Amendment 1.pdf

PDF 129 KB Posted

Attached to
Mineral Work Center Maintenance Federal contract opportunity
Solicitation number
278282
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

Amendment One

View the file

Other files for this federal contract opportunity

Other files attached to Mineral Work Center Maintenance, newest first.
File Type Posted
Amendment Two.pdf PDF
Return Package.pdf PDF
Solicitation.pdf PDF
Attachment 4_ec080181_window_glass.pdf PDF
Attachment 2_ea070140.13_roof.pdf PDF
WAGE DECISION.pdf PDF
Attachment 6_fa2769.09.1_Elec_Insp.pdf PDF
Attachment 3_eb070140.23_siding.pdf PDF
Attachment 8_fc2769.09.1_Plumbing_Insp.pdf PDF
Attachment 10_g2769.09.1_MinWC_sitemap.pdf PDF
Attachment 7_fb2769.09.1_ HVAC_Insp.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE Page of Pages AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 4

2. Amendment/Modification No. 3. Effective Date 4. Requisition/Purchase Req. No. 5. Project No.

1 09/11/2009 278282 2769.09.1

6. Issued By: Code 7. Administered By: Code

USDA Forest Service Sierra Cascade Province, Acquisition Group 2550 Riverside Drive Susanville, CA 96130

See Block 6

8. Name and Address of Contractor (X) 9A. Amendment of Solicitation No.

278282

9B. Dated (See Item 11) X September 1, 2009

10A. Modification of Contract No.

10B. Date Issued (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. THE HOUR AND DATE SPECIFIED FOR

RECEIPT OF OFFERS IS EXTENDED TO 9/21/2009 BY 4:30 PM.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting and Appropriation Data (If required) Not Required

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS; IT MODIFIES THE CONTRACT/ORDER NO. AS

DESCRIBED IN ITEM 14.

A. This Change Order is issued pursuant to: (specify authority) The changes set forth in item 14 are made in the Contract Order No. in item 10A.

B. The above numbered contract/order is modified to reflect the administrative changes set forth in Item 14. pursuant to the authority of FAR 43.103(b).

C. This supplemental agreement is entered into pursuant to authority of:

D. Other (specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return (1) Original copies to the issuing office.

14. Description of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Page 1 Solicitation Offer, Block 11 should read “The Contractor shall begin performance within 3 calendar days and complete it within 45 calendar days after receiving award. The performance period is mandatory.”

Page 5, item number 3, Seal Shell. Clarify treatment of existing foam wall repairs.

Page 5, item number 3d, Seal Shell. Added text to help clarify definition of metal roof openings.

Page 5, item number 3e, Seal Shell. Clarify work items for dryer vent in B-house. Clarify process for removing abandoned chimney/vents and openings. Clarify acceptable methods for sealing of bathtub plumbing holes underneath A-house.

Page 5, item number 3f, Seal shell. Clarification; each building has one stack/vent to be removed. Added detail to method of closure.

Page 6, item number 6d, Electrical Inspection and Work Items. Hard wiring and switches for appliances.

Page 7, item number 8d. General mechanical, minor repairs; remove supply ducting in basement of A-house.

By signature in Block 15B Contractor releases the Government from all claims relating to this modification. This settlement is complete accord and satisfaction. Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name and Title of Signer 16A. Name and Title of Contracting Officer

CHARLOTTE CARTER

15B. Contractor/Offeror Date Signed 16B. United States of America Date Signed

(Authorized Signature) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105 STANDARD FORM 30 (REV.10-83)

PRESCRIBED BY GSA

FAR (48CFR) 53.243

Solicitation No. 278282 Page 5 of 33 Quarters Maintenance for Mineral Work Center Amendment One

SUPPLIES/SERVICES AND PRICES/COSTS (CONT.)

DESCRIPTION AND STATEMENT OF WORK

The Lassen National Forest is undertaking a project to ensure the safety and health of occupants on three residential buildings at the Mineral Work Center.

