Specs-Final Combined set Legionella.pdf
PDF 2 MB Posted
- Attached to
- Z2DA--Legionella - Mixing Valves, Schematics, Controls Federal contract opportunity
- Solicitation number
- 36C25921R0015
About this file
This document is a presolicitation notice for construction services to complete the Legionella - Mixing Valves, Schematics, Controls project at the Salt Lake City VA Medical Center. The project magnitude is between $1,000,000 and $5,000,000, with a NAICS code of 236220 and small business size standard of $39.5 million. The procurement is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. Offerors must be verified by the VA's Center for Verification and Evaluation and listed in the Vendor Information Pages database to be considered eligible. The point of contact is listed as Robyn Young, who can be reached at 307-433-3728 or robyn.young2@va.gov. The response due date will be on or about December 9, 2020.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25921R0015 0007.pdf | ||
| 36C25921R0015 0006.pdf | ||
| 36C25921R0015 0005.pdf | ||
| S02 2016-10-20 Instructions to Offerors - PPT.pdf | ||
| UPDATED 660-15-111 Construction SOW.pdf | ||
| Past Performance Questionnaire.docx | DOCX document | |
| NESHAP VA Limited ACM Building 3 SLC UT 01-04-21.pdf | ||
| 660-15-111 Equipment Cut Sheets.pdf | ||
| 36C25921R0015 0004.pdf | ||
| NESHAP VA Limited ACM Bldg 1 SLC UT 01-04-20.pdf | ||
| Legionella questions.pdf | ||
| 36C25921R0015 0003.pdf | ||
| 2016-09-07 S04 -Site Visit Meeting Doc.pdf | ||
| Site Walk 1- attendance.pdf | ||
| 36C25921R0015 0002.pdf | ||
| Site Walk 2- attendance.pdf | ||
| 36C25921R0015 0001.pdf | ||
| C27 660-15-111 100 percent Drawings.pdf | ||
| 36C25921R0015_1.pdf | ||
| C27 Specs-Final Combined set.pdf | ||
| 36C25921R0015.docx | DOCX document |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LEGIONELLA-MIXING VALVES, SCHEMATICS, CONTROL
VAMC SALT LAKE CITY, UTAH
PROJECT 660-15-111
Bid Package 100% SUBMITTAL
PROJECT MANUAL
May 20, 2020
PREPARED BY:
MEP ENGINEER:
VALI COOPER INTERNATIONAL
18300 E.71st Ave Suite 130, Denver CO
Legionella-Mixing Valves, Schematics, Control
VAMC Salt Lake City, Utah
100% Submittal
VA No. 660-15-111
May 20, 2020
THIS SHEET INTENTIONALLY LEFT
SALT LAKE CITY VAMC- LEGIONELLA MITIGATION
SALT LAKE CITY, UTAH
100% Submittal
VA NO.660-15-111
20 May 2020
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18
01 32 16.15 Project Schedules (Small Projects - Design/Bid/Build 04-13
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 09-19
01 45 00 Quality Control 05-20
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 - EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 04-19
DIVISION 07 - THERMAL AND MOISTURE
07 84 00 Firestopping 10-17
07 92 00 Joint Sealants 11-16
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-14
DIVISION 22 - PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 19 Meters and Gages for Plumbing Piping 09-15
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 11-19
22 13 00 Facility Sanitary and Vent Piping 09-15
22 40 00 Plumbing Fixtures 09-15
DIVISION 23 - HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 09 23 Direct-Digital Control System for HVAC 09-11
DIVISION 26 - ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 24 16 Panelboards 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
100% Submittal
VA NO.660-15-111
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Sheet Number Drawing Title
GI001 Coversheet
GI002 Construction Safety Risk Assessment
GI003 Interim Life Safety Measures
GI004 Infection Control Risk Assessment &
TB Assessment
P-001 Plumbing Legend and Abbreviations
P-101 B1: Ground Floor Plumbing Plan A
P-102 B1: Ground Floor Plumbing Plan B
P-103 B1: First Floor Plumbing Plan A
P-104 B1: First Floor Plumbing Plan B
P-105 B1: First Floor Plumbing Plan C
P-106 B1: First Floor Plumbing Plan D
P-107 B1: First Floor Plumbing Plan E
P-108 B1: Second Floor Plumbing Plan A
P-109 B1: Second Floor Plumbing Plan B
P-110 B1: Second Floor Plumbing Plan C
P-111 B1: Third Floor Plumbing Plan A
P-112 B1: Third Floor Plumbing Plan B
P-113 B1: Fourth Floor Plumbing Plan A
P-114 B1: Fourth Floor Plumbing Plan B
P-115 B1: Fifth Floor Plumbing Plan A
P-116 B1: Fifth Floor Plumbing Plan B
P-117 B1:
Plan
Sixth & Seventh Floor Plumbing
P-118 B3: Ground Floor Plumbing Plan A
P-119 B3: Ground Floor Plumbing Plan B
P-120 B3: First Floor Plumbing Plan A
P-121 B3: First Floor Plumbing Plan B
P-122 B3: Second Floor Plumbing Plan
P-123 B32: First Floor Plumbing Plan
P-124 B32: Second Floor Plumbing Plan
100% Submittal
VA NO.660-15-111
00 01 15 - 2
P-125
P-201
P-401
P-501
