36C26118R0214-002.pdf

PDF 5 MB Posted

Attached to
654-250 New Parking Structure
Solicitation number
36C26118R0214
Issued by

About this file

36C26118R0214 VA DEMO 15 654-16-603 BID SET SPECS 4-3-17.pdf

View the file

Other files

File Type Posted
36C26118R0214-0004001.pdf PDF
36C26118R0214-0004000.docx DOCX document
36C26118R0214-0003001.pdf PDF
36C26118R0214-0003000.docx DOCX document
36C26118R0214-0003002.pdf PDF
36C26118R0214-0002001.pdf PDF
36C26118R0214-0001001.docx DOCX document
36C26118R0214-024.pdf PDF
36C26118R0214-054.docx DOCX document
36C26118R0214-045.docx DOCX document
36C26118R0214-006.pdf PDF
36C26118R0214-070.docx DOCX document
36C26118R0214-071.docx DOCX document
36C26118R0214-058.docx DOCX document
36C26118R0214-022.pdf PDF
36C26118R0214-005.pdf PDF
36C26118R0214-027.docx DOCX document
36C26118R0214-008.pdf PDF
36C26118R0214-029.docx DOCX document
36C26118R0214-081.pdf PDF
36C26118R0214-057.docx DOCX document
36C26118R0214-037.docx DOCX document
36C26118R0214-009.pdf PDF
36C26118R0214-079.pdf PDF
36C26118R0214-025.docx DOCX document
36C26118R0214-031.docx DOCX document
36C26118R0214-048.docx DOCX document
36C26118R0214-010.pdf PDF
36C26118R0214-004.pdf PDF
36C26118R0214-069.docx DOCX document
36C26118R0214-061.docx DOCX document
36C26118R0214-001.docx DOCX document
36C26118R0214-044.docx DOCX document
36C26118R0214-075.pdf PDF
36C26118R0214-063.docx DOCX document
36C26118R0214-052.docx DOCX document
36C26118R0214-040.docx DOCX document
36C26118R0214-039.docx DOCX document
36C26118R0214-019.pdf PDF
36C26118R0214-053.docx DOCX document
36C26118R0214-074.pdf PDF
36C26118R0214-067.docx DOCX document
36C26118R0214-043.docx DOCX document
36C26118R0214-011.pdf PDF
36C26118R0214-078.pdf PDF
36C26118R0214-021.pdf PDF
36C26118R0214-066.docx DOCX document
36C26118R0214-051.docx DOCX document
36C26118R0214-034.doc DOC document
36C26118R0214-000.docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Reno Demo Bldgs. 15A, 15B, K, F, &138

PROJECT

SPECIFICATIONS

Project 654-16-603 VA Sierra Nevada Health Care System 975 Kirman Avenue Reno, NV 89502

VA Contract Officer Representative (COR):

David Wolf 775-789-6680

Construction Documents

BID SET

April 3, 2017

DEPARTMENTOFVETERANSAFFAIRSVARENODEMOBILDGS.15A,15B,F,K,&138
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-603

00 01 10 - 1

4-3-17

SECTION 00 01 10

TABLE OF CONTENTS

DIVISION 00

00 01 10 TABLE OF CONTENTS

00 01 15 LIST OF DRAWING SHEETS

DIVISION 01

01 00 00 GENERAL REQUIREMENTS

01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01 35 26 SAFETY REQUIREMENTS

01 42 19 REFERENCE STANDARDS

01 45 29 TESTING LABORATORY SERVICES

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 CONSTRUCTION WASTE MANAGEMENT

DIVISION 02

02 41 00 DEMOLITION

02 82 11 TRADITIONAL ASBESTOS ABATEMENT

02 83 33.13 LEAD-BASED PAINT REMOVAL AND DISPOSAL

DIVISION 03

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04

04 05 13 MASONRY MORTARING

04 05 16 MASONRY GROUTING

04 20 00 UNIT MASONRY

DIVISION 07

07 01 50.19 PREPARATION FOR RE-ROOFING

07 54 19 POLYVINYLE-CHLORIDE (PVC) ROOFING

07 60 00 FLASHING AND SHEET METAL

07 92 00 JOINT SEALANTS

DIVISION 09

09 91 00 PAINTING

DIVISION 26

26 05 11 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS

26 05 19 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 33 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS

