36C26119R0025-006.pdf
PDF 116 KB Posted
- Solicitation number
- 36C26119R0025
About this file
36C26119R0025 07 01 50.19.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26119R0025-0005005.pdf | ||
| 36C26119R0025-0005004.pdf | ||
| 36C26119R0025-0005002.pdf | ||
| 36C26119R0025-0005001.docx | DOCX document | |
| 36C26119R0025-0005003.pdf | ||
| 36C26119R0025-0004000.docx | DOCX document | |
| 36C26119R0025-0003000.docx | DOCX document | |
| 36C26119R0025-0003001.dwg | DWG drawing | |
| 36C26119R0025-0002000.docx | DOCX document | |
| 36C26119R0025-0001001.pdf | ||
| 36C26119R0025-0001000.docx | DOCX document | |
| 36C26119R0025-014.pdf | ||
| 36C26119R0025-017.pdf | ||
| 36C26119R0025-007.pdf | ||
| 36C26119R0025-010.pdf | ||
| 36C26119R0025-016.docx | DOCX document | |
| 36C26119R0025-008.pdf | ||
| 36C26119R0025-002.docx | DOCX document | |
| 36C26119R0025-009.pdf | ||
| 36C26119R0025-003.pdf | ||
| 36C26119R0025-004.pdf | ||
| 36C26119R0025-015.pdf | ||
| 36C26119R0025-011.pdf | ||
| 36C26119R0025-013.pdf | ||
| 36C26119R0025-005.pdf | ||
| 36C26119R0025-012.pdf | ||
| 36C26119R0025-001.docx | DOCX document |
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
02-01-16
07 01 50.19 - 1
SECTION 07 01 50.19
PREPARATION FOR RE-ROOFING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Complete roof removal for new roof system installation.
2. Partial roof removal for new roof system installation.
3. Roofing membrane and selective roofing system component removal for new roof membrane installation.
4. Existing roofing membrane preparation for new roofing installation.
B. Existing Roofing System: Built-up asphalt. System components include:
1. Pavers and paver supports.
2. Roof insulation and drainage board.
3. Aggregate surfacing.
4. Roofing membrane.
5. Cover board.
6. Roof insulation.
7. Vapor retarder.
8. Substrate board.
1.2 RELATED REQUIREMENTS
A. New Roofing System: Section 07 51 00.11, BUILT-UP BITUMINOUS ROOFING, HOT-APPLIED
B. Sheet Metal Counterflashing: Section 07 60 00, SHEET METAL FLASHING AND
TRIM.
1.3 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. American National Standards Institute/Single-Ply Roofing Institute
(ANSI/SPRI):
1. FX-1-01(R2006) Standard Field Test Procedure for Determining the
Withdrawal Resistance of Roofing Fasteners.
C. American Society for Nondestructive Testing (ASNT):
1. SNT-TC-1A - Personnel Qualification and Certification for
Nondestructive Testing.
D. ASTM International (ASTM):
1. C208-12 - Cellulosic Fiber Insulating Board.
2. C578-15 - Rigid, Cellular Polystyrene Thermal Insulation.
3. C728-15 - Perlite Thermal Insulation Board.
07 01 50.19 - 2
4. C1177/C1177M-13 - Glass Mat Gypsum Substrate for Use as Sheathing.
5. C1153-97(2003)e1 - Location of Wet Insulation in Roofing Systems
Using Infrared Imaging.
6. C1278/C1278M-07a(2015) - Fiber-Reinforced Gypsum Panel.
7. D4263-83(2012) - Indicating Moisture in Concrete by the Plastic
Sheet Method.
E. U.S. Department of Commerce National Institute of Standards and
Technology (NIST):
1. DOC PS 1-09 - Structural Plywood.
2. DOC PS 2-04 - Performance Standard for Wood-Based Structural-Use
Panels.
1.4 PREINSTALLATION MEETINGS
A. Conduct preinstallation meeting minimum 30 days before beginning Work of this section.
1. Required Participants:
a. Contracting Officer's Representative.
b. Inspection and Testing Agency.
c. Contractor.
d. Installer.
e. Manufacturer's field representative.
f. Other installers responsible for adjacent and intersecting work, including mechanical and electrical equipment installers.