B42: Plumbing Plan
Plumbing Elevations
Plumbing Expansions
Plumbing Details I
P-502 Plumbing Details II
P-601 Plumbing Schedule I
P-602 Plumbing Schedule II
P-701 Site Control Schematic
P-702 B1: Control Schematic
P-703 B1: Second Floor Controls Schematic: Zones A, B & C
P-704 B1: Second Floor Controls Schematic: Zones D & E
P-705 B1: Third Floor Controls Schematic: Zones A, B & C
P-706 B1: Third Floor Controls Schematic: Zones D & DDC Points List
P-707 B3: Control Schematic
P-708 B3: First Floor Control Schematic
P-709 B3: Second Floor Control Schematic
P-710 B3, B32, B43: DDC Points List
E-101 Electrical Equipment Plan
E-102 Electrical Equipment Plan
E-103 Electrical Equipment Plan
E-601 Electrical Plumbing Equipment Schedule
100% Submittal
VA NO.660-15-111
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 RESTORATION
1.10 LAYOUT OF WORK
1.11 AS-BUILT DRAWINGS
1.12 WARRANTY MANAGEMENT
1.13 TEMPORARY USE OF EXISTING ELEVATORS
1.14 TEMPORARY TOILETS
1.15 AVAILABILITY AND USE OF UTILITY SERVICES
1.16 TESTS
1.17 INSTRUCTIONS
1.18 GOVERNMENT-FURNISHED PROPERTY
1.19 RELOCATED EQUIPMENT ITEMS
1.20 CONSTRUCTION SIGN
1.21 SAFETY SIGN
1.22 PHOTOGRAPHIC DOCUMENTATION
i
100% Submittal
VA NO.660-15-111
01 00 00 -2
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Salt Lake City VAMC as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Office.
C. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, Building 1 Work includes all labor, material, equipment and supervision to perform the required construction work for Building 1 on this project.
ITEM II, Building 3 Work includes all labor, material, equipment and supervision to perform the required construction work for Building 3 on this project.
ITEM III, Buildings 42 and 43 Work includes all labor, material, equipment and supervision to perform the required construction work for Building 42 and 43 on this project.
ITEM IIII, Building 32 Work includes all labor, material, equipment and supervision to perform the required construction work for Building 32 on this project.
100% Submittal
VA NO.660-15-111
01 00 00 -3
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangementscan be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
100% Submittal
VA NO.660-15-111
01 00 00 -4
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the
Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
D. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting
Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the
Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting
100% Submittal
VA NO.660-15-111
01 00 00 -5
Officer and shall be built with labor and materials furnished by the
Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be determined by the Resident Engineer/COR.
E. Workers are subject to rules of SLC VA Medical Center applicable to their conduct.
F. Execute work to interfere as little as possible with normal functioning of
SLC VA Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and
Contractor's personnel, except as permitted by Resident Engineer/COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two workdays.
100% Submittal
VA NO.660-15-111
01 00 00 -6
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week.
Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the
CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To ensure such executions, Contractor shall furnish the Resident
Engineer/COR with a schedule of approximate phasing dates on which the
Contractor intends to accomplish work in each specific area of the building or portion thereof. In addition, Contractor shall notify the Resident
Engineer/COR two weeks in advance of the proposed date of starting work in each specific area of, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases is mutually agreeable to Medical Center Director, Resident Engineer COR and
Contractor.
H. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Resident Engineer/COR .
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of Resident Engineer/COR . Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer
100% Submittal
VA NO.660-15-111
01 00 00 -7 to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL
INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and
28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
Resident Engineer/COR in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least
15 calendar days prior to the desired time and shall be performed as directed by the Resident Engineer/COR.
5. In case of a contract construction emergency, service will be interrupted on approval of Resident Engineer/COR. Such approval will be confirmed in writing as soon as practical.