26 56 00 EXTERIOR LIGHTING

DIVISION 27

27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS

27 05 26 GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS

27 05 33 RACEWAYS AND BOXES FOR COMMUNICATIONS SYSTEMS

27 10 00 CONTROL, COMMUNICATION AND SIGNAL WIRING

27 11 00 TELECOMMUNICATIONS ROOM FITTINGS

DEPARTMENTOFVETERANSAFFAIRSVARENODEMOBILDGS.15A,15B,F,K,&138
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-603

00 01 10 - 2

27 15 00 COMMUNICATIONS STRUCTURED CABLING

DIVISION 28

28 31 00 FIRE ALARM

DIVISION 31

31 20 00 EARTH MOVING

ATTACHEMENTS

Rules of the Facility for Construction Contractors, MAY 3, 2016

Safety and Infection Control Handbook for Contractors ICRA and ISLM forms Equipment Maintenance Form Construction Sign Detail Safety Sign Detail

DEPARTMENTOFVETERANSAFFAIRSVARENODEMOBILDGS.15A,15B,F,K,&138
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-603

00 01 15 - 1

4-3-17

SECTION 00 01 15

SHEET SCHEDULE

GENERAL

GI-0.0 COVER SHEET

CIVIL

C 0.0 CIVIL DEMOLITION PLAN

C 0.1 CIVIL DEMOLITION PLAN

ARCHITECTURAL

AD-0.1 EXISTING CONDITIONS

AD-1.0 DEMOLITION PLAN

AD-1.2 ROOF DEMOLITION PLAN

AD-3.1 BUILDINGS: 15A. 15B, F, K, 138 PHOTOS

AD-3.2 BUILDINGS: 15A. 15B, F, K, 138 PHOTOS

AD-3.3 BUILDINGS: 15A. 15B, F, K, 138 PHOTOS

AD-4.1 DEMOLITION SECTIONS

AE-1.2 ROOF PLAN

AE-3.1 EXTERIOR ELEVATIONS

AE-4.1 SECTIONS

AE-5.1 DETAILS

STRUCTURAL

SD-0.1 PROJECT TITLE , NOTES AND DEMOLITION PLAN

ELECTRICAL

E-0.1 ELECTRICAL LEGEND & DRAWING SCHEDULE

E-0.2 PANEL & FIXTURE SCHEDULES & ENERGY COMPLIANCE FORMS

ED-0.1 DEMOLITION & FIXTURE SCHEDULES

ED-0.2 DEMOLITION ONELINE DIAGRAMS

ED-1.1 OVERALL DEMOLITION ELECTRICAL SITE PLAN

ED-2.1 ENLARGED DEMOLITION PLAN - BUILDING 15

ED-2.2 ENLARGED DEMOLITION PLAN - BUILDING F

ED-2.3 ENLAREGED DEMOLITION PLAN - BUILDING 138 FMS

ES-1.1 OVERALL NEW WORK SITE PLAN

ES-1.2 ENLARGED POWER & LIGHTING NEW WORK PLAN

ES-2.1 SITE PHOTOMETRIC CALCULATIONS

TELECOM

TD-0.1 TELECOM GENERAL NOTES, LEGEND & DRAWINGS SCHEDULE

TD-0.2 TELECOM DEMOLITION & NEW ONELINE DIAGRAMS

TD-0.3 TELECOM ENLARGED BUILDING 7 TELECOM ROOM

TD-1.1 OVERALL TELECOM SITE PLAN

DEPARTMENTOFVETERANSAFFAIRSVARENODEMOBILDGS.15A,15B,F,K,&138
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-603

11-01-15 i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION......................................................................................................1
1.3 STATEMENT OF BID ITEM(S).....................................................................................2
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR..........................................3
1.5 CONSTRUCTION SECURITY REQUIREMENTS.............................................................3
1.6 OPERATIONS AND STORAGE AREAS...........................................................................5
1.7 ALTERATIONS..................................................................................................................10
1.8 DISPOSAL AND RETENTION........................................................................................12

