Replace Air Handling Units Federal contract opportunity
Solicitation number
36C25919R0090
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

36C25919R0090 0003 36C25919R0090 0003.docx

View the file

Other files for this federal contract opportunity

Other files attached to Replace Air Handling Units, newest first.
File Type Posted
36C25919R0090-0007000.docx DOCX document
36C25919R0090-0006000.docx DOCX document
36C25919R0090-0005000.docx DOCX document
36C25919R0090-0004001.pdf PDF
36C25919R0090-0004002.pdf PDF
36C25919R0090-0004003.pdf PDF
36C25919R0090-0004000.docx DOCX document
36C25919R0090-0002000.docx DOCX document
36C25919R0090-0002003.pdf PDF
36C25919R0090-0002001.pdf PDF
36C25919R0090-0002002.pdf PDF
36C25919R0090-0001001.pdf PDF
36C25919R0090-0001000.docx DOCX document
36C25919R0090-0001002.pdf PDF
36C25919R0090-001.docx DOCX document
36C25919R0090-007.pdf PDF
36C25919R0090-006.pdf PDF
36C25919R0090-004.docx DOCX document
36C25919R0090-003.pdf PDF
36C25919R0090-002.pdf PDF
36C25919R0090-005.docx DOCX document
36C25919R0090-000.docx DOCX document
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION

OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADM

INISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and d ate specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 3

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO

MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 05-08-2019 623-15-104 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 To all Offerors/Bidders

36C25919R0090 04-17-2019

X x x ** HOUR & DATE for Receipt of Offers is EXTENDED to: May 29, 2019 at 2:00 pm MT The purpose of this amendment is to provide answers to question and extend solicitation close date.

This solicitation is extended to close on May 29, 2019 at 2:00 P.M. MDT.

All other terms and conditions remain unchanged.

1. Please provide the specification table of contents.

Attached

2. Note 8 on sheet GI401 calls for the contractor to cover the existing floor with plywood or similar material to prevent floor damage. Will the VA accept the use of roll out floor protection such as Ram Board or equal product?

In the case of Contractor removing heavy materials over carpet plywood is appropriate

3. Please confirm that the temp cooling units listed in the phasing notes, will become the property of the VA at the end of the project.

Confirmed – shall be property of VA

4. Are the temp cooling units listed in the phasing notes required to be new units? Yes If so does the VA have a specific requirement for these units? Please provide specifications.

No requirements other than tonnage listed.

5. Details 3/GI501 and 4/GI501 show a suspended plastic zipper wall barrier curtain system. Please clarify which rooms this would apply to.

If construction dust/debris is contained, zippered poly barriers may be used when work is < 1 eight hour shift. Otherwise, use engineered rigid boundary per Sheet Note 3, Dwg GI401

6. Please list all of the areas that will be required to be functional at the end of each night/ weekend shift. IE: areas incorporated in plan pages AD105.

All areas are required to be functional at the end of each night/weekend shift. There is no swing space available.

7. If areas of construction are required to be functional at the end of each shift, will temporary construction methods be acceptable, IE: visqeen ceilings etc. or will permanent construction be expected?

Permanent construction is expected.

8. Please provide specifications for roofing.

Contractor shall coordinate with TBD roofing contractor to maintain warranty.

9. What is the existing roof type as shown on sheet MD103 note 10?

Built up roof

10. Please provide contact information for the existing DDC controls contractor.

Joel Karstetter – Automated Building Systems - 918-665-3974

11. Sheet MD107 key note 4 says that if asbestos is found in the insulation, stop work and inform the COR. Does this mean that we are not required to perform asbestos removal and if found it will be considered a change to the contract?

VA will determine if ACM removal is by change to contract or removal by a third party.

12. What are the existing roof types for the C- wing North and South roofs shown on sheet MD111?

Existing is built up roof. This is expected to be replaced on another project with a new TPO roof prior to contractor setting new curbs.

13. Please provide contact info for the existing roof warranty.

TBD when roof project is awarded.

14. The electrical plans on sheet EP111 call for new heat tracing to be installed, please provide specifications for heat tracing.

See Specification 23 21 13 2.18

15. Will all employees require badging for this project?

Yes

16. Will background checks be required?

Yes

17. How long will the badging process take?

Up to 4 weeks

18. Will a location for a laydown area be provided on site?

No

19. Will a location for a construction office trailer be provided onsite?

No

20. Please provide specifications for Acoustic ceiling tile.

See Specification 09 51 00

21. Please provide a finish schedule as built for the existing areas that are affected by this project.

Finish schedule will not be provided. Match existing.

