P01 - PWS Attachment 14 - Quality Assurance Surveillance Plan.pdf

PDF 78 KB Posted

Attached to
Z1DZ--Develop Maintenance Management Plan Solicitation Amendment | Change of Site Visit, Response date and add attachments Federal contract opportunity
Solicitation number
36C26124Q0843
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 21

About this file

This document is a Quality Assurance Surveillance Plan (QASP) that outlines the performance standards, monitoring, and incentives/disincentives for a federal contract. The QASP covers required services such as preparing a Project Management Plan (MMP), conducting progress meetings, providing meeting minutes, maintaining the facility management system, developing an Integrated Maintenance Master Schedule, reporting on equipment damage and discrepancies, and providing cost estimates.

The acceptable quality levels, monitoring methods, and consequences for non-conforming services are specified for each performance standard. The Government will not pay for services that do not meet the performance standards, and the contractor will be given the opportunity to correct any non-conforming services at no cost. This QASP is associated with a Department of Veterans Affairs solicitation for "Develop Maintenance Management Plan" under Solicitation Number 36C26124Q0843.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DZ--Develop Maintenance Management Plan Solicitation Amendment | Change of Site Visit, Response date and add attachments, newest first.
File Type Posted
36C26124Q0843 0001.docx DOCX document
P01 - PWS Attachment 6b - Building 500 Drawings - Part 02.pdf PDF
P01 - PWS Attachment 6d - Building 500 Drawings - Part 04.pdf PDF
P01 - PWS Attachment 6e - Building 500 Drawings - Part 05.pdf PDF
P01 - PWS Attachment 9a - Building 710 Drawings - Vol 01.pdf PDF
P01 - PWS Attachment 16a - Building 530 Scope.pdf PDF
P01 - PWS Attachment 1 - Building 100 G-wing Scope.pdf PDF
P01 - PWS Attachment 5a - Building 100 G-wing Drawings - Part 01.pdf PDF
P01 - PWS Attachment 5b - Building 100 G-wing Drawings - Part 02.pdf PDF
P01 - PWS Attachment 6a - Building 500 Drawings - Part 01.pdf PDF
P01 - PWS Attachment 7 - Building 603 Drawings.pdf PDF
P01 - PWS Attachment 9b - Building 710 Drawings - Vol 02.pdf PDF
P01 - PWS Attachment 16b - Building 530 Scope.pdf PDF
P01 - PWS Attachment 2 - Building 500 Scope.pdf PDF
P01 - PWS Attachment 4 - Building 710 Scope.pdf PDF
P01 - PWS Attachment 6c - Building 500 Drawings - Part 03.pdf PDF
P01 - PWS Attachment 8 - Building 615 Drawings.pdf PDF
P01 - PWS Attachment 3 - Buildings 603 and 615 Scope.pdf PDF
36C26124Q0843_3.docx DOCX document
Past Performance Surveys.docx DOCX document
36C26124Q0843 DEVELOP MAINTENANCE MANAGEMENT PLAN.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Standards

Required Services Performance

Standards

Acceptable Quality

Level (AQL)

Monitoring Incentives/

Disincentives

Prepare the Project

Management Plan

(MMP)

MMP contains, at a minimum, section 14 of the PWS and is updated to include approved changes.

MMP is complete and contains the level of detail commensurate with the size, scope and complexity of the activities to be performed under the contract.

100% review by the COR

The Government will not pay for services that do not conform or do not meet performance standards, or have not been properly rendered

The Contractor shall be given an opportunity to correct non-conforming services at no cost to the Government

Conduct progress meetings

Schedule, organize and distribute agendas for weekly progress meetings. See section

19 of the PWS

No deviation unless authorized by the

COR

100% review by the COR

The Government will not pay for services that do not conform or do not meet performance standards, or have opportunity to correct non-conforming services at no cost to the Government

Standards

Acceptable Quality

Level (AQL)

Monitoring Incentives/

Disincentives

Present meeting minutes

Complete meeting minutes are presented within three (3) days of each meeting

Meeting minutes are complete and contains the level of detail appropriate to accurately capture the meeting’s content, including, but not limited to, discussion points, action items, and issues. Meeting minutes are delivered within (3) business days of each meeting

100% review by the COR

The Government will not pay for services that do not conform or do not meet performance standards, or have opportunity to correct non-conforming services at no cost to the Government

Provide documents in the facility maintenance system in VistA

The facility management system contains, at a minimum, the contents withing the MMP and sections listed in section 17 of the PWS.

Manage all assets and work orders in VistA to ensure efficiency and completion. Meet the conditions set forth in the VA approved

MMP as they pertain to the contents within the MMP and to section 17 of the PWS

100% review by the COR

The Government will not pay for services that do not conform or do not meet performance standards, or have opportunity to correct non-conforming

Standards

Acceptable Quality

Level (AQL)

Monitoring Incentives/

Disincentives

Develop an

Integrated

Maintenance

Master Schedule

Using the inventoried equipment and systems, within the

MMP, develop an

IMMS that is updated within the facility management system in

Vista.

No deviation. 100% review by COR

The Contractor will develop a remediation plan for damaged

FF&E and/or building infrastructure within five (5) business days of identification. The

Contractor will present the remediation plan to the COR for approval. The contractor will begin implementing the approved remediation plan within one (1) week of approval.

Provide equipment damage report

Equipment damage identified by the

Contractor is logged in facility management system in Vista and reported to the COR

100% accuracy and

100% completeness with identified damage entered into the facility management system and direct notification to the

COR within one (1) business day

100% review by the COR

The Government will not pay for services that do not conform or do not meet performance standards, or have opportunity to correct non-conforming

Standards

Acceptable Quality

Level (AQL)

Monitoring Incentives/

Disincentives

Provide equipment discrepancy report

Equipment discrepancies identified by the

Contractor are logged in facility management system in Vista and reported to the COR.

See section 15 of the

PWS.

No deviation 100% review by COR

The Government will not pay for services that do not conform or do not meet performance standards, or have opportunity to correct non-conforming services at no cost to the Government

Provide cost estimate

Contractor to provide cost estimate of execution of MMP activities for COR approval.

No deviation 100% review by COR

The Government will not pay for services that do not conform or do not meet performance standards, or have opportunity to correct non-conforming