22-0022 Maintain Airfield Pavements Rubber Removal-SoW.pdf

PDF 89 KB Posted

Attached to
FY22 Runway Rubber Removal Federal contract opportunity
Solicitation number
FA4661-22-Q-0003
Issued by
Department of the Air Force Global Strike Command

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

January 10, 2022

STATEMENT OF WORK

FOR

FNWZ 22-0022 MAINTAIN AIRFIELD PAVEMENTS RUBBER REMOVAL RW/LZ

Project #: _FNWZ 22-0022 “Maintain Airfield Pavements Rubber Removal RW/LZ

Civil Engineering Point of Contact (Name/phone #): __John Ford 325-696-5618_____________

Scope of Work: 1- Perform rubber removal as indicated in attached drawings C1 through C3 and per specifications at runways 16/34 and 164/344.

Two rubber removals are required for runway 16/34 and one for runway 164/344.

2- Paint airfield markings as indicated in attached drawings C1 through C3 following contract specifications.

Phasing Requirements: This contract shall be performed in two phases:

Phase 1: immediately after contract award -Perform rubber removal at runways 16/34 and 164/344 (Tye LZ); only weekend work -Perform re-painting of airfield markings as indicated in attached drawings sheets C1-C3 Phase 2: to be determined but to be completed before September 30, 2022 -Perform rubber removal at runway 16/34 -Perform re-painting of airfield markings as indicated in attached drawings sheets C1-C3

Special Requirements/Security/Submittals:

Contractor shall coordinate with the contracting officer (CO and the airfield manager (AM), at least 45 days prior, the weekends when rubber removal and runway pavement markings will be allowed.

Project is in a General/Controlled Area: work under this contract is in the main runway. Access to it is subject to operations requirements and only after it has been coordinated with the CO in conjunction with the AM and 7 CES.

FOR OFFICIAL USE ONLY

Performance Time/Desired Project Completion Date: 210 days

Additional/Other Information: none

1. REMOVE RUBBER WITHIN THE INDICATED AREA PER

SPECIFICATIONS SECTION 2K "RUBBER REMOVAL" OF THE REPAIR

AIRFIELD PAVEMENTS IDIQ CONTRACT. REFER TO GENERAL NOTE

#1 ABOVE FOR PHASING REQUIREMENTS.