This is a Job Specific General Provisions document for Rhode Island Contract No. 2026-CH-034, issued by the Rhode Island Department of Transportation (RIDOT) for pavement improvements on Putnam Pike from Danecroft Avenue to 300 feet west of George Waterman Road in Smithfield and Johnston, Providence County. The contract encompasses full-width micro-milling and overlay, traffic signal installation and upgrades, pedestrian signal improvements, pavement markings, ADA-compliant wheelchair ramps, cement concrete curbing, sidewalks, and associated incidental work. The project involves 106 bid line items including clearing and grubbing (300 square yards), earth excavation (3,700 cubic yards), hot mix asphalt (100,500 square yards), Portland cement concrete sidewalks (15,000 square yards), precast concrete curb (13,600 linear feet), and pavement markings (90,000 linear feet). Bids are due August 14, 2026 at 1:00 p.m. EDT with a submission deadline for questions on August 5, 2026. The work must achieve Substantial Completion by September 8, 2028, with Final Acceptance by June 7, 2029, with liquidated damages of $2,350 per day assessed for non-compliance with completion dates.

The project is federally funded under the Federal-Aid Highway program with mixed funding sources: Federal-Aid Project No. STP-RESF(482) at 80 percent FHWA and 20 percent State funding, and Federal-Aid Project No. STP-RESF(497) at 100 percent FHWA funding. A bid bond of 5 percent of total bid is required, and the successful bidder must provide a performance bond of 100 percent of contract price with a Federal Register Circular 570-listed surety. The contract includes prevailing wage requirements under the Davis-Bacon Act and Work Hours Act of 1962, plus a 0.33 percent contract administrative fee. Required insurance includes general liability at $1 million combined single limit, workers compensation at $100,000 each accident, and automobile liability at $1 million each occurrence. Price adjustments apply to Liquid Asphalt Cement at a base price of $712.00 per ton and Diesel Fuel at $3.7242 per gallon. Bidders must comply with Buy America requirements per the Infrastructure Investment and Jobs Act, the Rhode Island Diesel Emissions Reduction Act, and federal and state procurement regulations, including certifications covering anti-collusion, debarment, conflicts of interest, DBE special provisions, EEO requirements, and OMB lobbying forms. Submissions must be made electronically through Ocean State Procures, with late or misdirected submissions not accepted.

Text of this file

STATE OF RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND CONTRACT NO. 2026-CH-034

FEDERAL-AID PROJECT NOS. STP-RESF(482),

STP-RESF(497)

PAVEMENT IMPROVEMENTS

PUTNAM PIKE

Danecroft Avenue to 300’ west of George Waterman Road

Towns of Smithfield and Johnston

County of Providence

Rhode Island

GENERAL PROVISIONS-JOB SPECIFIC

GM2 Associates, Inc.

Pawtucket, Rhode Island

July 2026

INDEX

SPECIFICATIONS – JOB SPECIFIC

CODE TITLE PAGE

JS-i

Rhode Diesel Emissions Reduction Program JS-1

106.01.1 Buy American JS-2

108.1000 Prosecution and Progress JS-5

401.9901 Modified Class 9.5 HMA With Pay Adjustments PG76e-34 JS-6

702.9902 ADA Frame and Grate JS-7

704.9901 Reconstruct Drainage Structure JS-8

711.9901 Infiltration Swale (STU-PRW-100) JS-9

711.9902 Sand Filter System (STU-PRW-518) JS-11

817.9901 Repairs to Reaper Brook Culvert JS-13

938.1000 Price Adjustments JS-14

999.9901 Miscellaneous Work JS-15

T11.9910 Dual Mast Arm (25x50) Gal Steel Traffic Signal Post & Fndn. Std 19.2.0 JS-16

T12.0300 Modify Existing Traffic Signal Controller/Cabinet JS-17

T12.9901 Field Monitoring Unit (FMU) JS-18

T12.9904 Point to Point Ethernet Radio Unit JS-24

T12.9910 Remove Existing Controller And Appurtenances And JS-27

Install In New Cabinet On New Foundation

T12.9911 Remove Existing Cabinet, Controller, And Appurtenances and Install On New Foundation