I. To minimize interference of construction activities with flow of Medical
Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
J. Coordinate the work for this contract with other construction operations as directed by Resident Engineer/COR.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the Resident Engineer/COR and a representative of VA Supply
Service, of buildings B1, B3 and B32 and all areas in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:
100% Submittal
VA NO.660-15-111
01 00 00 -8
2. Existence and conditions of items such as plumbing fixtures and accessories required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and Resident Engineer or COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of Resident
Engineer/COR and or Supply Representative to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and
"CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Protection: Provide the following protective measures:
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
2. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to
100% Submittal
VA NO.660-15-111
01 00 00 -9 prevent damage which would be detrimental to re-installation and reuse.
Store such items where directed by Resident Engineer/COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of
Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the Resident Engineer/COR.
Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the Resident Engineer/COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract
100% Submittal
VA NO.660-15-111
01 00 00 -10 time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.10 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at
Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The
Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The
Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the
Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
100% Submittal
VA NO.660-15-111
01 00 00 -11
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article
"Professional Surveying Services".
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the Resident Engineer's/COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the Resident Engineer/COR within 15 calendar days after each completed phase and after the acceptance of the project by the Resident Engineer/COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least
30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project
100% Submittal
VA NO.660-15-111
01 00 00 -12 acceptance and continue for the product warranty period. A joint 4 month and
9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address, and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction.
Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
100% Submittal
VA NO.660-15-111
01 00 00 -13
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance Bond: The Performance Bond must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the
Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting.
In connection with these requirements and at the time of the Contractor’s
100% Submittal
VA NO.660-15-111
01 00 00 -14 quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to
Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
Following oral or written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 workdays and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
Code 1-Plumbing
a. Hot water heater failure.
b. Leaking water supply pipes.
Code 2-Plumbing
a. Flush valves not operating properly
100% Submittal
VA NO.660-15-111
01 00 00 -15
b. Fixture drain, supply line or any water pipe leaking.
Code 3- Controls
a. Control performance and operation
1.13 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the Resident Engineer/COR for use of elevators. The Resident Engineer/CORwill ascertain that elevators are in proper condition. Contractor may use service elevators in Building No.
1 for exclusive use during normal business hours. and for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans
Affairs.
1.14 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by Resident Engineer/COR , provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.15 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government.
The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution
100% Submittal
VA NO.660-15-111
01 00 00 -16 lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat.
Electricity for all other uses is available at no cost to the Contractor.
1.16 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Plumbing and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be
100% Submittal
VA NO.660-15-111
01 00 00 -17 coordinated to work together during normal operation to produce results for which the system is designed. etc.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.17 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the Resident Engineer/COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are
100% Submittal
VA NO.660-15-111
01 00 00 -18 component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the Resident Engineer/CORand shall be considered concluded only when the Resident Engineer/COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the Resident Engineer/COR , does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.18 GOVERNMENT-FURNISHED PROPERTY
A. The Government shall deliver to the Contractor, the Government-furnished property shown on the drawings.
B. Equipment furnished by Government to be installed by Contractor will be furnished to Contractor at the Medical Center.
C. Contractor shall be prepared to receive this equipment from Government and store or place such equipment not less than 90 days before Completion Date of project.
D. Notify Contracting Officer in writing, 60 days in advance, of date on which
Contractor will be prepared to receive equipment furnished by Government.
Arrangements will then be made by the Government for delivery of equipment.
1. Immediately upon delivery of equipment, Contractor shall arrange for a joint inspection thereof with a representative of the Government. At such time the Contractor shall acknowledge receipt of equipment described, make notations, and immediately furnish the Government representative with a written statement as to its condition or shortages.
2. Contractor thereafter is responsible for such equipment until such time as acceptance of contract work is made by the Government.
E. Equipment furnished by the Government will be delivered in a partially assembled (knock down) condition in accordance with existing standard commercial practices, complete with all fittings, fastenings, and appliances
100% Submittal
VA NO.660-15-111
01 00 00 -19 necessary for connections to respective services installed under contract.
All fittings and appliances (i.e., couplings, ells, tees, nipples, piping, conduits, cables, and the like) necessary to make the connection between the
Government furnished equipment item and the utility stub-up shall be furnished and installed by the contractor at no additional cost to the
Government.
F. Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with specifications and drawings.
G. Furnish supervision of installation of equipment at construction site by qualified factory trained technicians regularly employed by the equipment manufacturer.
1.19 RELOCATED EQUIPMENT ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment and items indicated by symbol "R" or otherwise shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the Resident Engineer/COR
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph
"Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
E. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
1.20 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the Resident Engineer/ COR .
