5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 515-22-1-390-0002 None Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 1100 Indianapolis IN 46240 Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 1100 Indianapolis IN 46240 To all Offerors/Bidders
36C25022Q0023 11-09-2021
X X X
See CONTINUATION Page X The purpose of this amendment is to respond to a request for information (RFI) provided by prospective offerers and to make changes to section B4 Price Schedule.
RFI responses are below and attached.
Updated section B4 Price Schedule is below. Utilize the new pri ce schedule when submitting responses to the subject
RFQ.
Sally L. Leitch Contracting Officer
CONTINUATION PAGE
1. Question: Please provide specifications on the Automated CHP cooling tower feed system (brand and model) and the extent to which we are expected to maintain this equipment? Normal service includes recalibrating and program equipment when onsite, but will we be expected to replace parts when they go bad or will the VA purchase replacements if needed?
Answer: Cooling tower feed system brand and mode were provided in an earlier amendment. Photo also attached. VA will purchase replacement parts if needed.
2. Question: Please provide details on the maintenance expected for the RO and Softener systems? Does this include refilling salt, changing filters, changing membranes, etc. or just normal testing and calibration while on site during monthly service visits?
Answer: Contractor shall periodically verify the proper operation of non-chemical water treatment systems which serve the boiler plant including: Feedwater, deaerator, water softener, reverse osmosis (RO), dealkalyzer, continuous blowdown, and condensate vacuum system water softener and RO systems. This shall include inspecting salt level and RO filter conditions. No adding of salt.
3. Question: Please detail what is required in item 0001AH inspect reverse osmosis system and how that differs from item 0001AE?
Answer: Answer: New price schedule clarifies requirement.
4. Question: Please provide system information on Boilers (HP, operating PSI) and Cooling towers (Tonnage, system Volume, and pictures if possible so we can price the tower cleaning job correctly)? Also please let us know if the cooling towers are on the roof or the ground or would need any special scaffolding to reach to clean?
Answer: System information on Boilers (HP, operating PSI) and Cooling towers provided in previous amendment. Cooling Towers are located on the roof. Previous clean by contractors did not need scaffolding.
5. Do you also want us to include HPC testing in accordance with the new Engineering standard requirements for Cooling Tower systems or just Legionella testing?
Answer: Only Legionella.
6. Question: The Schedule for Services description lists cooling towers in the CHP and in Building 22 as part of the SOW but the Price/Cost schedule only appears to mention 1 cooling tower?
Answer: New price schedule clarifies requirement.
7. Question: Is line item 0001AK Chemicals for ALL chemicals (boilers and cooling towers) or just for the cooling tower based on the makeup listed? If just for cooling tower, where would you like the boiler chemical to be accounted for?
Answer: New price schedule clarifies requirement.
8. Question: if the VA owns the controllers and chemical tanks at the site or if they are provided by the contractor. It doesn’t say in any of the info you provided.
Answer: VA owns the controllers but not the totes or secondary equipment.
B.4 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Water Treatment Services for Boiler Feed Water and Cooling Towers at CHP and Bldg. 22.
Battle Creek VA Medical Center In accordance with the Statement of Work
Contract Period: Base POP Begin: 12-01-2021 POP End: 11-30-2022
PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning Contractors PRODUCT/SERVICE CODE: Z1NB - Maintenance of Heating and Cooling Plants
0001AA
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Automated Chemical Feed Systems to CHP & Bldg. 22 Cooling Tower and Boiler Feed Water System
Contract Period: Base POP Begin: 12-01-2021 POP End: 11-30-2022
0001AB
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Continuous Monitoring System.
0001AC
| 1.00 |
| JB |
| __________________ |
| __________________ |
Waterside inspection of boilers, feedwater deaerator and condensate storage tank.
0001AD
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide/maintain Storage Tanks.
0001AE
| 12.00 |
| MO |
| __________________ |
| __________________ |
Monthly testing, calibration, inspection, maintenance of boiler water, reverse osmosis, and Softener Chemical Systems.