T12.9921 Reconfigure Adaptive Control JS-29

T12.9922 Remove, Relocate, Reconfigure Antenna JS-31

T13.9901 Video and Radar Vehicle Detection System JS-32

T13.9904 Extension Bracket for Pedestrian Detector JS-40

T13.9911 Meter Socket w Manual Bypass JS-41

Date: 6/24/24

RICN: 2026-CH-034

RHODE ISLAND DIESEL EMISSIONS REDUCTION PROGRAM

The Rhode Island Department of Transportation (RIDOT) is conducting a Program in accordance with the Environmental Protection Agency’s (EPA) National Clean Diesel Campaign

(NCDC) initiative to reduce pollution from diesel engines throughout the country, including vehicles on highways, city streets, construction sites, and ports.

The Program is necessary in order to achieve the pressing public health and environmental goals outlined Chapter 31-47.3 of the Rhode Island General Laws entitled "The Diesel Emissions

Reduction Act". This act shall be known and may be cited as "An Act Concerning Government

Responsibility To Protect Public Health From Diesel Pollution.”, which aims to reduce emissions from diesel engines through an anti-idling program, ultra-low sulfur diesel use requirements, and retrofitting school buses and construction equipment with filters that reduce emissions up to

90%.

STATEMENT OF INTENT TO COMPLY

State Agency: Rhode Island Department of Transportation RIC No.:

Project: County/State: /Rhode Island

Contractor:

The undersigned, on behalf of the above-named Contractor, agrees to comply with Chapter 31-47.3 of the Rhode Island General Laws entitled “The Rhode Island Diesel Emissions Reduction Act”, and associated specifications by having designated on-road and non-road (non-registered) diesel vehicles/equipment used on the project be retrofitted with a designated emissions reduction device/s.

(Signature of Contractor’s Authorized Representative) (Date)

JS-1

Job Specific RIC No. 2026-CH-034

106.01.1

BUY AMERICA JOB SPECIFICATION (BABA)

Remove Subsection 106.01.1 from the Standard Specifications in its entirety and replace with:

106.01.1 Buy America Job Specification (BABA)

Introduction:

While existing Buy America requirements previously applied to iron, steel, and certain manufactured goods, the Infrastructure Investment and Jobs Act (IIJA) expands requirements to include all manufactured products and construction materials in construction contracts that include Federal Aid funding in the construction phase. Additional information available in 23 CFR 635.410 Buy America and it’s Q&A at FHWA's Buy America Q and A for Federal-aid Program - Buy America - Contract Administration - Construction - Federal Highway Administration (dot.gov) [fhwa.dot.gov]

Purpose:

Provide materials from domestic sources when products are permanently incorporated into the work.

Ensure all manufacturing processes, including applications of coatings, occur in the United States. A coating includes all processes required to apply the coating to a product to protect or enhance the value of the product. The requirements of this JS are not applicable to equipment, tools, and temporary items, including materials left in place at the Contractor’s convenience.

Certifications:

All certifications are submitted by the prime Contractor. When submitting certifications for materials that are subject to the requirements of this specification, the certification shall be on Form provided by the Department.

Determination of Material Category:

• Foreign or Uncertified Products.

Buy America does not apply to minimal use of steel/iron materials provided that the total cost of all foreign source items used in the contract, as delivered to the project site, is less than $2500 or one-tenth-of-one percent of the total contract amount, whichever is greater.

The total value is that shown to be the cost of the steel and iron products as delivered to the project site. Contractor to keep a log of foreign source items to ensure that the minimal use threshold is not exceeded during the life of the contract.

• Manufactured Products

Provide manufactured products produced in the United States.

A manufactured product is acceptable under this provision if:

JS-2

The manufactured product was manufactured in the United States; and The cost of the components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55 percent of the total cost of all components of the manufactured product.

• Construction Materials

The category of construction materials excludes cement and cementitious materials, aggregates such as stone, sand, or gravel, or aggregate binding agents or additives.