All wood members shall be of framing lumber. Cover sign frame with 0.7 mm
(24 gage) galvanized sheet steel nailed securely around edges and on all
100% Submittal
VA NO.660-15-111
01 00 00 -20 bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm
(two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the Resident Engineer/ COR
1.21 SAFETY SIGN
A. Provide a Safety Sign where directed by Resident Engineer/COR. Face of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm
(three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by Resident Engineer/COR .
D. Standard Detail Drawing Number SD10000-02(Found on VA TIL) of safety sign showing required legend and other characteristics of sign is // attached hereto and is made a part of this specification.
E. Post the number of accident free days on a daily basis.
1.22 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and at selected milestones including electronic indexing, navigation, storage and remote access to the documentation, as per these specifications. The commercial photographer or the subcontractor used for this work shall meet the following qualifications:
1. Demonstrable minimum experience of three (3) years in operation providing documentation and advanced indexing/navigation systems including a
100% Submittal
VA NO.660-15-111
01 00 00 -21 representative portfolio of construction projects of similar type, size, duration and complexity as the Project.
2. Demonstrable ability to service projects throughout North America, which shall be demonstrated by a representative portfolio of active projects of similar type, size, duration and complexity as the Project.
B. Photographic documentation elements:
1. Each digital image shall be taken with a professional grade camera with minimum size of 6 megapixels (MP) capable of producing 200x250mm (8 x 10 inch) prints with a minimum of 2272 x 1704 pixels and 400x500mm (16 x 20 inch) prints with a minimum 2592 x 1944 pixels.
2. Indexing and navigation system shall utilize actual AUTOCAD construction drawings, making such drawings interactive on an on-line interface. For all documentation referenced herein, indexing and navigation must be organized by both time (date-stamped) and location throughout the project.
3. Documentation shall combine indexing and navigation system with inspection-grade digital photography designed to capture actual conditions throughout construction and at critical milestones.
Documentation shall be accessible on-line through use of an internet connection. Documentation shall allow for secure multiple-user access, simultaneously, on-line.
4. Before construction, the building pad, adjacent streets, roadways, parkways, driveways, curbs, sidewalks, landscaping, adjacent utilities and adjacent structures surrounding the building pad and site shall be documented. Overlapping photographic techniques shall be used to ensure maximum coverage. Indexing and navigation accomplished through interactive architectural drawings. If site work or pad preparation is extensive, this documentation may be required immediately before construction and at several pre-determined intervals before building work commences.
5. Construction progress for all trades shall be tracked at pre-determined intervals, but not less than once every thirty (30) calendar days
(“Progressions”). Progression documentation shall track both the exterior and interior construction of the building. Exterior
Progressions shall track 360 degrees around the site and each building.
100% Submittal
VA NO.660-15-111
01 00 00 -22
Interior Progressions shall track interior improvements beginning when stud work commences and continuing until Project completion.
6. As-built condition of pre-foundation utilities and site utilities shall be documented prior to pouring footers, placing concrete and/or backfilling. This process shall include all underground and in-slab utilities within the building(s) envelope(s) and utility runs in the immediate vicinity of the building(s) envelope(s). This may also include utilities enclosed in slab-on-deck in multi-story buildings. Overlapping photographic techniques shall be used to ensure maximum coverage.
Indexing and navigation accomplished through interactive site utility plans.
7. As-built conditions of mechanical, electrical, plumbing and all other systems shall be documented post-inspection and pre-insulation, sheet rock or dry wall installation. This process shall include all finished systems located in the walls and ceilings of all buildings at the
Project. Overlapping photographic techniques shall be used to ensure maximum coverage. Indexing and navigation accomplished through interactive architectural drawings.
8. As-built conditions of exterior skin and elevations shall be documented with an increased concentration of digital photographs as directed by the
COR in order to capture pre-determined focal points, such as waterproofing, window flashing, radiused steel work, architectural or
Exterior Insulation and Finish Systems (EIFS) detailing. Overlapping photographic techniques shall be used to ensure maximum coverage.
Indexing and navigation accomplished through interactive elevations or elevation details.
9. As-built finished conditions of the interior of each building including floors, ceilings and walls shall be documented at certificate of occupancy or equivalent, or just prior to occupancy, or both, as directed by the COR. Overlapping photographic techniques shall be used to ensure maximum coverage. Indexing and navigation accomplished through interactive architectural drawings.
10. Miscellaneous events that occur during any Contractor site visit, or events captured by the Department of Veterans Affairs independently, shall be dated, labeled and inserted into a Section in the navigation structure entitled “Slideshows,” allowing this information to be stored in the same “place” as the formal scope.
100% Submittal
VA NO.660-15-111