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS............................................................................12
1.10 RESTORATION...............................................................................................................13
1.11 PHYSICAL DATA...........................................................................................................14
1.12 PROFESSIONAL SURVEYING SERVICES................................................................15
1.13 LAYOUT OF WORK........................................................................................................15
1.14 AS-BUILT DRAWINGS.................................................................................................15
1.15 USE OF ROADWAYS......................................................................................................16
1.16 RESIDENT ENGINEER'S FIELD OFFICE..............................................................16
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT..............16
1.18 TEMPORARY USE OF EXISTING ELEVATORS......................................................17
1.19 TEMPORARY USE OF NEW ELEVATORS..................................................................17
1.20 TEMPORARY TOILETS.................................................................................................18
1.21 AVAILABILITY AND USE OF UTILITY SERVICES...........................................18
1.22 NEW TELEPHONE EQUIPMENT...................................................................................19
1.23 TESTS..............................................................................................................................19
1.24 INSTRUCTIONS.............................................................................................................20
1.25 GOVERNMENT-FURNISHED PROPERTY.....................................................................22
1.26 RELOCATED // EQUIPMENT // ITEMS //.........................................................23
1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT23
1.28 CONSTRUCTION SIGN.................................................................................................23
1.29 SAFETY SIGN...............................................................................................................23
1.30 PHOTOGRAPHIC DOCUMENTATION............................................................................24
1.32 HISTORIC PRESERVATION........................................................................................26
1.33 VA TRIRIGA CPMS......................................................................................................26

1.34 SCHEDULING…………………………………………………………………………………………………..……………………26

1.35 PERMITS…….…………………………………………………………………………………………………………..……………..26

1.36 WALL/FLOOR PENETRATIONS……………………………………………………………………………………….28

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for additional safety and infection control requirements.

A. Infection Control:

See attached: ICRA and ILSM forms.

1. “Comply with the guidance provided in the ICRA and the ILSM

(attached).”

2. “If the ICRA requires a negative air atmosphere, provide instrumentation outside the envelope which validates the negative air condition. Instrumentation must portray real time pressure and be able to provide a 48 hour log of the pressure at intervals not to exceed 60 seconds.”

B. In addition, the contractor shall comply with the following attachments:

Rules of the Facility for Construction Contractors 16-05-03, is to be read and signed by every contractor employee at the specific time they apply for a badge.

Safety and Infection Control Handbook for Contractors, is to be presented by the prime contractor to both prime and sub employees during various safety sessions.

Special note:

Crane Ops are not permitted over occupied areas. Crane ops should be scheduled when occupants are not routinely under the crane ops area.

All crane ops require submission of a crane lift permit utilizing the template provided by the VA and attached to this specification. Areas of more impact will require greater advance scheduling.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the remodel of existing

Building 7 and related site work as required by drawings and specifications.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -2

B. Visits to the site by Bidders may be made only by appointment with the

Contracting Officer and the Contracting Officer Representative (COR).

C. Offices of Sikora Architecture,PC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, DEMOLITION OF BUILDINGS: 15, 15A, F, K, AND 138: Work includes:

Demolition of the listed buildings including all associated mechanical, plumbing, and electrical equipment. The buildings are to be removed in their entirety including foundations. There is one footing that runs north/south along the east wall of Building 7 that is not to be removed; this work to be coordinated with architectural, structural, and civil. Any and all remaining cabinets, furniture, equipment, etc.

within the buildings at the time the demolition/construction contract is signed will be come the ownership of the contractor. The scope of the project also includes repair and construction work along the east and north walls of Building 7 where it abuts Building 15; including but not limited to, some roof reconstruction and repair.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -3

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

3. Refer to “Rules of the Facility for Construction Contractors”.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Guards: N/A

D. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -4

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

3. Except for the Bldg 1 freight elevator key, contractors are not permitted to possess a VA key. No project site access gates/doors/etc or access to mech/elec room doors may be left unsecure unless the door is in immediate use and a contractor employee is within 10’ (very strict) of the access point. All requests for access must start with the project COR, then to other

CORs within the Projects Section. In general, the COR will respond to two requests for contractor access per day. The contractor is advised to keep at least one contractor employee within the secure area to permit access.

E. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -5

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

1. No contractor vehicle, whether POV or company, is permitted to park on VA property except as necessary for construction operations or in the process of on/off loading materials/equipment, violators will be ticketed and fined. Vehicle parking for stated exception must have specific COR approval when outside the construction fence boundary.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

1. The construction site boundary established in the contract, at contractor expense, may be modified up to five times to increase or decrease based upon changes to the VA’s opinion of the perceived need by the contractor.

2. Dumpster or material/tool/equipment storage on VA property is not permitted except within the boundaries of the construction project.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -6

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as shown on the drawings, and as directed by the COR.

E. Workmen are subject to “Rules of the Facility for Construction

Contractors” as to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by the COR.

1. Do not store materials and equipment in other than assigned areas.

2. Provide unobstructed access to Medical Center areas required to remain in operation. This is particularly required as related to the two Pharmacy Storage rooms associated with this project. This means that the loading dock must remain available to the Pharmacy staff at all times; and, any access limitations must be coordinated and approved through the COR. The contractor shall give the COR ample notice so that he may coordinate with the Pharmacy staff for scheduleing.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -7

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

F*. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

G. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

To insure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.

H. Building No. 7 will be vacated by Government other than the one

Pharmacy storage room: N221, beginning immediately after date of receipt of Notice to Proceed and turned over to Contractor. Pharmacy staff access to room N221 must be provided at all times other than as directed and approved by the COR.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -8

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

2. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.

Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm

(one inch) above grade. Remove the fence when directed by COR.

J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -9

K. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the COR’s and the Medical Center Director’s prior knowledge and written approval. Refer to specification

Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11, REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS, and

28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 14 days in advance of proposed interruption.

Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -10

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

N. Coordinate the work for this contract with other construction operations as directed by the COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of the buildings and site affected by the scope of this project and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds,

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -11 shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.

Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4 and VAAR 852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed,

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -12 floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

1. Contractor shall remove anything left at the construction site to include any supplies, furniture, materials, debris, etc

B. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -13

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -14

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

1.11 PHYSICAL DATA

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. Asbestos Sampling, Building 7 Dated: May 14, 2015

Prepared by: Converse Consultants

4840 Mill Street Suite 5, Reno NV 89502

(775) 856-3833

Converse Proj. No.: 15-23660-01

2. Limited Asbestos and Lead Base Paint Survey, Building 7 Remodel

Dated: May 11, 2016

Prepared by: Converse Consultants

4840 Mill Street Suite 5, Reno NV 89502

(775) 856-3833

Converse Proj. No.: 16-23111-02

B. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -15

Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.

The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established, indicated on the drawings, or as directed by the COR. The

Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the

Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the

Contractor.

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -16 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.

2. Vehicle Parking:

No contractor vehicle, whether POV or company, is permitted to park on

VA property except as necessary for construction operations or in the process of on/off loading materials/equipment. Vehicle parking for stated exception must have specific COR approval when outside the construction fence boundary.

1.16 COR'S FIELD OFFICE

The COR has an office onsite.

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -17 overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.18 TEMPORARY USE OF EXISTING ELEVATORS

Not Applicable

1.19 TEMPORARY USE OF NEW ELEVATORS

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -18

1.20 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

A*. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by Medical Center.

Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Not applicable

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials.

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -19

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the existing electrical distribution system.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR’s discretion) of use of water from Medical Center's system.

G. Fuel: Natural and LP gas and burner fuel oil required for boiler cleaning, normal initial boiler-burner setup and adjusting, and for performing the specified boiler tests will be furnished by the

Government. Fuel required for prolonged boiler-burner setup, adjustments, or modifications due to improper design or operation of boiler, burner, or control devices shall be furnished and paid by the

Contractor at Contractor's expense.

1.22 NEW TELEPHONE EQUIPMENT

The contractor shall coordinate with the work of installation of telephone equipment by others. This work shall be completed before the building is turned over to VA.

1.23 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Not Applicable

DEPARTMENTOFVETERANSAFFAIRSBUILDING7REMODEL
VASIERRANEVADAHEALTHCARESYSTEM
975KIRMANAVENUE,RENO,NV
PROJECTNO.654-16-621

11-01-15

01 00 00 -20

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.

Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.

E. All related components as defined above shall be functioning when any system…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.