RFI 001 Response.pdf
PDF 82 KB Posted
- Solicitation number
- 36C24623B0011
About this file
This document contains responses to a Request for Information (RFI) regarding a construction project to improve patient privacy at the Department of Veterans Affairs Hunter Holmes McGuire VA Medical Center in Richmond, Virginia. The RFI response addresses nine questions relating to details of the construction drawings and specifications. Specific issues addressed include responsibilities for relocating existing occupants and furniture, acceptance of alternative contract management software, qualifications of the site superintendent, provision of hazardous materials reports, responsibilities for installing a patient lift system, applicability of exterior window replacement notes, and locations of fire extinguishers and cabinets.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24623B0011 0004.docx | DOCX document | |
| 17-261_Addendum 01.pdf | ||
| 3655-HH McGuire VAMC Six Month ReInspection.pdf | ||
| Asbestos Surveillance Report 06-19-2022.pdf | ||
| RFI 002 Response.pdf | ||
| RFI 003 Response.pdf | ||
| 36C24623B0011 0003.docx | DOCX document | |
| S04 Pre-Bid Site Visit Attedance Log 12-15-2022.pdf | ||
| 36C24623B0011 0002.docx | DOCX document | |
| S04 Pre bid Agenda and ATTENDANCE LOG.pdf | ||
| 36C24623B0011 0001.docx | DOCX document | |
| 652-21-106 Improve Patient Privacy 4C - Phase 2 Drawings 11-4-22.pdf | ||
| Attachment B - Contractor EMR Certification Form 2022.docx | DOCX document | |
| 652-21-106 Improve Patient Privacy 4C - Phase 2 - Specs 11-4-22.pdf | ||
| Wage Det. VA20220155 Rev 4 Dated 08192022.pdf | ||
| VAAR 852.219-77 Certification.docx | DOCX document | |
| 36C24623B0011_1.docx | DOCX document | |
| Attachment A - RFI Form B0011.doc | DOC document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION (RFI)
36C24623B0011
TO: Contract Specialist, Madeline Lucena-Pulst (email: madeline.lucena-pulst@va.gov )
RFI NO.: 001 DATE: REFERENCE:
REPLY NEEDED BY:
INFORMATION NEEDED:
1. Sheet GI-03, Phase 2 Note 1 indicates to temporarily relocate occupants from the phase 2 area to other areas. Is the VA relocating their occupants or is this the contractor’s responsibility? What is the intent for all existing loose furniture, furnishings, and equipment in those rooms (i.e. demolished, removed, relocated, moved back, remain in place) and whose responsibility is it?
2. Spec 01 00 00, Para 1.22 – will the Government accept Procore or Submittal Exchange as equivalent contract management software?
3. Spec 01 35 26 para 1.7, please confirm the Superintendent can also serve as the SSHO.
4. Sheet GI-04 sheet notes, please provide the hazardous material survey inspection reports.
5. Sheet AS-5, Legend, the Patient Lift Ceiling Track is shown as VA provided, Contractor installed (V.C). Sheet AS-09, section B states Patient Lift Track is Contractor provided, Contractor installed. Please confirm which is correct.
6. Sheet AS-15, Detail 1 and Sheet AS-04, detail both state Exterior Window (Replacement is part of the Alternate Bid Deduct
#1). Please confirm this note is not applicable to the solicitation.
7. Sheet AS-15, section 8 states PC Wall Mount System is Not in the Contract. But then it says “This Item is Furnished and
Installed by the Contractor). Please clarify that this item is not in this Construction Contract.
8. Sheet AS-07, Alcove-4 has an elevation callout for C/AS10. Please confirm callout to be C/AS9.
9. Please provide locations for fire extinguishers and cabinets.
REPLY:
1. The VA will relocate their occupants. It is the Contractor responsibility to demolish, remove and dispose all existing loose furniture, furnishings and equipment in the rooms that are part of the Demolition plan Contract Documents.
2. Yes. Procore is highly preferred.
3. Yes, Superintendent can also serve as the SSHO.
4. the hazardous material survey inspection reports will be provided during the project execution.
5. Contractor must provide all supplies, materials, personnel, equipment, tools, supervision, and other items and services required to construct a fully operational ceiling-mounted patient lift system that meet the specifications indicated in the Contract Document Specifications section 10 90 00.
6. Confirmed. Exterior window replacement is part of base contract. The VA would like manual shades.
7. Only the PC Wall Mount System will be done in house by the VA. However, it is in this contract to provide everything else showing in section 8 (i.e. phone data and power outlet, Emergency power outlet, etc.)
8. Confirmed. Yes, elevation marker for the alcove should be referencing elevation on sheet AS-09.
PROJECT NUMBER: 652-21-106 Please ensure that before submitting questions or requests for clarification that you thoroughly read the solicitation, specifications, drawings and other pertinent documents. When submitting questions on this project the
Government requires contractors to specifically identify the specification and/or solicitation section(s) or drawing number(s) in reference to the question or request for clarification submitted. No question or request for clarification will be answered by the Government unless the above requirements are met. Failure to comply may prevent the Government from responding in a timely manner.
PROJECT TITLE: Improve Patient Privacy 4C-Phase 2
PROJECT LOCATION: Department of Veterans Affairs
Hunter Holmes McGuire
VA Medical Center
1209 Broad Rock Blvd.
Richmond, Va. 23249
SUBMITTED BY: City/State:
PHONE NO.:
mailto:madeline.lucena-pulst@va.gov
9. One will be located at the Corridor C4C-3 at Column Z-23. One will be located at Corridor C4C-1 at Column Z-29.
REPLY FROM:
COR/FACILITY
DATE: 12-20-2022
ATTACHMENTS:
COPY TO: