalancing?
All affected systems within scope of work. Refer to response to RFI
HVAC - RFI 03 Please provide the Chilled Water pipe diameters of the risers that will be wet tapped? Existing chilled water risers are 6"
SPRINKLER - RFI 01- Please confirm that flow and pressure data for each floor riser connection point will be provided for hydraulic calculations. Contractor shall provide hydraulic calculations for each floor.
SPRINKLER - RFI 02-There are no ceiling void sprinkler heads shown on the drawings. Can you please confirm that ceiling void will not be sprinklered?
Refer to sprinkler drawings for required coverage. No additional sprinklers are expected to be required.
PLUMBING - RFI 01-According to plumbing drawings the waste water piping will be installed in the ceiling void one floor below the construction area. Please provide reflected ceiling plans for 22nd, 26th and 28th floors.
Ceiling plans on the adjoining lower floors is not available. Routing was planned per visual observation of conditions below to the extent possible. Contractor shall be required to survey associated areas on floor below to verify and confirm sanitary piping routing and installation.
107 1-1. Please provide the dimensions of the freight elevator FOB Freight - 9' x 5'8" x 8'7" (4000 lb capacity)/- Annex Freight - 9'10" x 7'2" x 10' (6000 lb capacity)
1-2. Please confirm all work and loading will be during normal working hours
Correct except for hot work. After-hours work can be arranged upon prior notice of approximately 2 weeks.
1-3. Sheet A-602 – Elevation 2,6,8,10 Tag ACC01 – Does not appear in the specification, please clarify.
Please provide Bobrick B-35903 recessed paper towel dispenser. To be mounted to meet ADA requriements, per drawings.
1-4. Sheet A-123, A-124, A-127, A-129 General Note 3. New Blinds to be Provided at all Windows, Refer to Specifications
– No Specification provided, please clarify.
All windows to receive horizontal metal blinds. Levolor Riviera 1" metal blinds, to be installed on inside of window with a painted metal fascia.
1-5. ACT 3 is called out on drawing A-424, however the finish schedule and specifications only show ACT-1 and ACT-2 please advise
Please provide Armstrong Optima 3262, 24"x96"x1" square tegular 916" tile, to be used with 6" Techzone. To be cut to size as necessary.
1-6. Please advise of locations for the recessed SCIF cab Detail 3/A-604 Please disregard detail. Not used
1-7. Detail 6 on drawing A-742 seems to be used at all perimeter columns were note 7 is called out on the floor plans. This detail is also called out on drawing A-129 Level 29 in Open area 1.29c please confirm as there is no note 7 on the 29th floor.
Detail 6/A-742 is to be used in all room 14/SWE areas.
Disregard the callout on level 29. No SWE is located on this floor.
1-8. Note 14 on the floor plans calls for ¾” plywood wall to wall, is the height of this plywood 8’? Plywood is to be installed wall to wall, floor to ceiling.
115 1-9. Is FSC certified wood required for this project? FSC certified wood is not required for this project.
1-10. What should the leg width be for the corner guards on this project? Do the perimeter columns require corner guards? Drawing A-743 detail 4 calls for a white painted corner guard, the specifications call for #4 stain brushed stainless steel please confirm which is correct. If not, the stainless steel please provide make and model for the white corner guard.
The leg width of the corner guard should be 3 1/2", white powder coated 18 ga stainless steel.
1-11. Will shop drawings be required for interior partitions and ceilings or will standard product data submittals be acceptable?
Per the specifications, shop drawings will be required for control joint locations, 1-12. ACT 1 is calling for a 2x2 TechZone the layout that is shown on the drawings shows a 6” x 2’ tile with a 6” tee where there are no linear lights, this tile would be a custom/field cut since the standard tile is 6” x 4’ tile #1403.
Please confirm that the intent is to use the 6” tees and the cut 6” x 2’ tiles as shown or if the 6” x 4’ tile should be figured in a layout similar to the image below.
ACT01 is a standard 24"x24" Armstrong tile to be used with a STANDARD 6" Techzone panel, that runs in 24" increments, per the plans. Refer to Armstrong installation documentation for mor information.
1-13. Please provide the spec for the existing induction units to be replaced.
Perimeter induction units shall be a direct replacement in kind. Plans have been revised to include schedule and additional information.
1-14. Section 08 80 00 – GL21 – GL22 – GL24 listed but cannot locate on plans, please clarify.
Per the specifications, GL21 is the glass pertaining to the office front system. GL22 is not used. GL24 to be provided at doors indicated as type 1W
1-15. Section 09 77 23 – Fabric Wrapped Panels – Not found on plan, please clarify. Disregard. Fabric wrapped panels not used
1-16. Section 09 72 00 – WCV01 is listed but cannot locate on plans, please clarify.
This RFI is generating reduntant information that is contained in the documents. Please refer to the finish plans for locations of WCV01. Also, refer to keynote #1 on finish floor plans
37) Please identify on all drawings which are the areas/rooms of Add Option no.1 - 23 floor area A.
This RFI is generating reduntant information that is contained in the documents. Per the construction floor plans, the options are indicated with a dark dashed line and annotation at the top of the drawings. 23A indicates non SCIF areas on the 23rd floor
38) Please identify on all drawings which are the areas/rooms of Add Option no.1 - 23 floor area B.
This RFI is generating reduntant information that is contained in the documents. Per the construction floor plans, the options are indicated with a dark dashed line and annotation at the top of the drawings. 23B indicates SCIF areas on the 23rd floor
39) Drawing A-051, in the elevator lobby it calls for demo note no.12 which states drywall to be removed from side of wall, existing studs to remain. On new construction plan drawing A-123, the same area has wall type A4 which is a drywall with both side gypsum board, please clarify if this new wall type A4 is correct, as the existing elevator lobby should have existing masonry walls.
Contractor to verify exact condition in field. Complete A4 wall to be provided in front of masonry walls if that is existing condition.
40) Section 019113 ‘General Commissioning Requirements’ is listed in table of contents, but these section is missing from the spec book. Please disregard. Spec division is not required.
41) What is the individual time limit to complete the work of Alternates 1A, 2A, 1B, 2B, 1C, 2C, 1D, 2D, 1E and 2E.
Shall be done during the period of performance stated in the contract documents.
42) All asbestos abatement drawings have note no.8 which states “A 24 hour fire-watch in accordance with FDNY rules and regulations (FC1404.5 Fire Watch) shall be instituted upon the removal of fire-resistance rated spray-on fire-proofing and shall be maintained until all spray-on fire-proofing is restored to code compliant conditions and verified with A-TR1 inspection and certification. The fire watch shall be provided by individual holding a certificate of fitness as a fire guard to perform constant patrols and watch for the occurrence of fire” ---- Please confirm this requirement of 24 hour fire watch personnel is correct?
GSA accepts requirements of NFPA 241 as an alternative to New York City requirements for a fire watch. The entire tenant space will be unoccupied, and free of combustible materials, during application of SFRM. If there are any combustible materials, or storage areas, in the core during the period, the core must be separated from the tenant space with fire-rated gypsum board partitions with fire doors are openings. In accordance with Section
7.1.2 of NFPA 241, the contractor shall submit a plan to maintain sprinkler protection to the maximum extent practicable during demolition, and to expedite provision of sprinkler protection during construction. Current sprinkler drops may be turned up, sprigs may be added, and upright sprinklers installed for temporary protection.
Turning pipe down and replacing uprights with pendent heads in their final position shall be coordinated with installation of ceiling tiles. Additional control valves and flanges can be used to isolate sections of the sprinkler system on the floor if necessary.
Re: Mechanical Demolition-Sheets M-123.00, M-124.00, M-
127.00 and M-129.00 do not provide any indication on the extent of mechanical demolition in the areas to be work in.
What is to be demolished with regard to mechanical systems in the work areas?
As indicated on the drawings, where identified, all ductwork is to be demolished and removed back to the point of connection. It is recommended that the contractor assume 3 pounds of sheetmetal per SF. It is not anticipated that there is any large equipment located above the ceiling.
Re: Operable Partitons-The specification 102226 - 2.4 c calls for Marker boards and tack boards but there is no indication on which panels are to receive marker boards and which one are to receive tack boards. Can this be clarified?
Operable partitions are to receive gypsum wall and painted to match walls in room.
Re: Louvers-Plan sheet M224.0 has two new louvers shown on column line J labelled ‘By Others’. Specification 233113 paragraph 3.1.NN has that ‘louvers in Building Façade… will be provided as part of the work of another contractor’ and the specifications provide no requirements for exterior louvers under this contract. Plan sheet M-603 provides an exterior louver detail. Are exterior louvers to be provided under this contract, and if so, what are the requirements for those louvers?
Louvers are existing and should be assumed to provide adequate open area for the equipment shown.
Re: Mechanical Work for Options 1 and 2Plan sheet M223 shows ductwork for supply that crosses the boundary between areas A and B at several locations, and sheet M324 shows piping supplying units in area B being supplied across area A. For example if only option 1 is taken the supply ductwork for rooms 2304, 2305, and 2306 would not be connected. If only option 1 is taken what changes are required for the piping and ductwork at the boundary between area A and area B?
These room numbers are in the annex side of the building and have no relationship to Option B.
Therefore, if Option B happens and not A there would be no impact to HVAC for these rooms.
Re: Wall at Area A and B Boundary-Is the wall between areas A and B to be assumed to be constructed under both options 1 and 2? The wall should be constructed under Area B.
Re: Fire Watch-Is a 24 hour fire watch required in the construction areas when the fire sprinkler service in that area when the sprinkler is inactive in the construction area?
When the sprinkler system is inactive on the floor, in the construction zone, and/or occupied adjacent areas, a continuous 24 hour fire watch is required, unless a temporary heat detection system, or a temporary sprinkler protection (i.e., upright heads in space with no suspended ceiling), is provided
Re: Alternates- On the floor plans Finish Note #1 says that WCV01 is an alternate to Gl23 but there is no place on the bid form for this. Can this be clarified? Bid sheet to be revised to include the deduct alternates
Re: Window Treatment:Note 8 on A-123 says provide new window treatment as scheduled. Please provide a specification and schedule.
