264100 - Facility Lighting Protection.pdf

PDF 77 KB Posted

Attached to
5650--674-22-130 Replace Bldg. 163 Roof Systems
Solicitation number
36C25722B0005
Issued by

About this file

This document includes a federal contract opportunity solicitation and related technical specifications for a facility lighting protection system. The solicitation is to replace the roof system on Building 163 at the Temple VA Health Care System in Temple, Texas. The opportunity is set aside solely for Service-Disabled Veteran-Owned Small Businesses. The specifications call for a complete, UL-certified lightning protection system for the building, including air terminals, conductors, grounding components, installation according to NFPA and UL standards. The contract value is estimated between $2-5 million. The point of contact for inquiries is Michael Walls at the listed email address. The solicitation number is 36C25722B0005 and will be posted on September 29, 2021.

View the file

Other files

File Type Posted
36C25722B0005 0006.docx DOCX document
163 asbestos report - roof.pdf PDF
RFI - Answers to Questions 1-179 - 36C25722B005 Replace Bldg. 163 Roof Systems.pdf PDF
36C25722B0005 0005.docx DOCX document
075423 Thermoplastic Polyolefin (TPO) Roofing.pdf PDF
Replace BLDG 163 Roof Systems Drawings.pdf PDF
SOLICITATION-DESCRIPTION.docx DOCX document
RFI - Answers to Questions 15-179 - 36C25722B005 Replace Bldg. 163 Roof Systems.pdf PDF
36C25722B0005 0004.docx DOCX document
Pre-Bid Sign In sheet.pdf PDF
2nd Pre-Bid Site Visit sign-in sheet.pdf PDF
36C25722B0005 0003.docx DOCX document
674-22-130 Replace BLDG 163 Roof Systems - Drawings.pdf PDF
075216.11- Cold Adhesive Styrene Butadiene Styrene Modified Bituminous Membrane 7-1-2021.pdf PDF
36C25722B0005 0002.docx DOCX document
Temple_Screening_Route_Map.pdf PDF
070150.19 - Preporation for ReRoofing 7-1-2021.pdf PDF
Temple VA Campus Map.pdf PDF
36C25722B0005 0001.docx DOCX document
079200 - Joint Sealants.pdf PDF
072200 - Roof and Deck Insulation.pdf PDF
As Built - H9.pdf PDF
As Built - S2.4.pdf PDF
076000 - Sheet Metal Flashing and Trim .pdf PDF
013323 - Shop Drawings _ Product Data and Submittals.pdf PDF
36C25722B0005_1.docx DOCX document
As Built - 27R.pdf PDF
As Built - 14 Penthouse _ Roof Plan.pdf PDF
061000 - Rough Carpentry.pdf PDF
As Built - 0016_A-106.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

10-18-2020

26 41 00 - 1

SECTION 26 41 00

FACILITY LIGHTNING PROTECTION

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies the furnishing and installation of a complete UL master labeled lightning protection system.

1.2 RELATED WORK

A. Section 07 60 00, FLASHING AND SHEET METAL: Penetrations through the roof.

1.3 SUBMITTALS

A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:

1. Shop Drawings:

a. Submit sufficient information to demonstrate compliance with drawings and specifications.

b. Show locations of air terminals, connections to required metal surfaces, down conductors, and grounding means.

c. Show the mounting hardware and materials used to attach air terminals and conductors to the structure.

2. Certifications: Two weeks prior to final inspection, submit the following.

a. Certification by the manufacturer that the lightning protection system conforms to the requirements of the drawings and specifications.

b. Certification by the Contractor that the lightning protection system has been properly installed and inspected.

c. Certification that the lightning protection system has been inspected by a UL representative and has been approved by UL without variation.

1.4 APPLICABLE PUBLICATIONS

A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.

B. National Fire Protection Association (NFPA):

70-17...................National Electrical Code (NEC)

26 41 00 - 2

780-17..................Standard for the Installation of Lightning

Protection Systems

C. Underwriters Laboratories, Inc. (UL):

96-16...................Lightning Protection Components

96A-16..................Installation Requirements for Lightning

Protection Systems

467-13..................Standard for Grounding and Bonding Equipment

PART 2 - PRODUCTS

2.1 GENERAL REQUIREMENTS

A. Lightning protection components shall conform to NFPA 780 and UL 96, for use on Class I. Aluminum materials are not allowed.

1. Class I conductors: Copper.

2. Class I air terminals: Solid copper,18 inches long, not less than

9.5 mm (3/8 inch) diameter, with sharp n ickel-plated points.

4. Ground rods: Stainless steel, 0.75 in (19 mm) diameter by 3 m (10 feet) long.

5. Ground plates: Stainless steel, not less than 20 gauge.

6. Bonding plates: Bronze, 50 square cm (8 square inches).

7. Through roof connectors: Solid copper riser bar, length and type as required to accommodate roof structure and flashing requirements.

8. Down conductor guards: Stiff copper or brass.

9. Anchors and fasteners: Bronze bolt and clamp type shall be used for all applications except for membrane roof. Adhesive type are allowed only for attachment to membrane roof materials, using adhesive that is compatible with the membrane material.

10. Connectors: Bronze clamp-type connectors shall be used for roof conductor splices, and the connection of the roof conductor to air terminals and bonding plates. Crimp-type connectors are not allowed.

11. Exothermic welds: Exothermic welds shall be used for splicing the roof conductor to the down conductors, splices of the down conductors, and for connection of the down conductors to ground rods, ground plates, and the ground ring.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Installation shall be in accordance with the NEC, as shown on the drawings, and manufacturer’s instructions.

26 41 00 - 3

B. Coordinate installation with the roofing manufacturer and roofing installer.

C. Install the conductors as inconspicuously as practical.

D. Install the down conductors within the concealed cavity of exterior walls where practical. Run the down conductors to the exterior at elevations below the finished grade.

E. Where down conductors are subject to damage or are accessible near grade, protect with down conductor guards to 2.4 m (8 feet) above grade. Bond down conductors guards to down conductor at both ends.

F. Make connections of dissimilar metal with bimetallic type fittings to prevent electrolytic action.

G. Install ground rods and ground plates not less than 600 mm (2 feet) deep and a distance not less than 900 mm (3 feet) nor more than 2.5 m

(8 feet) from the nearest point of the structure. Exothermically weld the down conductors to ground rods and ground plates in the presence of the Resident Engineer.

H. Bond down conductors to metal main water piping where applicable.

I. Bond down conductors to building structural steel.

J. Connect roof conductors to all metallic projections and equipment above the roof as indicated on the drawings.

K. Connect exterior metal surfaces, located within 900 mm (3 feet) of the conductors, to the conductors to prevent flashovers.

L. Maintain horizontal or downward coursing of main conductor and insure that all bends have at least an 200 mm (8 inches) radius and do not exceed 90 degrees.

M. Conductors shall be rigidly fastened every 900 mm (3 feet) along the roof and down to the building to ground.

N. Air terminals shall be secured against overturning either by attachment to the object to be protected or by means of a substantial tripod or other braces permanently and rigidly attached to the building or structure.

O. Install air terminal bases, cable holders and other roof-system supporting means without piercing membrane or metal roofs.

P. Use through-roof connectors for penetration of the roof system.

Flashing shall be provided by roofing contractor in accordance with

Section 07 60 00, FLASHING AND SHEET METAL.

Q. Down conductors coursed on or in reinforced concrete columns or on structural steel columns shall be connected to the reinforcing steel or

26 41 00 - 4 the structural steel member at its upper and lower extremities. In the case of long vertical members an additional connection shall be made at intervals not exceeding 30 M (100 feet).

R. A counterpoise or ground ring, where shown, shall be of No. 1/0 copper cable having suitable resistance to corrosion and shall be laid around the perimeter of the structure in a trench not less than 600 mm (2 feet) deep at a distance not less than 900 mm (3 feet) nor more than

2.5 M (8 feet) from the nearest point of the structure.

S. On construction utilizing post tensioning systems to secure precast concrete sections, the post tension rods shall not be used as a path for lightning to ground.

T. Where shown, use the structural steel framework or reinforcing steel as the down conductor.

1. Weld or bond the non-electrically-continuous sections together and make them electrically continuous.

2. Verify the electrical continuity by measuring the ground resistances to earth at the ground level, at the top of the building or stack, and at intermediate points with a sensitive ohmmeter. Compare the resistance readings.

3. Connect the air terminals together with an exterior conductor connected to the structural steel framework at not more than 18 M

(60 feet) intervals.

4. Install ground connections to earth at not more than 18 M (60 feet) intervals around the perimeter of the building.

5. Weld or braze bonding plates to cleaned sections of the steel and connect the conductors to the plates.

6. Do not pierce the structural steel in any manner. Connections to the structural steel shall conform to UL 96A.

3.2 ACCEPTANCE CHECKS AND TESTS

A. Test the ground resistance to earth by standard methods, and conform to the ground resistance requirements specified in Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS.

B. A UL representative shall inspect the lightning protection system.

Obtain and install a UL numbered master label for each of the lightning protection systems at the location directed by the UL representative and the Resident Engineer.

---END---