36C25618B0674-003.pdf
PDF 331 KB Posted
- Attached to
- Project No. 586-16-102 "Upgrade Chiller Plant"
- Solicitation number
- 36C25618B0674
About this file
36C25618B0674 Attch 2 Revised Drawing EP0101 - POWER PLAN.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25618C0128-000.docx | DOCX document | |
| 36C25618B0674-0006000.docx | DOCX document | |
| 36C25618B0674-0005000.docx | DOCX document | |
| 36C25618B0674-0005001.pdf | ||
| 36C25618B0674-0004000.docx | DOCX document | |
| 36C25618B0674-0004001.pdf | ||
| 36C25618B0674-0003009.docx | DOCX document | |
| 36C25618B0674-0003003.pdf | ||
| 36C25618B0674-0003001.docx | DOCX document | |
| 36C25618B0674-0003007.pdf | ||
| 36C25618B0674-0003000.docx | DOCX document | |
| 36C25618B0674-0003006.pdf | ||
| 36C25618B0674-0003005.pdf | ||
| 36C25618B0674-0003002.pdf | ||
| 36C25618B0674-0003008.pdf | ||
| 36C25618B0674-0003004.jpg | JPG image | |
| 36C25618B0674-0002000.docx | DOCX document | |
| 36C25618B0674-0001000.docx | DOCX document | |
| 36C25618B0674-0001002.pdf | ||
| 36C25618B0674-0001001.pdf | ||
| 36C25618B0674-001.docx | DOCX document | |
| 36C25618B0674-005.pdf | ||
| 36C25618B0674-002.pdf | ||
| 36C25618B0674-006.pdf | ||
| 36C25618B0674-004.pdf | ||
| 36C25618B0674-000.docx | DOCX document |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A T
O M ain
1-1 T
IE
2-1
M A
IN
N1-2N2-2 MAIN MAIN
G R
O U
N D
N2-2 N1-2
J J
J
CH1DPNH1CH1DPNH2
CH1LNH1
CH1T1
CH1LNL1
CH1SWBDN1CH1SWBDN2
CH-1 CH-2
CH-6
FUTURE
CH-4CH-3
CH-5
FUTURE
CHWP-1 CHWP-2 CHWP-3 CHWP-4
CHWP-5
FUTURE
CHWP-6
FUTURE
EX
TRANSFORMER 2
E X
S P
E C
T R
A S
E R
IE
S
S W
IT
C
H B
O A
R D
CT XFMR
CT DISCONNECT
LIGHTING
CONTROL
PANEL
CHR1
CHILLED WATER PUMP
VFD LOCATIONS
CT
CTL
FCU-1
EF-1
SUMP
PUMP
SEWAGE
PUMP
SUMP
PUMP
2 SEWAGE
PUMP
JOCKY
PUMP FIRE
PUMP
FCU-2
R&E SEC. WATER PUMP
P1&P2
AIR
COMPRESSOR
AIR
DRYER
5 7
REFRIGERANT LEAK
DETECTION PANEL BAS PANEL
LIGHTING CONTROL
PANEL
1100 Clark Avenue St. Louis, Missouri 63102
T: 314.241.6250 F: 314.241.2570
JACKSON, MS
CANNON DESIGN PROJECT NO. 03640.62
© CannonDesign 2017 All rights reserved. No part of this document may be reproduced or utilized in any form, without prior written authorization by the Cannon Corporation
SEPT 13, 2017
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS: Office of Construction and Facilities Management o n e e ig h th in c h o n e fo o t 1
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Department of Veterans Affairs
VA CHILLER PLANT
586-16-102
ADDENDUM 01 04/11/2018
POWER PLAN
EP0101
TZ JMS
1. EXTEND BRANCH CIRCUITS IN THIS AREA TO THE FOLLOWING BRANCH PANELBOARDS, UNLESS OTHERWISE NOTED:
120 / 208V PANELBOARDS
CH1LNL1 - NORMAL POWER
277 / 480V PANELBOARDS
CH1LNH1 - NORMAL POWER
2. REFER TO EQUIPMENT CONNECTION / MOTOR CONTROLLER SCHEDULE FOR ALL OTHER LOADS.
BRANCH CIRCUIT NOTES :
1/4" = 1'-0"
POWER PLAN
1 2
A. CONDUIT ROUTING SHOWN AS ACCURATELY AS POSSIBLE FINAL COORDINATION SHALL BE DONE IN FIELD.
B. ALL NEW RECEPTACLES IN THE CHILLER PLANT SHALL BE GFCI.
GENERAL NOTES:
1. INTERCEPT EXISTING PULLBOX AT EXTERIOR AND UTILIZE EXISTING UNDERGROUND PATHWAY TO THE COOLING
TOWER PANELS.
2. THIS EXISTING PULL BOX WILL BE UTILIZED TO SPLICE THE NEW FEEDER FROM CH1SWBDN2 TO THE EXISTING FEEDER
THAT GOES OUT TO THE COOLING TOWER ELECTRICAL ROOM.
3. INSTALL NEW GROUND BAR AND TIE IT INTO THE THE EXISTING GROUNDING ELECTRODE SYSTEM REFER TO DETAILS
1/EP0302.
4. EXAUST FAN AND SERVICE RECEPTACLE ARE LOCATED ON THE ROOF.
5. EXACT LOCATION OF THE PUMP SHALL BE FIELD VERIFIED.
6. THE WALL SHALL BE CUT AND ROXTEC SEALS SHALL BE ADDED TO THE OPENING REFER TO DETAIL 5/EP0302 FOR
MORE INFORMATION.
7. SWITCHGREAR SHALL BE GE SPECTRA SERIES TO MEET THE WORKING SPACE AND DEDICATED SPACE CLEARENCES.
KEYED NOTES :
| Sheets |
| EP0101 - POWER PLAN |
File details come from the government source that posted it.