2. Meeting Agenda: Distribute agenda to participants minimum 3 days before meeting.
a. Removal and installation schedule.
b. Removal and installation sequence.
c. Preparatory work.
d. Protection before, during, and after installation.
e. Removal and installation.
f. Temporary roofing including daily terminations.
g. Transitions and connections to other work.
h. Inspecting and testing.
i. Other items affecting successful completion.
3. Document and distribute meeting minutes to participants to record decisions affecting installation.
07 01 50.19 - 3
1.5 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Submittal Drawings:
1. Show size, configuration, and installation details.
C. Manufacturer's Literature and Data:
1. Description of each product.
2. Description of temporary roof system and components.
3. List of patching materials.
4. Recover board fastening requirements.
5. Temporary roofing installation instructions and preparation instructions to receive new roofing.
6. Existing roofing warrantor's instructions.
D. Photographs: Document existing conditions potentially affected by roofing operations before work begins.
E. Field Inspection Reports:
1. Certify warrantor inspected completed roofing and existing warranty remains in effect.
F. Infrared Roof Moisture Survey Report.
1.6 QUALITY ASSURANCE
A. Installer Qualifications:
1. Same installer as Section 07 51 00.11, BUILT-UP BITUMINOUS ROOFING, HOT-APPLIED.
2. Licensed to perform asbestos abatement in Project jurisdiction when removal of asbestos-containing material is required.
3. Approved by existing roofing system warrantor when work affects existing roofing system under warranty.
1.7 FIELD CONDITIONS
A. Building Occupancy: Perform work to minimize disruption to normal building operations.
1. Verify occupants are evacuated from affected building areas when working on structurally impaired roof decking above occupied areas.
2. Provide notice minimum 72 hours before beginning activities affecting normal building operations.
B. Existing Roofing Available Information:
1. The following are available for Contractor reference:
a. Roof moisture survey.
07 01 50.19 - 4
b. Test cores analysis.
c. Construction drawings and project manual.
2. Examine available information before beginning work of this section.
C. Weather Limitations: Proceed with reroofing preparation only during dry weather conditions as specified for new roofing installation in Section
07 51 00.11, BUILT-UP BITUMINOUS ROOFING, HOT-APPLIED.
1. Remove only as much roofing in one day as can be made watertight in same day.
D. Hazardous materials are not expected in existing roofing system.
1. Known hazardous materials were removed before start of work.
2. Do not disturb suspected hazardous materials. When discovered, notify Contracting Officer's Representative.
3. Hazardous materials discovered during execution of the work will be removed by Government as work of a separate contract.
1.8 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Warranty of
Construction."
PART 2 - PRODUCTS
2.1 MATERIALS
A. Patching Materials: Match existing roofing system materials.
B. Metal Flashing: See Section 07 60 00, SHEET METAL FLASHING AND TRIM.
C. Temporary Protection Materials:
1. Expanded Polystyrene (EPS) Insulation: ASTM C578.
2. Plywood: NIST DOC PS 1, Grade CD Exposure 1.
3. Oriented Strand Board (OSB): NIST DOC PS 2, Exposure 1.
D. Temporary Roofing System Materials: Contractor's option.
E. Recover Board: One of the following:
SPEC WRITER NOTE: Retain one of paragraphs below when new roofing is installed over existing roofing.
1. Insulation: See Section 07 22 00, ROOF AND DECK INSULATION.
2. Fiber Board: ASTM C208, Type II, fiber board; 13 mm (1/2 inch) thick.
3. Glass Mat Gypsum Board: ASTM C1177/C1177M, water-resistant; // 6 mm
(1/4 inch) // 13 mm (1/2 inch) // Type X, 16 mm (5/8 inch) // thick.
07 01 50.19 - 5
4. Fiber Reinforced Gypsum Board: ASTM C1278/C1278M, water-resistant;
// 6 mm (1/4 inch) // 10 mm (3/8 inch) // 13 mm (1/2 inch) // 16 mm
(5/8 inch) // thick.
5. Perlite: ASTM C728; // 3 mm (1/2 inch) // 19 mm (3/4 inch) // 25 mm
(1 inch) // thick.
F. Fasteners: Type and size required by roof membrane manufacturer to resist wind uplift.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Infrared Roof Moisture Survey: Ground-based, walk-over type performed according to ASTM C1153.
1. Record the entire survey on DVD and provide one copy to Contracting
Officer's Representative with report.
2. Include in report thermograms of suspect areas and corresponding daytime photos of same locations.
3. Conduct inspection by NDT test technician certified to at least
Level 2 in Thermal/Infrared test method according to ASNT SNT-TC-1A.
4. Mark out roof areas determined to be wet to indicate // minimum // areas to be removed.
3.2 PREPARATION
A. Examine and verify substrate suitability for product installation.
B. Protect existing roofing system indicated to remain.
1. Cover roof membrane with temporary protection materials without impeding drainage.
2. Limit traffic and material storage to protected areas.
3. Maintain temporary protection until replacement roofing is completed.
C. Protect existing construction and completed work from damage.
D. Protect landscaping from damage.
E. Maintain access to existing walkways and adjacent occupied facilities.
F. Coordinate use of rooftop fresh air intakes with Contracting Officer's
Representative to minimize effect on indoor air quality.
G. Ensure temporary protection materials are available for immediate use in case of unexpected rain.
H. Ensure roof drainage remains functional.
1. Keep drainage systems clear of debris.
2. Prevent water from entering building and existing roofing system.
07 01 50.19 - 6
I. Coordinate rooftop utilities remaining active during roofing work with
Contacting Officer's Representative.
3.3 RE-ROOFING PREPARATION - GENERAL
A. Notify Contacting Officer's Representative of planned operations, daily.
1. Identify location and extent of roofing removal.
2. Request authorization to proceed.
3.4 OVERBURDEN REMOVAL
A. N/A
3.5 COMPLETE ROOFING SYSTEM REMOVAL
A. N/A
3.6 PARTIAL ROOFING SYSTEM REMOVAL
A. N/A
3.7 ROOFING MEMBRANE AND SELECTIVE ROOFING SYSTEM COMPONENT REMOVAL
A. Remove existing roofing membrane, only, in locations and to extent indicated on drawings.
B. Visually inspect roof insulation, and substrate board for moisture immediately after roof membrane removal.
1. Coordinate with Contracting Officer's Representative to observe inspections.
2. Identify wet roofing system components required to be removed.
3. Mark roofing system removal locations and extents.
C. Remove wet roofing system components.
1. Remove or cut-off roofing system fasteners when removals expose structural roof deck.
D. Patch selective roofing system removals immediately after inspection and repair.
E. Install patching materials to match existing roofing system.
F. Patch roofing membrane to maintain building watertight, unless new roofing membrane is installed same day as removal and repair.
3.8 DECK PREPARATION
A. N/A
3.9 TEMPORARY ROOFING
A. Install temporary roofing to maintain building watertight.
B. Remove temporary roofing before installing new roofing.
07 01 50.19 - 7
C. Prepare temporary roofing to receive new roofing.
3.10 EXISTING MEMBRANE PREPARATION FOR NEW ROOFING
A. Remove existing roofing surface projections and irregularities. Produce smooth surface to receive recover boards.
1. Broom clean existing surface.
3.11 BASE FLASHING REMOVAL
A. Expose base flashings to permit removal.
1. Two-Piece Counterflashings: Remove cap flashing and store for reuse.
2. Single Piece Counterflashings: Carefully bend counterflashing.
3. Metal Copings: Remove decorative cap and store for reuse.
B. Remove existing base flashings.
1. Clean substrates to receive new flashings.
C. Replace counterflashings damaged during removal.
1. Counterflashings: See Section 07 60 00 SHEET METAL FLASHING AND
TRIM.
3.12 RECOVER BOARD INSTALLATION
A. N/A
3.13 FIELD QUALITY CONTROL
A. Field Tests:.
1. Fastener Pull Out Tests: ANSI/SPRI FX-1.
B. Existing Roofing System Warrantor Services:
1. Inspect reroofing preparation and roofing installation to verify compliance with existing warranty conditions.
2. Submit reports of field inspections, and supplemental instructions issued during inspections.
3.14 DISPOSAL
A. Collect waste materials in containers.
B. Remove waste materials from project site, regularly, to prevent accumulation.
C. Legally dispose of waste materials.
- - E N D - -