580-20-103 Statement of Work.docx
DOCX document 26 KB Posted
- Solicitation number
- 36C25622R0102
About this file
This statement of work and related federal contract opportunity describe requirements for replacing sanitary sewer lines at a Department of Veterans Affairs medical center. The statement of work provides project details for a construction project to replace deteriorated cast iron sanitary sewer lines in the basement and first floor of Building 100 at the Michael E. DeBakey VA Medical Center in Houston, Texas. The related federal contract opportunity is a pre-solicitation notice for a firm-fixed-price construction contract with a period of performance of 300 calendar days from notice to proceed. The contract value is estimated between $1,000,000 to $2,000,000. The solicitation will be issued as a request for proposals and set aside for service-disabled veteran-owned small businesses. The North American Industry Classification System code for this project is 237110.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 580-20-103 Pre-Award Site Visit Sign-In Sheet.pdf | ||
| Hard Ceiling Basement.pdf | ||
| 36C25622R0102 0001.docx | DOCX document | |
| Sewer Line Area C Rev1.pdf | ||
| 580-20-103 Project Drawings.pdf | ||
| 580-20-103 Project Specifications.pdf | ||
| DOL Wage Determination TX20220253 dated 7-8-22.pdf | ||
| 36C25622R0102_1.docx | DOCX document | |
| SF24 Bid Bond.pdf | ||
| 36C25622R0102.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace Sanitary Sewer Lines B-100 Project No: 580-20-103 Scope of Work 1 Foreword
1.1 Contractor shall provide all labor, materials, tools, equipment, expertise, administration, supervision and transportation as necessary to perform all work in accordance with provided construction specifications, drawings, all documents attached to this contract, all terms and conditions of this contract, and this statement of work.
1.2 This document does not relieve the contractor of their professional responsibility to comply with all local and federal construction and environmental codes and to perform and complete a fully coordinated job.
2 General Project Description
2.1 The project will replace deteriorated sanitary sewer lines, in basement and 1st floor of Building 100. All construction work must adhere to the latest JCAHO, NFPA, and life safety requirements. All construction work must be performed without affecting medical center’s operations.
2.2 Work includes all labor, material, equipment, and supervision to perform the required plumbing construction work on this project including, replacing all existing 2” cast iron sanitary sewer line in Basement Interstitial space with 3” cast iron pipe, and replacing 4”, 6”, and 8” cast iron sanitary sewer line as indicated on the drawings. Sanitary sewer lines that are indicated on drawings. This Scope of Work is not considered to be a comprehensive description of work details for this project. All work shall be completed per the plans/drawings and specifications.
3 General Construction Requirements
3.1 Prior to any mobilization and construction, the contractor shall request and have an approved Infection Control Construction Permit, Construction Safety Plan, and an Interim Life Safety Measures Certification from the VAMC. Also project/construction schedule, schedule of values/prices and construction phases have to be provided and approved by VA’s COR/Project Engineer and/or Contracting Officer.
3.2 Contractor shall completely prepare site, prior to the installation of the equipment, and furnish labor, equipment and materials to perform work for this specific project as required by construction documents.
3.3 The entire project’s associated construction and temporary works shall conform to the latest VA specifications, VA Standards, energy conservation methods, EPA, OSHA, NFPA, NEC, ASHRAE, LIFE SAFETY CODE, UBC, local, Federal and industry requirements and regulations.
3.4 Project Record Drawings: The Contractor will maintain a set of Record Drawings. The Contractor will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process. The project record drawings will be available for review by the VA COR at all times.
3.5 The following milestone dates shall be incorporated into the contractor’s schedule.
3.5.1 Submittal Schedule and log shall be provided within ten (10) calendar days after Notice to Proceed. The contractor shall provide it to the Contracting Officer’s Representative (COR) for approval and shall include the dates for submission of Shop Drawings, Product Data, and Samples.
3.5.2 All Shop Drawings, Product Data and Samples shall be submitted and approved by the VA within sixty (60) calendar days after Notice to Proceed. The VA will provide the Contractor with written comments within 15 business days after receiving each submittal.