All windows to receive horizontal metal blinds. Levolor Riviera 1" metal blinds, to be installed on inside of window with a painted metal fascia.
Re: Low Voltage Raceways:Section 230900 paragraph 3.3.a.3 calls for all control wiring and all primary network wiring to be run in conduit. Section 260519 paragraph 3.7.a.1 states that miscellaneous low voltage systems may be run without conduit. Section 2660001 paragraph 3.2.b states that fire alarm wiring shall be run in conduit. Can the DDC control wiring be installed without conduit and utilizing plenum rated cable?
Low voltage telecommunication system will be run without conduit.
Re: Low Voltage RacewaysCan the fire alarm cabling be installed using plenum rated cable without conduit? No must be in conduit
Re: Telecommunications Scope-The plans state that the contractor is to install conduits with pull strings and cable tray for this contract. There is a complete telecommunications specification provided, where it is stated that the contractor is to coordinate with the GSA vendor.
What are the requirements for contractor coordination with the GSA vendor?
Telecommunication wiring will be furnished by GSA vendor.
Electrical contractor shall provide pathways (conduit, sleeves, cable trays, wiring poles - raceways, pull strings, etc.) for all telecommuncation wiring. Field coordination is required between all trades to achieve the design intent.
Re: Security System Scope:Specification 01 31 00 Paragraph 1.3.c.3 lists that security systems and packages might be provided by others. Is the security system called out in the plans to be provided under this contract, or only to be coordinated under this contract?
Security wiring will be furnished by GSA vendor. Electrical contractor shall provide pathways (conduit, sleeves, cable trays, wiring poles - raceways, pull strings, etc.) for all telecommuncation wiring. Field coordination is required between all trades to achieve the design intent.
Re: Staffing on Multiple Floors-If work is being performed on multiple floors at the same time will a Quality Control Manager/Superintendent be required on each floor?
The GC to determine appropriate staffing to implement the work.
Re: Staffing on Multiple Floors-If work is being performed on multiple floors at the same time will a SSHO(Site Safety and Health Officer) be required on each floor? The GC to determine appropriate staffing to implement the work.
Re: Wall Type A6C:Wall type A6C is provided on the partition schedule on sheet A702 which shows installation of foil and new gypsum wallboard on existing exterior walls at the windows in secure areas. Plan sheets A123.00 and A124.00 do not call out this wall type to be installed and have it noted that the insulation behind the induction units is not to be disturbed. In addition, sheets M123.00 and M124.00 call for those existing induction units to remain in place which would prohibit the installation of wall type A6C at those locations.
Induction units are to remain and not be touched in these locations. The induction unit will act as the foil in the wall, so foil does not need to be added to the wall where the induction unit is located, only in the portion of the wall above.
Re: Wall type A6C: Where is wall type A6C to be installed?
Wall type A6C indicates existing walls at the perimeter of room 14/SWE spaces. This drawing indicates where the new RF film is to be located with keynote 7
Re: Fire Sprinkler Specifications: The fire sprinkler specifications have multiple sections where it appears that the specification allows for selection between various items, but no selection was made.
The updated Fire Protection Specification will uploaded to FOB on or before July 20th.
Re: Fire Sprinkler Specifications:In paragraph 1.3.d, the specification has ‘indicate latest water supply test information and pressure available at [the fire pump discharge flange][the base of the sprinkler riser]’. What is required?
The referenced paragraph in the sprinkler specification may be disregarded. The available pressure available at each floor via tanks is indicated on the sprinkler drawings.
Re: Fire Sprinkler Specifications:In paragraph 1.7.b, installer qualifications are listed as ‘minimum five years experience and [state of][ ][New York City] certification.’ What is required?
The sprinkler contractor shall have a minimum of five years of experience and be licensed in New York City. Note that designers and installers require NICET certification.
Re: Fire Sprinkler Specifications:There are multiple items in the paragraph 2, products that are unselected. For example in paragraph 2.3.E.1 class 150 [250][300]. Can the fire protection specifications be edited to select items.
The sprinkler specification will be uploaded to FOB on or before July 20th. The contractor should also be advised that all sprinkler components must be listed for 175 psi. The references to class (150, 250, 300) in this section are not relevant.
1. Symbol S60 in diamond shown on E-123 in rooms 23- 301, 302, 303 & 304 is not defined in the legend. Please specify what this symbol is for.
The graphic symbol or tag indicated is not utilized on the electrical drawings. All utilized symbols are referenced on E-001. S60 diamond is shown on the SE-
123. The keyed note is defined as "PROVIDE (2) CAT-
5 CABLE DROPS IN OPPOSITE CORNERS OF THE
ROOM FOR CAMERAS THAT WILL BE PLACED
NEAR THE CEILING. EXACT PLACEMENT SHOULD
BE COORDINATED WITH THE TENANT."
2. As per note 32 on FA001, raceways may be omitted for system low voltage wiring where run in voids of hung ceilings. On the other hand as per note 1 on FA-301 all wiring for Fire Alarm notification appliances shall be installed in conduit.