0001AF
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual Cleaning of CHP and Bldg. 22 Tower Sump, Fill and Basin.
0001AG
| 3.00 |
| JB |
| __________________ |
| __________________ |
Training for 9 operators
0001AH
| 12.00 |
| MO |
| __________________ |
| __________________ |
Inspect boiler water reverse osmosis system and condensate vac RO System.
0001AJ
| 12.00 |
| MO |
| __________________ |
| __________________ |
Legionella testing of CHP cooling tower.
0001AK
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide chemicals for Boiler Feed Water and CHP Cooling Tower, and Bldg. 22 Cooling Tower. (*based on estimated annual 1,100,000 make-up for Cooling Tower treatment.)
| 1.00 |
| JB |
| __________________ |
| __________________ |
Water Treatment Services for Boiler Feed Water and Cooling Towers at CHP and Bldg. 22.
In accordance with the Statement of Work
Contract Period: Option 1 POP Begin: 12-01-2022 POP End: 11-30-2023
1001AA
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Automated Chemical Feed Systems to CHP & Bldg. 22 Cooling Tower and Boiler Feed Water System
Contract Period: Option 1 POP Begin: 12-01-2022 POP End: 11-30-2023
1001AB
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Continuous Monitoring System.
Contract Period: Option 1
1001AC
| 1.00 |
| JB |
| __________________ |
| __________________ |
Waterside inspection of boilers, feedwater deaerator and condensate storage tank.
1001AD
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide/maintain Storage Tanks.
1001AE
| 12.00 |
| MO |
| __________________ |
| __________________ |
Monthly testing, calibration, inspection, maintenance of boiler water, reverse osmosis, and Softener Chemical Systems.
1001AF
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual Cleaning of CHP and Bldg. 22 Tower Sump, Fill and Basin.
1001AG
| 3.00 |
| JB |
| __________________ |
| __________________ |
Training for 9 operators
1001AH
| 12.00 |
| MO |
| __________________ |
| __________________ |
Inspect boiler water reverse osmosis system and condensate vac RO System.
1001AJ
| 12.00 |
| MO |
| __________________ |
| __________________ |
Legionella testing of CHP cooling tower.
1001AK
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide chemicals for Boiler Feed Water and CHP Cooling Tower, and Bldg. 22 Cooling Tower. (*based on estimated annual 1,100,000 make-up for Cooling Tower treatment.)
| 1.00 |
| JB |
| __________________ |
| __________________ |
Water Treatment Services for Boiler Feed Water and Cooling Towers at CHP and Bldg. 22.
In accordance with the Statement of Work
Contract Period: Option 2 POP Begin: 12-01-2023 POP End: 11-30-2024
2001AA
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Automated Chemical Feed Systems to CHP & Bldg. 22 Cooling Tower and Boiler Feed Water System
Contract Period: Option 2 POP Begin: 12-01-2023 POP End: 11-30-2024
2001AB
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Continuous Monitoring System.
2001AC
| 1.00 |
| JB |
| __________________ |
| __________________ |
Waterside inspection of boilers, feedwater deaerator and condensate storage tank.
2001AD
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide/maintain Storage Tanks.
2001AE
| 12.00 |
| MO |
| __________________ |
| __________________ |
Monthly testing, calibration, inspection, maintenance of boiler water, reverse osmosis, and Softener Chemical Systems.
2001AF
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual Cleaning of CHP and Bldg. 22 Tower Sump, Fill and Basin.
2001AG
| 3.00 |
| JB |
| __________________ |
| __________________ |
Training for 9 operators
2001AH
| 12.00 |
| MO |
| __________________ |
| __________________ |
Inspect boiler water reverse osmosis system and condensate vac RO System.
2001AJ
| 12.00 |
| MO |
| __________________ |
| __________________ |
Legionella testing of CHP cooling tower.