3.5.3 The Contractor shall submit a construction schedule within ten (10) calendar days after Notice to Proceed. The construction schedule shall be prepared in terms of calendar days (not working days). Once the construction schedule is submitted by the Contractor and approved by the CO, no lateness in the schedule shall be tolerated without the CO’s approval.
3.5.4 A pre-construction meeting shall be held within ten (10) calendar days after award of Contract. During the construction, the Contractor shall attend all weekly construction progress meetings. The meeting schedule and place will be discussed in the pre-construction meeting.
4 General Contract Requirement
4.1 Work as described under this contract shall be accomplished during Non-Working Hours, which are defined as 4:30 pm and 4:30 a.m., Monday through Friday, unless otherwise specifically authorized by the Contracting Officer. Contractor can work earlier or later in the day and on weekends with prior approval. Administrative work can be completed during normal work hours 7:30am thru 4:30 pm.
4.2 Pursuant to clause 52.236-8 Other Contracts incorporated by reference under section 4.33 52.252-2 Clauses Incorporated by Reference, Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. If required by the Contracting Officer, Contractor shall, at no additional cost to the VA, coordinate with other VA’s activities including but not limited to construction activities near the job site to ensure the construction work under this project will be in harmony with those activities. This coordination shall include but not limited to the careful scheduling of work commencement, equipment mobilization etc.
4.3 The following legal holidays are observed by this Government Agency:
| New Year's Day | January 1st | |
| Martin Luther King's Birthday | Third Monday in January | |
| Presidents Day | Third Monday in February | |
| Memorial Day | Last Monday in May | |
| Juneteenth | June 19th | |
| Independence Day | July 4th |
Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th and any day declared by the federal government as holiday.
5 Project Meetings
5.1 Each week the contractor shall hold a progress meeting to review progress to date and to resolve all questions for the upcoming week. The progress meeting shall include at a minimum, the Project Manager and the Superintendent representing the Contractor, the COR and the CO representing the Government. Technical supervisor (foreman), sub-contractors, suppliers, etc. shall attend when requested by the Contracting Officer. The meeting shall be same day, time, and place each week.
5.2 Meeting Minutes - The contractor shall take minutes of all meetings held relative to this project. The format must be acceptable to the Contracting Officer (CO). Minutes must include the meeting date and time; agenda; meeting location; list of participants with their affiliations, and telephone numbers; be fully descriptive of issues, problems and decisions made; and action items with names of responsible parties and deadlines. In addition, the minutes must include, as attachments, all exhibits and references distributed as handout materials, unless the materials are part of a formal submission. The contractor shall provide, via e-mail, complete copies of all minutes to all attendees within 72 hours of the meeting. All challenges to the minutes will be reflected in a revised version prepared by the contractor and CO along with the contractor and COR shall sign/initial the minutes. In the event of any disputes or challenges that can’t be resolved, the Contracting Officer shall render a final decision. Copies of updated minutes shall be distributed to the all attendees within 48 hours after change notice.
6 Safety and Security
6.1 Contract workers under this project may require a VA issued identification card before the start of construction work at the Houston VAMC. There is no charge for the badges; however, multiple trips to MEDVAMC facility maybe required.
6.2 Contract employees, including all subcontractor employees, must be TB tested and receive a flu shot (each year under the contract performance) if they will work within the VA Hospital Building 100. A letter from the prime contractor shall be submitted to the CO prior to work commencing that all staff members are TB negative and the flu shot was received.
6.3 All contract personnel are subject to inspection of personal effects when entering or leaving the project site.
6.4 Parking is rigidly controlled throughout the Medical Center. Contractor parking is only allowed in authorized areas. Contractor shall abide by all police requirements. Parking in designated patient parking areas is strictly prohibited. Parking for unloading equipment necessary to perform the work will be authorized in advance by the COR prior to starting the project.
6.5 Contractor shall abide by MEDVAMC’s policy for measures to prevent the spread of COVID. Policies may change during contract performance. COR and/or CO will provide updates as they are issued by the Facility Director. Contractor shall follow the CDC guidelines for COVID.
--- End---