36C25921R0015 0007.pdf
PDF 177 KB Posted
- Attached to
- Z2DA--Legionella - Mixing Valves, Schematics, Controls Federal contract opportunity
- Solicitation number
- 36C25921R0015
About this file
This document includes a federal contract solicitation and related amendment. The solicitation is for construction services to complete the Legionella - Mixing Valves, Schematics, Controls project at the Salt Lake City VA Medical Center. The project magnitude is between $1,000,000 and $5,000,000. The NAICS code is 236220 with a small business size standard of $39.5M. The opportunity is 100% set aside for Service-Disabled Veteran-Owned Small Businesses. Offerors must be verified by the VA Center for Verification and Evaluation. The amendment extends the solicitation response due date to April 15, 2021 at 14:00 MDT and provides answers to requester questions about chemical feeders, insulation pads, and backflow preventers.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25921R0015 0006.pdf | ||
| 36C25921R0015 0005.pdf | ||
| S02 2016-10-20 Instructions to Offerors - PPT.pdf | ||
| UPDATED 660-15-111 Construction SOW.pdf | ||
| Specs-Final Combined set Legionella.pdf | ||
| Past Performance Questionnaire.docx | DOCX document | |
| NESHAP VA Limited ACM Building 3 SLC UT 01-04-21.pdf | ||
| 660-15-111 Equipment Cut Sheets.pdf | ||
| 36C25921R0015 0004.pdf | ||
| NESHAP VA Limited ACM Bldg 1 SLC UT 01-04-20.pdf | ||
| Legionella questions.pdf | ||
| 36C25921R0015 0003.pdf | ||
| 2016-09-07 S04 -Site Visit Meeting Doc.pdf | ||
| Site Walk 1- attendance.pdf | ||
| 36C25921R0015 0002.pdf | ||
| Site Walk 2- attendance.pdf | ||
| 36C25921R0015 0001.pdf | ||
| C27 660-15-111 100 percent Drawings.pdf | ||
| 36C25921R0015_1.pdf | ||
| C27 Specs-Final Combined set.pdf | ||
| 36C25921R0015.docx | DOCX document |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 2
0007 04-08-2021
660-15-111
36C259
Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111
36C259
Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111
To all Offerors/Bidders
36C25921R0015
02-11-2021
X x x
April 15, 2021 at 14:00 MDT
The purpose of this amendment is to extend solicitation close date and answer questions.
Solicitation closes on April 15, 2021 at 14:00 MDT.
Answers to RFI’s
1. This note calls out installing Chemical Feeders, but we aren’t finding a lot of information in the drawings or plumbing schedule about this equipment. What is the Basis of design for Shock Chlorination and Chemical Feeders to be used?
The chemical feeders called out for B1 areas are for Hyper-Chlorination purposes only.
Each floor level will have a chemical feeder near the main riser branch to be manually enabled in the event Legionella remediation is required at the specific floor level. The hyper-chlorination will be limited at the affected floor level as opposed to the entire building. The chemical feed pump shall be capable of injecting sodium hypochlorite in the floor level branch line (Est Domestic water system flow rate 12-16gpm, pressure 60- 80psig) at 2mg/L to 5mg/L. Flow paced chemical feed pump is preferred. Connection to BAS is not required, this will be a manually operated system only.
The chemical feeder in B3 is an existing AEGIS I controller with LMI feeder pump.
Upgrade the controller to AEGIS II to provide BACnet connection to BAS.
2. P-502 Plumbing Detail 1 Note F6 says “Provide Insulation Pads” for the Mixing valve, however Watts (Basis of Design) does not know of any type of insulation pad that is designed to work with this valve nor do they feel it is needed. Will you please clarify the design intent for insulation pad?
The insulation pad is simply a removable insulation pad/blanket for valves, devices, etc.
requiring routine maintenance. We can omit this requirement, since it’s hard to find one for a small size thermo-mixing valve.
3. What is the Basis of Design for the Backflow Preventer?
¾” to 2” pipe: Zurn Model 975XL
2.5” or greater pipe: Zurn Model 350 with butterfly valves.