2001AK
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide chemicals for Boiler Feed Water and CHP Cooling Tower, and Bldg. 22 Cooling Tower. (*based on estimated annual 1,100,000 make-up for Cooling Tower treatment.)
| 1.00 |
| JB |
| __________________ |
| __________________ |
Water Treatment Services for Boiler Feed Water and Cooling Towers at CHP and Bldg. 22.
In accordance with the Statement of Work
Contract Period: Option 3 POP Begin: 12-01-2024 POP End: 11-30-2025
3001AA
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Automated Chemical Feed Systems to CHP & Bldg. 22 Cooling Tower and Boiler Feed Water System
Contract Period: Option 3 POP Begin: 12-01-2024 POP End: 11-30-2025
3001AB
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Continuous Monitoring System.
3001AC
| 1.00 |
| JB |
| __________________ |
| __________________ |
Waterside inspection of boilers, feedwater deaerator and condensate storage tank.
3001AD
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide/maintain Storage Tanks.
3001AE
| 12.00 |
| MO |
| __________________ |
| __________________ |
Monthly testing, calibration, inspection, maintenance of boiler water, reverse osmosis, and Softener Chemical Systems.
3001AF
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual Cleaning of CHP and Bldg. 22 Tower Sump, Fill and Basin.
3001AG
| 3.00 |
| JB |
| __________________ |
| __________________ |
Training for 9 operators
3001AH
| 12.00 |
| MO |
| __________________ |
| __________________ |
Inspect boiler water reverse osmosis system and condensate vac RO System.
3001AJ
| 12.00 |
| MO |
| __________________ |
| __________________ |
Legionella testing of CHP cooling tower.
3001AK
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide chemicals for Boiler Feed Water and CHP Cooling Tower, and Bldg. 22 Cooling Tower. (*based on estimated annual 1,100,000 make-up for Cooling Tower treatment.)
| 1.00 |
| JB |
| __________________ |
| __________________ |
Water Treatment Services for Boiler Feed Water and Cooling Towers at CHP and Bldg. 22.
In accordance with the Statement of Work
Contract Period: Option 4 POP Begin: 12-01-2025 POP End: 11-30-2026
4001AA
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Automated Chemical Feed Systems to CHP & Bldg. 22 Cooling Tower and Boiler Feed Water System
Contract Period: Option 4 POP Begin: 12-01-2025 POP End: 11-30-2026
4001AB
| 12.00 |
| MO |
| __________________ |
| __________________ |
Maintain Continuous Monitoring System.
4001AC
| 1.00 |
| JB |
| __________________ |
| __________________ |
Waterside inspection of boilers, feedwater deaerator and condensate storage tank.
4001AD
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide/maintain Storage Tanks.
4001AE
| 12.00 |
| MO |
| __________________ |
| __________________ |
Monthly testing, calibration, inspection, maintenance of boiler water, reverse osmosis, and Softener Chemical Systems.
4001AF
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual Cleaning of CHP and Bldg. 22 Tower Sump, Fill and Basin.
4001AG
| 3.00 |
| JB |
| __________________ |
| __________________ |
Training for 9 operators
4001AH
| 12.00 |
| MO |
| __________________ |
| __________________ |
Inspect boiler water reverse osmosis system and condensate vac RO System.
4001AJ
| 12.00 |
| MO |
| __________________ |
| __________________ |
Legionella testing of CHP cooling tower.
4001AK
| 12.00 |
| MO |
| __________________ |
| __________________ |
Provide chemicals for Boiler Feed Water and CHP Cooling Tower, and Bldg. 22 Cooling Tower. (*based on estimated annual 1,100,000 make-up for Cooling Tower treatment.)
| GRAND TOTAL |
| __________________ |
| Period of Performance |
| Annual Total |
| Base Year |
| $ |
| Option Year 1 |
| $ |
| Option Year 2 |
| $ |
| Option Year 3 |
| $ |
| Option Year 4 |
| $ |
| Total Contract Value |
| $ |
See attached document: Automated CHP Cooling tower feed system.