Construction materials are materials that consist primarily of:

− Non-ferrous metals.

− plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables);

− glass (including optic glass);

− lumber; or − drywall.

Waivers:

The Contractor may submit a waiver request to the department using RIDOT procedures and form provided in the PMP document management folder. The form must reflect a detailed justification for the use of goods, products, or materials mined, produced, or manufactured outside the United States and including copies of all documentation verifying the unavailability of the material or product.

The Department will submit approved waiver requests to FHWA for review. The Contractor shall investigate and respond to any public comments made to the FHWA Office of Program Administration, indicating that a domestic supplier cannot provide the material for which a waiver has been requested.

Final approval of the Buy America Waiver request will be made by the Administrator, Federal Highway Administration. The waiver will be effective the date following publication in the Federal Register.

Contractor fully understands there is no guarantee a waiver request will be approved. Any contract delays caused by this waiver process will be the sole responsibility of the contractor.

The contractor shall be responsible for all cost associated with any of the construction materials that are permanently incorporated into the project that does not meet the requirements of this Special Provision without prior written approval from the Department, up to and including removal and replacement.

The Contractor may submit a waiver request to the department during construction:

1. Determine which type of the three waivers applies.

o Public Interest Waiver: applying the domestic content procurement preference would be inconsistent with the public interest. A waiver in the public interest may be appropriate where the approving federal agency determines that other important policy goals cannot be achieved consistent with the IIJA requirements, and the proposed waiver would not meet the requirements for a nonavailability or unreasonable cost waiver.

JS-3

o Nonavailability Waiver: for types of iron, steel, manufactured products, or construction materials that are not produced in the United States in sufficient and reasonably available quantities or of a satisfactory quality.

o Unreasonable cost waiver: the inclusion of iron, steel, manufactured products, or construction materials produced in the United States will increase the cost of the overall project by more than 25 percent. Provide documentation that no domestic alternatives are available within this cost parameter. Document in the waiver a comparison of the cost of the domestic product to the cost of the foreign product or a comparison of the overall cost of the project with domestic products to the overall cost of the project with foreign-origin products.

2. Contractor shall prepare waiver documentation including waiver form provided by RIDOT;

located in the PMP portal and submit to the Department’s Project Manager with a cc: to the Construction Manager (RE)

3. RIDOT/Project Manager to Submit waiver to Federal Highway Division.

4. Federal Highway Division submits the waiver to the Made in America Office. All waivers have to be submitted by Federal agencies to the Made in America Office. Project specific waivers require a minimum of 15 calendar day public comment period. General applicability waivers are subject to a minimum 30 calendar day public comment period. Federal agencies are responsible for performing due diligence and approving or rejecting waivers.

JS-4

SECTION 108.1000

PROSECUTION AND PROGRESS

In accordance with Section 108.08, Failure to Complete on Time, Para. a., Phased Completion, Interim Completion and Substantial Completion the following defines the Interim and

Substantial Completion Dates and Associated Liquidated Damages:

• Substantial Completion: The following fine/charge for not completing contract work according to Section 101.89 by September 8, 2028 is $2,350.00 per day.

• Final Acceptance: All Contract work shall be completed as defined by Section 105.18 by

June 7, 2029, or a Daily Charge will be deducted from any money due in the amount of

$2,350.00 per calendar day.

JS-5

CODE 401.9901

MODIFIED CLASS 9.5 HMA WITH PAY ADJUSTMENTS PG76E-34

DESCRIPTION: Modified Class 9.5 HMA with Pay Adjustments PG76E-34 shall be in accordance with Section 401 of the Standard Specifications except for the following modifications:

401.02 MATERIALS.

401.02.2. Performance Graded Asphalt Binder (PGAB). The asphalt binder shall be PG 76E-

34. The modified binder shall meet a minimum elastic recovery of 75 percent at 10°C when tested in accordance with AASHTO T 301. The base asphalt cement shall conform to AASHTO M 320 and shall be PG 58 or lower (≤ PG 58-XX) prior to modification.