The project consists primarily of sealing the outer and inner building envelope against rodent intrusion and repairing internal plumbing and electrical issues. All work performed under this contract shall be made rodent proof as defined in Item 3b below in addition to requirements listed here and in the attached Specifications. Window glass replacement and sealed.

Contractor must bid and be ready to perform all of items 3 through 8 to be considered for this work.

1) Mobilization

a) If contractor requires a mobilization charge for equipment, it shall be included in this item.

b) Additional equipment required for work shall be determined on a case-by-case basis and added in the applicable change order.

2) Travel Expenses

a) If contractor requires travel and lodging expenses they shall be included under this item.

b) Additional travel expenses for additional work shall be determined on a case-by-case basis and included in the applicable change order.

3) Seal shell

a) Seal or repair all outer walls/roof and foundation penetrations as specified in Attachments 2 and 3, Section

070140.13 and 070140.23 respectively.

b) Repairs shall be rodent proof. Rodent proof is defined as not having any round holes larger than a ¼” diameter or any gaps greater than ¾” long that are more than ¼” in any dimension of the opening size.

c) Repair all roof structure and roof vents to be sealed against any rodent intrusion and water leaks.

d) Seal all metal roof end openings at eaves with matching seal gaskets or spray foam. High expansion or low expansion foam may be used, however low expansion foam (i.e., Daptex ®) is recommended. If spray foam is used any foam extruding past the end of the metal roof shall be trimmed to match the end of the metal and sealed with dark brown exterior grade, satin or semi-gloss latex paint.

e) Repair penetrations through exterior walls, including bird/rodent holes and foundation vents including utility penetrations.

i) Existing foam wall repairs that have not been re-opened do not require additional work, except that they shall be painted with the same paint used to touch up new repairs.

ii) Routing of dryer vent to exterior space in B-house may require installation of crawlspace access. Such access will be added to work after award as required under Time and Materials portion of contract.

iii) Sealing of bathtub plumbing holes underneath A-house and other areas. Use of metal flashing or wood or a combination is acceptable under flooring.

f) Remove unused flue/chimney pipe vents etc.

i) Each building has one roof stack and/or ducting to be removed.

ii) For removing abandoned chimney/vents covering opening with wood at ceiling is acceptable.

iii) Roof openings shall be removed (where a cover is existing), reinforced with ⅝” or better OSB or ¾” plywood, sealed, and protected with sheet metal (or matching roofing material) and sealant.

4) Replace broken window panes

a) Repair existing windows according to Attachment 4 Section 080181. Work is summarized as follows.

b) Remove broken panes of single pane glass approximately 10” by 12” tall.

c) Remove old glazing materials, clean mounting surfaces.

d) Place a seating bead of silicone under glass pane.

e) Place new glazing around the outside of the glass panes.

f) Remove one modern vacuum sealed, dual pane, aluminum frame, glass assembly.

g) Replace in kind with like modern dual pane vacuum sealed glass assembly.

Solicitation No. 278282 Page 6 of 33

5) Install safety devices (electrical)

a) All detectors shall be hard wired (behind the wall) on a separate circuit and not switched to prevent tampering with or shutting off unit.

b) Install new smoke detectors

i) Smoke detectors shall be mounted and wired without any shut off device (except over-current protection at circuit panel).

ii) One smoke detector is required in each of the following areas:

(1) In each separate space between sleeping areas and exit door for those sleeping areas.

(2) Inside each sleeping area

(3) Inside our just outside rooms likely to be the source of fires, mechanical rooms, heater locations, etc.

iii) Each smoke detector must have battery backup, batteries to be supplied at initial installation by contractor. Low battery warning shall be included on each separate detector.

c) Install carbon monoxide detectors

i) CO detectors shall be installed in hallways outside of sleeping areas and at location of each gas fueled device.

(1) Contractor may install only one device to cover both locations where hallway and gas device are in same location.

ii) CO devices shall be installed at approximately 3’ from floor to represent build-up of CO at sleeping level of human respiration.