22. Exit lighting is not shown on the electrical plans, please confirm that the existing exit lighting will be reused.

Exit lighting will be re-used

23. Please confirm if personnel decontamination facilities (PDF) will be required for this project as described in section 02 82 13.13 1.9 Only if asbestos removal by contractor is necessary

24. Please confirm if waste/equipment decontamination facilities (W/EDF) will be required for this project as described in section 02 82 13.13 1.9 Only if asbestos removal by contractor is necessary

25. Please confirm that the contractor is not required to provide a industrial hygienist or VPIH/CIH for this project.

No

26. Please provide quantities for the ACM abatement required.

It is unknown if ACM abatement will be required or who will perform it. Any ACM removal by contractor would be a modification to the contract.

27. Please provide an ACM survey for the existing asbestos containing materials.

ACM survey will be reviewed with contractor prior to starting work. See question above.

28. Please confirm that water, required for the completion of the project, is available at no cost to the contractor.

Water is available at no cost. Contractor shall provide means to deliver to point of use.

29. Please confirm that Electricity, required for the completion of the project, is available at no cost to the contractor.

Electricity is available at no cost. Contractor shall provide means to deliver to point of use.

30. Can the contractor perform photographic documentation for this project, or will we be required to furnish the VA with a “Canon Powershot A480 to use for photographic documentation”?

Provide the camera to VA

31. Can the Superintendent also fulfill the roles of SSHO and CSHT if they meet the requirements of each?

Yes

32. Please clarify the ICRA Level for this solicitation.

Varies from Level I to Level III depending on work performed and location

33. Is TB Screening a requirement of this solicitation?

Yes

34. Please confirm that this project does not require whole building commissioning and that the only systems to be commissioned are the ones listed in section 01 91 00 subsection 1.6.

01 91 00 1.6 is incorrect. Systems to be commissioned are listed on Appendix A Page 55 of the Preliminary Commissioning Plan

35. Specification section 01 91 00 1.7B “Members Appointed by VA” indicates that the Commissioning Agent will be appointed by the VA and engaged under a separate contract. Please confirm that the VA will engage the commissioning agent under a separate contract, and that the contractor is NOT required to carry the cost of commissioning Commissioning Agent is provided by the A/E firm of record

36. Can demonstration and training recordings as referenced in section 01 91 00 3.7 I be performed by a member of the contractor’s organization or will the recordings need to be made by a “Commercial Photographer?”

Video tapes will not be required for this project.

37. Please confirm that any warranty referenced in the specifications, even if it modifies FAR clause 52.246-21, beyond one year is intended to be a manufacturer’s warranty for the product as referenced in the specification section All warranties over 1 year are a manufacturer’s warranty.

38. Does the test and balance of the HVAC systems need to be a third party?

Specification 230593 1.3.B.1 TAB Agency: The TAB agency shall be a subcontractor of the General Contractor and shall report to and be paid by the General Contractor.

39. Do the systems need to be commissioned by a third party?

Commissioning will be performed by third party provided by A/E of Record

40. The Fan Schedule for 1-SF-1.1 lists 20,000 CFM. The AHU Schedule for 1-AHU-1.1 lists 13,000 CFM. Which one is correct?

Modify Fan Schedule on Drawing M-607 so the Air Flow for 1-SF-1-1 is 13,000 CFM [6,100 L/s], not 20,000 CFM [9,400 L/s].

Also for clarification:

Change Sheet Key Notes 7 on MH103, 9 on MH104, and 6 on MH105 from: ”New Duct Risers.” to “New Duct Risers. Provide fire damper with access panel at all floor penetrations. Seal opening around duct at floor penetration.”:

41. Specification section 23 09 23-5 1.1 G Page 5 states this campus has standardized on an preselect controls integrator. Who is the preselected controls integrator?

Automated Building Systems of Tulsa--Joel Karstetter –918-665-3974

43. Project Phasing Notes on Sheet GI501 call for Temporary Heating and Cooling Units to be utilized during the project and units turned over to the VA at the completion of the project.

Are there any specific requirements for these temp units (I.E. Brand, Model Numbers, Etc.)?

