36C25919R0090-0005000.docx
DOCX document 19 KB Posted
- Attached to
- Replace Air Handling Units Federal contract opportunity
- Solicitation number
- 36C25919R0090
About this file
36C25919R0090 0005 36C25919R0090 0005.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25919R0090-0007000.docx | DOCX document | |
| 36C25919R0090-0006000.docx | DOCX document | |
| 36C25919R0090-0004001.pdf | ||
| 36C25919R0090-0004002.pdf | ||
| 36C25919R0090-0004003.pdf | ||
| 36C25919R0090-0004000.docx | DOCX document | |
| 36C25919R0090-0003000.docx | DOCX document | |
| 36C25919R0090-0002000.docx | DOCX document | |
| 36C25919R0090-0002003.pdf | ||
| 36C25919R0090-0002001.pdf | ||
| 36C25919R0090-0002002.pdf | ||
| 36C25919R0090-0001001.pdf | ||
| 36C25919R0090-0001000.docx | DOCX document | |
| 36C25919R0090-0001002.pdf | ||
| 36C25919R0090-001.docx | DOCX document | |
| 36C25919R0090-007.pdf | ||
| 36C25919R0090-006.pdf | ||
| 36C25919R0090-004.docx | DOCX document | |
| 36C25919R0090-002.pdf | ||
| 36C25919R0090-005.docx | DOCX document | |
| 36C25919R0090-003.pdf | ||
| 36C25919R0090-000.docx | DOCX document |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 05-24-2019 623-15-104 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 To all Offerors/Bidders
36C25919R0090 04-17-2019
X x x
May 31, 2019 at 2pm CDT The purpose of this amendment is to answer questions and extend solicitation.
Solicitation now closes May 31, 2019 at 2:00 PM CDT.
All other terms and conditions remain unchanged.
Please refer to questions 5, 6 & 7 from the questions and answers and the notes from the Phasing plan sheet GI501 that states;
“-Only one room may be worked on at a time for each floor.
-Contractor shall move furniture and equipment out of the room or cover it when working in the room or cover it when working in the room. Rooms shall be retuned for VA use during normal working hours the following day by 6:00 am.”
Q&A question 5: Details 3/GI501 and 4/GI501 show a suspended plastic zipper wall barrier curtain system. Please clarify which rooms this would apply to. Answer: If construction dust/debris is contained, zippered poly barriers may be used when work is < 1 eight hour shift. Otherwise, use engineered rigid boundary per Sheet Note 3, Dwg GI401 Q&A question 6: Please list all of the areas that will be required to be functional at the end of each night/ weekend shift. IE: areas incorporated in plan pages AD105. Answer: All areas are required to be functional at the end of each night/weekend shift. There is no swing space available.
Q&A question 7: If areas of construction are required to be functional at the end of each shift, will temporary construction methods be acceptable, IE: visqeen ceilings etc. or will permanent construction be expected? Answer: Permanent construction is expected.
New question: Due to the multiple trades that will need to work in each room and the restriction of only working in one room per night, we believe it will be impossible to accomplish the required task to allow for turn-over of the room for the VA’s use the next day. The logistics of accomplishing the following in one night is not possible for an eight or even 11 hour shift. The following work cannot be accomplished in one night;
1. install Infectious Controls, remove window install negative air and move furniture and exam tables out and cover everything with plastic,
2. VA inspects infectious controls, approves negative air for construction,
3. Remove ACT tiles and grid that is in the way (& at 5th floor demo the ACT grid as well with electrician make safe/support the existing lighting, fire alarm or other system or providing temp lighting)
4. HVAC remove existing ductwork & piping including hangers & supports,
5. HVAC to reinstall new piping and ductwork,
6. Fire Protection to drain system for 5th FL where ceiling is to be lowered by 2’ after and recharge the system,
7. Install new ceiling grid electrician to reinstall fire alarm, misc. PA etc. (and remove and replace light fixtures at 5th FL rooms)
8. HVAC complete ductwork diffuser drops
9. VA inspect above ceiling work
10. Complete reinstallation of tiles
11. Touch up paint if required, clean up and remove Infections controls and have VA re-inspect including window reinstallation for re-occupancy barring no infectious controls, fire alarm or life safety issues.
In lieu of this, we propose having a maximum of 3 rooms that the work can progress through. This would involve setting up a movable hard wall barrier with soft wall / plastic seals that will be left in front of the doors during the day that is lockable. Crews would work through to complete 1 room a night for turnover and start a new room. This would mean that the Contractor will have no more than 3 rooms being worked on at a time for each floor. This will ensure a much higher quality installation and all steps will be able to be inspected by the VA and is achievable for the contractor to perform. Is this change acceptable?
No. VA has no swing space. Contractor shall determine how much work can be accomplished in a shift. Multiple shifts may be required to complete one room.