JS-6

Date: 35/12/26

CODE 702.9902

ADA FRAME AND GRATE

DESCRIPTION. This item of work consists of the work actions required to prepare the site for subsequent construction operations, and the installation of an ADA compliant new frame and grate to the satisfaction of the Engineer.

MATERIALS. Materials shall be in conformance with the applicable sections of the Rhode Island

Standard Specifications for Road and Bridge Construction, Amended March 2026, with all revisions. ADA frame and grate shall be manufactured by EJ or approved equal.

CONSTRUCTION METHODS. Construction shall be in accordance with the applicable sections of the Rhode Island Standard Specifications for Road and Bridge Construction, Amended March

2026.

METHOD OF MEASUREMENT. “ADA Frame and Grate” will be measured by the number of each frame and grate actually installed in accordance with the Plans and/or as directed by the

Engineer.

BASIS OF PAYMENT. The accepted quantity of “ADA Frame and Grate” will be paid for at the contract unit bid price per each, as listed in the Proposal. This price shall constitute full compensation for furnishing and installing the ADA frame and grate, saw cutting the existing pavement structure, constructing the concrete collar, providing and maintaining temporary pavement patching, and all labor, materials, equipment, tools, and incidentals necessary to complete the work in accordance with the Plans, Specifications, and as directed by the Engineer.

JS-7

Date: 4/21/25

CODE 704.9901

RECONSTRUCT DRAINAGE STRUCTURE

DESCRIPTION. This work consists of reconstructing existing drainage structures (all types) as indicated in the Contract Documents or as directed by the Engineer, all in accordance with these

Specifications.

MATERIALS. Materials used in reconstructing existing drainage structures shall conform to the requirements of Subsection 702.02.1; Masonry Unit Construction, of the Rhode Island Department of Transportation Standard Specifications for Road and Bridge Construction, February 2026 edition, including all revisions..

CONSTRUCTION METHODS. A recommended reconstruction sequence for each drainage structure: First the structures shall be thoroughly cleaned. Next, the cast iron frames and grates are carefully removed and stockpiled. Then, the tops of the structure immediately below the castings are removed. Excavate to limit, remove corbelled section, rebuild using clay brick construction.

Backfill with gravel borrow, drill and grout dowels, replace concrete, then reset transition stones.

Construction methods to be employed in this effort shall conform to the applicable requirements as set forth in Subsection 702.03 of the Rhode Island Department of Transportation Standard

Specifications for Road and Bridge Construction, February 2026 edition, including all revisions.

METHOD OF MEASUREMENT. “Reconstruct Drainage Structure” will be measured by the number of such units actually reconstructed in accordance with the Plans and/or as directed by the

BASIS OF PAYMENT. The accepted quantity of “Reconstruct Drainage Structure” will be paid for at the contract unit price per each as listed in the Proposal. The price so-stated constitute full and complete compensation for all labor, materials and equipment for reconstructing drainage structures including, but not limited to, removing and disposing existing concrete slab and/or cone section, furnishing and installing new vertical walls and/or cone sections, removing basin sections

(all types) and/or walls, removal and disposal of existing pavement, concrete base, excavation, including excavation by hand, backfill, void filler, full depth pavement sawcut including concrete base, dowels, grouting, concrete collars, removing and resetting curbing, examining and cleaning the existing basin before and after reconstruction, the legal disposal of all surplus excavated and/or unsuitable materials, and all other incidentals required to finish the work, complete and accepted by the Engineer.

Furnishing and installing new inlet or apron stones (precast or granite) and metal frames and covers or grates will be paid for separately under the applicable bid items.