6) Electrical Inspection and Work Items

a) Perform a full commercial building code inspection and report all findings by line item. An example inspection is attached. The attached example is not comprehensive or exhaustive. The inspector shall use his/her judgment to ensure that all necessary safety items have been inspected. The inspection is not limited to but shall include the following items.

i) Shut off all known loads and check for current at meter, if a draw is present find it and report it.

ii) Inspect all interior wires and connections for safety and correct type and size for load.

iii) Inspect for dedicated circuits for appliances such as microwave, electric ovens, AC and Heat units.

iv) Repair or replace existing appliance wiring that is not properly wired to code.

v) Rate each branch circuit for the lowest capacity by :

(1) Circuit breaker load

(2) Wire size and run length (estimate run length)

(3) Connector types and size

vi) Properly identify and label existing circuit panels.

b) If possible repairs will be added under the Time & Materials portion of this contract for such items that cannot be foreseen such as new ‘home run’ dedicated circuits for electrical ovens, microwaves, air conditioners and heaters where a dedicated circuit is not already in place or the existing circuit wiring or connections, etc. are of inadequate size/type.

c) Inspection shall include a legible written report of all items found to be out of compliance or suspected to be unsafe.

d) Bid shall include replacement or repair of electrical connections, outlets, fixtures, etc. visible at time site visit.

i) All heating units and electric water heaters will require hard wired boxes with cutoff switches mounted at the units. Use of 20 amp wall switches for cut-off at units is acceptable. Use of surface mount armored cable to to units is acceptable.

Solicitation No. 278282 Page 7 of 33

7) Plumbing Inspection and Work Items

a) Perform a full commercial building code inspection and report all findings by line item. An example inspection is attached. The attached example is not comprehensive or exhaustive. The inspector shall use his/her judgment to ensure that all necessary safety items have been inspected. The inspection is not limited to but shall include the following items.

i) Shut of all water taps and hose bibs at that building and check for flow in line, if pressure runs up OK and no flow is present at supply then interior fixtures and exterior hose bibs are OK.

ii) Check and report static pressure at building supply point.

b) If possible repairs will be added under the Time & Materials portion of this contract for such items that cannot be foreseen such as repair or replacement of interior fixtures and hose bibs only where necessary (use 12”+ setback on hose bibs where replaced).

c) Inspection shall include a legible written report of all items found to be out of compliance or suspected to be unsafe.

d) Bid shall include replacement or repair of electrical connections, outlets, fixtures, etc. visible at time of site visit.

8) Mechanical Inspection and Work Items

a) Perform a full commercial building code inspection and report all findings by line item. An example inspection is attached. The attached example is not comprehensive or exhaustive. The inspector shall use his/her judgment to ensure that all necessary safety items have been inspected. The inspection is not limited to but shall include the following items.

i) Location of heating units for safety.

ii) Control thermostat location, type and settings.

(1) Multiple unit thermostats or multiple thermostat units may be more efficient than a single large unit on a single thermostat.

(2) Recommend programmable thermostats wherever non-programmable or broken thermostats are located.

iii) Specifically, size of heating system for capacity to heat entire building without over-running heater duty cycle.

(1) Buildings have approximately half the insulation material of a modern home and are neither uniformly nor completely insulated. Assume walls are not R-13 but 3” unfaced fiberglass for approximately R-3 to R-6 in walls and ceiling is not R-23+ but approximately R-6 to R-13.

(2) Provide calculations used or tables used to select size of heaters with inspection results.

iv) Inspect and pressure test all gas lines and all gas appliances for leaks and adequate supply pressure.

b) If possible, repairs will be added under the Time & Materials portion of this contract for such items that cannot be foreseen such as repair or replacement of interior fixtures and gas lines where necessary.

c) Inspection shall include a legible written report of all items found to be out of compliance or suspected to be unsafe.

d) Bid shall include replacement or repair of gas connections, outlets, fixtures, etcetera visible at time of site visit.

i) Remove supply ducting in basement of A-house, abandon and seal return duct at floor. Seal supply plenum holes at floor with structural repair to support nominal floor load. Seal return duct under floor with wood or metal to be rodent proof also seal floor with wood or sheet metal to prevent air communication with basement, place existing grate back in floor after opening is sealed.