No, other than listed tonnage

44. What is the intended function of the temp units (are the units designed to feed individual rooms, multiple rooms, common areas, Etc.)?

Intent is for contractor to use portable units to maintain space temperature if normal source of HVAC is interrupted during normal working hours.

45. Are there restrictions on where the temp units can be set up?

Yes. Reasonable access for occupants shall be maintained

46. Is it possible to provide a temporary HVAC system drawing showing the intent of this requirement?

No. Maintaining space temperatures during normal working hours is left to means and methods of the contractor.

47. Is the asbestos abatement the responsibility of the contractor or the facility?

If ACM is encountered, VA will determine whether to remove via contract modification or use a third party.

48. If contractor responsibility, what quantity should be used for estimating purposes?

N/A – see above

49. Without a given quantity it could be assumed that all of the material is asbestos or none of the material is. Would it be acceptable for the Contracting Officer to add a line item allowance of $50,000 to the bid form for abatement?

No

50. Can you please provide more information why the current NIACS 236220 was used for this solicitation?

As stated in the Scope of work, there is architectural, mechanical and electrical modifications, including ceiling modifications. As such, because of the multi-discipline aspects of this project the NAICS is 236220.

51. Is this project sales tax exempt? If the project is sales tax exempt can the government provide a sales tax exemption certificate?

Please see attached Tax Exempt Form

52. Will the Government provide comprehensive written badging requirements for the project if badging is required?

No written badging policy exists and policy is subject to change. Allow up to 4 weeks for badges to be processed. Work is not permitted without a badge.

53. Where will the designated parking area be for workers accessing the construction site?

Contractors can currently park behind Building 18 during normal working hours, but this is subject to change. Worst case, contractors will offload their materials then take the VA shuttle from Hatbox Field during normal working hours. Undesignated parking will be available at the facility after normal working hours.

54. Will the government accept the use of the industry leading Procore Project Management software as the primary submittal and data tracking tool for this project? The software is compatible with the VA’s networks and is currently in use at many VA locations.

Per contract, the AE is to provide Submittal Exchange or approved equal as the primary submittal and data tracking tool.

55. During construction in an area where the ceilings or fire suppression system will be disrupted, will NFPA 241 apply? Will the government require additional security measures beyond NFPA code such as fire watch, temporary fire alarms, adjustments to sprinkler heads, etc.

Interim life Safety Measures will be taken on a case by case basis as determined by the VA Safety officer.

56. Does the Government have a fire alarm servicer that they currently work with? What is the name and contact information of the person or persons that will need to be coordinated with for security and fire alarm and suppression systems work and/or disruptions?

ADVANCED, Oklahoma Branch Office, OK Lic #1890, 3158 S 108th E Ave, Ste 250, Tulsa, OK 74146 / POC Adam Winbury (918) 893-3444

57. Has the work area been checked for asbestos?

Asbestos surveys have been performed, but are no guarantee of asbestos free environment. If questionable material is encountered contact VA for testing.

58. What is the Governments’ policy if asbestos products are encountered during construction?

VA will either remove asbestos with a third party or will issue a modification for removal by contractor.

59. Does the Government currently have a 3rd party testing service for those items requiring testing or is the contractor free to locate and hire applicable testing firms?

Specifications that call for testing by the contractor shall be provided by the contractor.

60. Who is responsible for the utility locations?

No below ground utility locates are expected on this contract.

61. Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin.

In accordance with FAR 52.229-3, if a tariff is imposed after bid, the resulting contract amount may be increased by the amount of any after-imposed Federal tax if the Contractor certifies in writing that no amount for such newly imposed Federal excise tax or duty or rate increase was included in the contract price, as a contingency reserve or otherwise. Adversely, the contract amount may be decreased by the amount of any after-relieved tax.

62. Describe all tasks that may be required for this project as it relates to infectious control?

See Drawing GI-401 and specifications for general ICRA requirements

63. What is the level of infectious disease control rating for this site?

The ICRA Class depends on the location of work and type of work. There is no rating for the site.

64. Which company is responsible for the HVAC controls and who is the point of contact?

All controls so designated shall be integrated back to Niagara AX enterprise server. Contract Joel Karstetter at Automated Building Systems, Tulsa 918-665-3974

65. Does the SSHO have to be separate from the onsite super or project manager or can they dual hat?

Onsite superintendent can also be the SSHO if qualified.