This document contains an experience information sheet template and notice of a pre-solicitation for design-build services. The experience information sheet is a mandatory attachment for offerors to provide details on up to four relevant past projects. It requests information on the contractor, contract and task order details, work performed as prime or subcontractor, percentage of work, government agency and point of contact awarded to, scope of work, difficulties encountered, performance period, completion status and date, original and final contract values, and any terminations.

The related pre-solicitation notice is for replacement of an existing pedestrian bridge at the VA Caribbean Healthcare System in San Juan, Puerto Rico. The design-build project value is estimated between $1 million to $2 million, with requirements for design, construction, fencing, and bridge removal. The solicitation will be issued on November 25, 2022. Responses are due January 3, 2023. The opportunity is set aside for Service-Disabled Veteran-Owned Small Businesses. Interested parties must register in SAM.gov and be verified in VIP database to be eligible as an SDVOSB. The Department of Veterans Affairs Veterans Health Administration VISN 8 is the agency.

View the file

Other files for this federal contract opportunity

Other files attached to Y1LB--Replace AMA Bridge, newest first.
File Type Posted
S02 - Attachment_16_Letter of Commitment_(MANDATORY)_(1 page).docx DOCX document
S02 - Attachment_3 SPEC 01_32_16_17_Project Schedules (24 Pages).pdf PDF
S02 - Attachment_8_Past Performance_(FILL-IN IS MANDATORY)_(4 Pages).pdf PDF
S02 - Attachment_12_Station_672_Local Protocols for COVID-19_(1 Page).pdf PDF
S02 - Attachment_11_ Release of Claim (ROC) Form_(2 Pages).pdf PDF
S02 - Attachment_6 SPEC 01_57_19_Temporary Environmental Controls (24 Pages).pdf PDF
S02 - 12-12-2022 SOL 36C24823R0017.pdf PDF
S02 - Attachment_13_VA Supplemental Kt Req Combatting COVID-19_(2 Pages).pdf PDF
S02 - Attachment_14_Infection Control Guidelines Construction _ Renovation 11B-17-05 (11 Pages).docx DOCX document
S02 - Attachment_5 SPEC 01_42_19_Reference Standards (9 Pages).pdf PDF
S02 - Attachment_1 SOW_Exhibits A and B (4 Pages).pdf PDF
S02 - Attachment_9_EMR_(FILL-IN IS MANDATORY)_(1 Page).pdf PDF
S02 - Attachment_10_ Base Offer Price Breakdown_(FILL-IN IS MANDATORY)_(2 Pages).pdf PDF
S02 - Attachment_7 SPEC 01_35_26_Safety Requirements (37 Pages).pdf PDF
S02 - Attachment_4 SPEC 01_33_23_Shop Drawings Product Data and Samples (8 Pages).pdf PDF
S02 - Attachment_2 SPEC 01_00_00_General Requirements (24 Pages).pdf PDF
S03 - Amended Pre-Solicitation Notice 36C24823R0017_1.pdf PDF
36C24823R0017_1.docx DOCX document
36C24823R0017 Pre-solicitation (Replace AMA Bridge).docx DOCX document
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXPERIENCE INFORMATION SHEET

ATTACHMENT 15

SOL 36C24823R0017

REPLACE AMA BRIDGE

EXPERIENCE INFORMATION SHEET

PROJECT NO. [ ] Page 1 Must have a total of four (4) projects, more than 4 will not be evaluated; less than 4 may result in a lower rating.

a. Contractor Information of awarded contract (Firm Name, Address, DUNS Number and Cage Code, Phone number, POC Name, POC email, Company email)

b. Contract and/or Task Order Number and Award Date (mm/dd/yyyy)

c. Project Title/Name and Location

d. Work Performed as: Prime Contractor, Subcontractor, Joint Venture, Other (explain)

e. Percent (%) of project work performed by your company

f. If you work as subcontractor, who was the prime? Comment by Carla May: Should be a capital “I’ to if (Firm Name, Address, DUNS Number and Cage Code, Phone number, POC Name, POC email, Company email)

g. Government Agency/Company who awarded contract to offeror, and Contact Information, such Contracting Officer/Procurement Official/Point of Contract (Name, Title, Email, Phone Number).

EXPERIENCE INFORMATION SHEET

PROJECT NO. [ ] Page 2

h. Description of project’s scope of work and the offeror’s specific roles and responsibilities in the project: Describe work performed in sufficient detail to permit evaluation of project relevancy to this procurement. Detail how work performed is relevant to the effort required by the solicitation? Use continuation sheet for additional information, if necessary

EXPERIENCE INFORMATION SHEET

PROJECT NO. [ ] Page 3

i. Describe any difficulties and/or obstacles encountered during performance; steps taken toward resolution

j. Describe unforeseen conditions and how each were resolved

k. Performance Period, including contract start date (mm/dd/yyyy), and original completion date, if not completed, projected date (mm/dd/yyyy) contract start date:

original completion date, if not completed, projected completion date (mm/dd/yyyy)

l. Actual Completion Date (mm/dd/yyyy), and if not completed, why?

Actual Completion Date:

If not completed, Why?

m. Project is 50% or more complete? YES [ ] No [ ]. If “No” explain percentage of completion, if not 50% completed for any reason, rating may be lower.

n. The Offerors shall indicate if any of the contracts listed were terminated and the type and reasons for the termination.

o. Original Contract Price (Award Amount), Final Contract Price (to include all modifications, if applicable), Explain Differences.

Original Contract Price: Final Contract Price: