This is an Estimated Schedule document for the Cass Tech project bidding process. The document outlines a comprehensive timeline beginning September 30, 2026, and extending through October 29, 2027. The project schedule includes seven major phases: GC Procurement (130 days, concluding March 30, 2027), Board Vote (30 days, concluding November 10, 2026), Contract Signed (30 days, concluding December 22, 2026), PO Issued (30 days, concluding December 22, 2026), GC Onboard for Pre-Construction/Submittals/Materials (70 days, concluding March 30, 2027), Construction (98 days, concluding August 13, 2027), and Closeout (55 days, concluding October 29, 2027). The schedule indicates that procurement activities will occur concurrently with board approval and contract execution during the fall and early winter of 2026, followed by onboarding and pre-construction activities in late 2026 and early 2027.
The document does not contain information regarding pricing terms, set asides, incumbents, funding sources, or amounts. No other salient details related to contract award criteria, payment structures, or project-specific requirements are provided in this scheduling document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task
Mode
Task Name Duration Start Finish
1 GC Procurement 130 days Wed 9/30/26 Tue 3/30/27
2 Board Vote 30 days Wed 9/30/26 Tue 11/10/26
3 Contract Signed 30 days Wed 11/11/26Tue 12/22/26
4 PO Issued 30 days Wed 11/11/26Tue 12/22/26
5 GC Onboard for Pre-Con /
Submittals / Materials
70 days Wed
12/23/26
Tue 3/30/27
6 Construction 98 days Wed 3/31/27 Fri 8/13/27
7 Closeout 55 days Mon 8/16/27 Fri 10/29/27
W T F S S M T W T F S S M T W T F
Oct 4, '26 Oct 11, '26
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Cass Tech Bidding Sche
Date: Mon 7/13/26