JS-8

5/20/26

CODE 711.9901

INFILTRATION SWALE (STU-PRW-100)

DESCRIPTION: This item of work shall consist of furnishing and installing the Infiltration Swale

(STU-PRW-100) as shown on the Plans, including the filter bed and media, stone baffles, erosion control blankets, discharge outfall replacements, temporary erosion controls (compost filter sock, etc.), and all preparatory (excavation, grading, etc.) and finishing work (loam, seeding, etc.)

as indicated on the Plans and/or as directed by the Engineer and in accordance with this specification, the approved submittals, and with applicable sections of the Standard

The work shall include multiple RIDOT standard bid items of work and job-specific items of work necessary to provide a complete, fully operational Infiltration Swale (STU-PRW-100), including but not limited to those specified below:

• Item Code 202.0100 – Earth Excavation

• Item Code 204. – Trimming and Fine Grading

• Item Code 206.0301 – Compost Filter Sock

• Item Code 207.0210 – Stone Baffle Check Dam

• Item Code 701.7711 – Reinforced Concrete Pipe End Section Standard 2.3.0 – All Sizes

• Item Code 703. – Filter Fabric

• Item Code 906.0320 – Precast Concrete Curb

• Item Code 920.0320 – Riprap R-3, R-4, R-5

• Item Code L01.0102 – Loam Borrow 4 Inches Deep

• Item Code L02.0107 – Seeding

• Item Code L05.0505 – Erosion Control Blanket

• Item Code M01. – Sand Filter Media

MATERIALS: All materials shall conform to the applicable sections of the Standard Specifications and special provisions included in this contract. Additional requirements are given as follows:

Sand Filter Media

Sand filter media shall meet the specifications and requirements of AASHTO M-6 concrete filter sand.

Seeding

Seeding shall consist of RIDOT Type 4 Native Seed Mix.

CONSTRUCTION METHODS: Construction methods shall conform to the applicable sections of the Standard Specifications and special provisions included in this contract. Additional requirements are given as follows.

Delivery, Storage, and Handling

JS-9

5/20/26

Deliver, store, and handle all materials for the work of this section to prevent damage. Deliver and store manufactured materials in their original containers, plainly marked with product and manufacturer’s name. Coordinate delivery of all items to the project site to prevent delays.

Protection of Filter Bed Area

The Contractor shall determine and take appropriate measures to avoid the operation of any construction vehicles or equipment within any area designated for infiltration of stormwater runoff. Furthermore, such areas shall not be used for material storage / laydown. Should such an unauthorized use occur, the soil must be suitably amended, tilled, and vegetated upon completion of construction to restore the infiltration capacity of the subgrade as directed by the

Engineer and at no additional cost to the Owner.

Operation

Prior to going online, all surface covers within the receiving drainage catchment of the stormwater practice and at all outfall locations shall be suitably established.

Maintenance

Maintenance of the stormwater practice and all associated components shall be the responsibility of the Contractor until final project completion and acceptance by the Owner.

Maintenance responsibilities include but are not limited to: routine and post-storm inspections, cleaning and flushing of drainage systems, sediment/debris removal and disposal, and restoration of any eroded surface covers or slopes.

METHOD OF MEASUREMENT: This item does not require a measurement for payment.

BASIS OF PAYMENT: The Department will pay for the completed and accepted quantities at the

Contract unit price as follows.

Pay Item Pay Unit

INFILTRATION SWALE (STU-PRW-100) LUMP SUM

The price constitutes full and complete compensation for all labor, tools, equipment, materials, and incidentals to provide the Infiltration Swale (STU-PRW-100), complete and accepted by the

JS-10

5/20/27

CODE 711.9902

SAND FILTER SYSTEM (SCP-PRW-518)

DESCRIPTION: This item of work shall consist of furnishing and installing the Sand Filter System

(SCP-PRW-518) as shown on the Plans, including the filter bed and media, sediment forebay, stone baffle, frame/grate replacement for primary outlet structure, emergency riprap spillway, conveyance swale, temporary erosion controls (compost filter sock, etc.), and all preparatory

(excavation, grading, etc.) and finishing work (loam, seeding, etc.) as indicated on the Plans and/or as directed by the Engineer and in accordance with this specification, the approved submittals, and with applicable sections of the Standard Specifications.

