Draft_GC_Agreement_–_Section_1.A_–_Period_of_Performance.pdf

PDF 448 KB Posted

Attached to
Multiple Floor Renovations at 26 Federal Plaza
Solicitation number
47PC0318R0007
Issued by

About this file

Draft GC Agreement - Section 1.A - Period of Performance

View the file

Other files

File Type Posted
SF30_Amendment_0011.pdf PDF
Photos_Group_A.pdf PDF
Photos_Group_B.pdf PDF
Responses_to_Industry's_RFIs_as_of_7-18-18.pdf PDF
SF30_Amendment_0008.pdf PDF
SF30-Amendment_0007.pdf PDF
Past_Performance_Questionaire_Form.docx DOCX document
SF30-Amendment_0006.pdf PDF
Reps_Certs_-_Form_C301.docx DOCX document
SF30_-_Amendment_0005.pdf PDF
Amendment_0004_SF30.pdf PDF
Copy_of_Equipment_for_Disposal.pdf.xlsx XLSX spreadsheet
Past_Performance_Questionaire_(PPQ).pdf PDF
Pre-Con_Meeting_Multi-floor_Backfill_6-14-2018_9am_and_11am.pdf PDF
Responses_to_Industry's_RFIs_6-11-2018.pdf PDF
SBU_Contract_Cluase.pdf PDF
Amendment_0003_SF30.pdf PDF
Form_B_-_Sensitive_But_Unclassified_Document_Notice_to_Prospective_Bidders_or_Offerors.pdf PDF
GSA_Specs-_Volume_01_-_Encrypted.pdf PDF
GSA_Specs-_Volume_02_-_Encrypted.pdf PDF
Amendment_0002.pdf PDF
Revised_SF1442_with_Pricing_Sheet.pdf PDF
Amendment_0001.pdf PDF
SBSA_-_Solicitation_-_26_Federal_Multi_Floor_Project.pdf PDF
SF24-16.pdf PDF
GSA_527_-_Contractor's_Qualifications_and_Financial_Info.pdf PDF
Davis_Bacon_Wages.txt TXT text file
SF1442_-_26_Fed_Multifloor_Project_-Pricing_Sheet.pdf PDF
GC_Agreement_-_26_Federal_PLaza_Multi_Floor_Project_(4).pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

I.A. Period of Performance

The Contractor shall have 300 calendar days after receipt of Notice to Proceed (NTP) to achieve substantial completion of: The Multiple Floor Renovation Project for all base contract work on floors 27 and 29 located at the Jacob Javits Federal Building 26 Federal Plaza, New York, NY 10278.

ITEM DESCRIPTION

Total Lump Sum Base Bid for all work on the 27th and 29th Floors, excluding Alternates 1A & 2A (substantial completion within 300 calendar days of NTP) REFER TO NOTE 2 BELOW.

Alternate No. 1A: Rehabilitation of existing perimeter induction units on the 27th and 29th floors.

Alternate No. 2A: Replacement of perimeter induction units on the 27th and 29th floors.

Add Option No. 1: 23rd Floor – Area A, excluding Alternates 1B & 2B

(substantial completion within 120 calendar days of NTP) with an estimated NTP issuance 30 calendar days after completion of the 27th floor

Alternate No. 1B: Rehabilitation of existing perimeter induction units on the 23rd floor - Area A

Alternate No. 2B: Replacement of perimeter induction units on the 23rd floor - Area A.

Add Option No. 2: 23rd Floor – Area B, excluding Alternates 1C & 2C

(substantial completion within 120 calendar days of NTP) with an estimated NTP issuance 90 calendar days after issuance of the NTP.

Alternate No. 1C: Rehabilitation of existing perimeter induction units on the 23rd floor - Area B

Alternate No. 2C: Replacement of perimeter induction units on the 23rd floor - Area B.

Add Option No. 3: entire 23rd Floor, excluding Alternates 1D & 2D (substantial completion within 180 calendar days of NTP) with an estimated NTP issuance 30 calendar days after the completion of the 27th floor.

Alternate No. 1D: Rehabilitation of existing perimeter induction units on the entire 23rd floor

Alternate No. 2D: Replacement of perimeter induction units on the entire 23rd floor.

Add Option No. 4: 24th Floor, excluding Alternates 1E & 2E (substantial completion within 180 calendar days of NTP) with the expectation work would commence on or about February 2019.

Alternate No. 1E: Rehabilitation of existing perimeter induction units on the 24th floor

Alternate No. 2E: Replacement of perimeter induction units on the 24th

Note 1: Bidders are reminded that in their base bid or option price the cost for cleaning of the induction units is included. The alternate price is the added costs associated with the increased scope.

Note 2: Work on the 29th floor will commence upon receipt of Notice to Proceed (“NTP”), and work on the 27th floor will commence 30 calendar days after substantial completion of the 29th floor.

(1) Commencement. The Contractor shall commence performance of the Work within 30 days after the Contractor receives the Notice to Proceed (NTP).

(2) Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than 300 calendar days from issuance of Notice to Proceed (NTP).

(3) Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 60 calendar days of Substantial Completion.

floor.

Total Evaluated Offer –Sum of Lump Sum Base Bid Plus all Alternates

& Options