PreBid meeting minutes for Prep Site for PET CT.pdf

PDF 500 KB Posted

Attached to
C1DA--Prepare Site for PET-CT 539-CSI-204
Solicitation number
36C25020B0056
Issued by

About this file

This document contains pre-bid meeting minutes and a related federal contract opportunity notice for a site preparation project. The Department of Veterans Affairs Cincinnati VAMC will issue an IFB for project 539-CSI204 to prepare the site for a new PET-CT scanner. The pre-bid meeting outlined the mechanical scope of replacing roof equipment, a humidifier, and air handler along with associated electrical work. Questions are due by September 8th and the project magnitude is between $500,000 and $1,000,000. The notice specifies this is a 100% SDVOSB set-aside with a NAICS code of 236220 and business size standard of $39.5 million. The duration shall not exceed 180 days from NTP and bonds will be required.

View the file

Other files

File Type Posted
36C25020B0056 0004.docx DOCX document
RFI LPA response.docx DOCX document
Site Visit Sign in.pdf PDF
CLARIFICATION OF BID SUBMISSIONS.docx DOCX document
36C25020B0056 0003.docx DOCX document
539-CSI-204 DRAWINGS ADDENDUM 1.pdf PDF
36C25020B0056 0002.docx DOCX document
Wage Determinations General Decision Number OH20200082.pdf PDF
36C25020B0056 0001.docx DOCX document
539-CSI-204 SPECIFICATION 2020 0127.pdf PDF
539-CSI-204 CD DRAWINGS 0127-2020.pdf PDF
Contractor Certification Regarding EMR 02.docx DOCX document
Contractor Certification Regarding EMR.docx DOCX document
RFI Form.docx DOCX document
36C25020B0056_1.docx DOCX document
WAGE DETERMINATIONS.6.23.20.docx DOCX document
539-CSI-204_Brand Name Justification Honeywell Fire Alarm -1851.docx DOCX document
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STAN Engineers Since 1981

STAN and Associates, Inc. 300 W Monument Ave, Suite 200 Dayton, Ohio 45402

937.438.0177 www.stanengineers.com

CINCINNATI VA MEDICAL CENTER

PREPARE SITE FOR PET-CT

PRE-BID WALK-THROUGH MEETING MINUTES

Client Name: Cincinnati VA Medical Center Client Location: Cincinnati, Ohio Meeting Date: August 31, 2020, 1:00pm Meeting Location: Building 3, Engineering Conference Room Project Number: 1851 Project Name: PET-CT Replacement Issue Date: September 9, 2020

The following represents my understanding of the items discussed and observed. Please contact this office within ten days if changes, additions, or corrections are required.

ATTENDEES COMPANY

Josh Schneider (JS) Patrice Richardson-Scott (PR)

CVAMC

CVAMC

Rob Hart (RH) STAN and Associates, Inc.

Jim Killian Jr. (JK) Michael England (ME) Dave Wagner (DW) Galen Jeffs (GJ) Tin Culp (TC) Scott Sturgill (SS) Neville Hughart (NH) Chris Gaskins (CG) Jason Hazelwood (JH)

Eagle Mechanical V.C.I.

V.C.I.

Calvary Contracting Northview Enterprises Northview Enterprises Eagle Mechanical Jetts Specialty E.D.G.

This meeting was for the purpose of reviewing the contract drawings and walking the project site giving contractors an opportunity to make observations and ask questions pertaining to the project in preparation for submitting their bids.

1 The meeting convened and a brief outline of the project was presented by (RH) and (JS) to the attending contractors. The mechanical work was described in basic as the replacement of a condensing unit on the third floor roof, replacement of a humidifier inside of the PET/CT room and the replacement of an above ceiling A/C unit along with associated ductwork in the PET/CT area.

2 The electrical scope was described as the work to provide electrical power and connections associated with the above mechanical changes as well as the replacement of lighting fixtures and switching in the PET/CT area. The electrical contract also includes the installation of all

Pre-Bid Walk-Through - Meeting Minutes August 31, 2020 below floor conduits, recessed wireways and power reconfigurations as needed for the installation of the new PET/CT unit. It was stressed by (RH) that there will need to be a great deal of coordination with the G.E. project manager throughout the course of the project to ensure all project requirements are met for a complete installation.

3 At the direction of (JS) the meeting attendees then took part in a walk-through of the project site that included the first floor pharmacy area which will have conduit installation work directly below the second floor PET/CT room above. The walk-through also included the second floor PET/CT area.

4 (RH) noted that there was also work scope on the third floor roof and in the basement electrical room but no contractor had interest in walking either of those two areas.

5 As questions arose during the walk-through it was noted that the bidding contractors would need to officially submit their questions to the contracting officer.

6 Upon completion of the walk-through, the meeting reconvened back in the Building 3 conference room where Patrice Richardson-Scott, the contracting officer joined the meeting.

There was a brief review of the contract drawings. Josh Schneider then noted that the final day for submitting RFIs would be September 8, 2020.

Submitted by:

STAN and Associates, Inc.

Rob Hart, Electrical Designer