The work shall include multiple RIDOT standard bid items of work and job-specific items of work necessary to provide a complete, fully operational Sand Filter System (SCP-PRW-518), including but not limited to those specified below:

• Item Code 201.0428 – Remove and Dispose Frame and Cover

• Item Code 202.0100 – Earth Excavation

• Item Code 204. – Trimming and Fine Grading

• Item Code 206.0301 – Compost Filter Sock

• Item Code 207.0210 – Stone Baffle Check Dam

• Item Code 702.0501 – Frame and Grate – All Sizes and Types

• Item Code 703. – Filter Fabric

• Item Code 716. – Open Cell Concrete Block (OCB)

• Item Code 906.0320 – Precast Concrete Curb

• Item Code 920.0320 – Riprap R-3, R-4, R-5

• Item Code L01.0102 – Loam Borrow 4 Inches Deep

• Item Code L02.0107 – Seeding

• Item Code L05.0505 – Erosion Control Blanket

• Item Code M01. – Sand Filter Media

MATERIALS: All materials shall conform to the applicable sections of the Standard Specifications and special provisions included in this contract. Additional requirements are given as follows:

Open Cell Concrete Block

Open cell concrete paving stones shall be provided in accordance with Section 716 of the 2026

Standard Specifications. The Contractor shall furnish and install filter fabric, subbase, and all other incidental materials as recommended by the open cell concrete paving stone manufacturer.

Sand Filter Media

Sand filter media shall meet the specifications and requirements of AASHTO M-6 concrete filter sand.

JS-11

5/20/27

Seeding

Seeding shall consist of RIDOT Type 4 Native Seed Mix.

CONSTRUCTION METHODS: Construction methods shall conform to the applicable sections of the Standard Specifications and special provisions included in this contract. Additional requirements are given as follows.

Delivery, Storage, and Handling

Deliver, store, and handle all materials for the work of this section to prevent damage. Deliver and store manufactured materials in their original containers, plainly marked with product and manufacturer’s name. Coordinate delivery of all items to the project site to prevent delays.

Protection of Filter Bed Area

The Contractor shall determine and take appropriate measures to avoid the operation of any construction vehicles or equipment within any area designated for infiltration of stormwater runoff. Furthermore, such areas shall not be used for material storage / laydown. Should such an unauthorized use occur, the soil must be suitably amended, tilled, and vegetated upon completion of construction to restore the infiltration capacity of the subgrade as directed by the

Engineer and at no additional cost to the Owner.

Operation

Prior to going online, all surface covers within the receiving drainage catchment of the stormwater practice and at all outfall locations shall be suitably established.

Maintenance

Maintenance of the stormwater practice and all associated components shall be the responsibility of the Contractor until final project completion and acceptance by the Owner.

Maintenance responsibilities include but are not limited to: routine and post-storm inspections, cleaning and flushing of drainage systems, sediment/debris removal and disposal, and restoration of any eroded surface covers or slopes.

METHOD OF MEASUREMENT: This item does not require a measurement for payment.

SAND FILTER SYSTEM (SCP-PRW-518) LUMP SUM

The price constitutes full and complete compensation for all labor, tools, equipment, materials, and incidentals to provide the Sand Filter System (SCP-PRW-518), complete and accepted by the

JS-12

Date: 05/12/2026

RIC No: 2026-CH-034

CODE 817.9901

REPAIRS TO REAPER BROOK CULVERT

DESCRIPTION. This work shall consist of furnishing all labor, materials, tools, and equipment to repair deteriorated steel sheeting at the Rear Brook Culvert wingwall beneath Putnam Pike

(Route 44), as shown on the plans and as directed by the Engineer.

MATERIALS. Steel repair plates shall conform to ASTM A36 and shall have a minimum thickness of 1/2 inch unless otherwise shown on the plans. Plate dimensions shall be field measured by the Contractor to fully cover deteriorated areas and shall provide a minimum 1/2-inch overlap beyond the damaged limits. Welding materials and procedures shall conform to AWS D1.1 requirements. Flowable fill (Class II) shall conform to RIDOT Standard Specifications. Temporary cofferdams shall be non-invasive and shall not damage the existing culvert, wingwall, or streambed.

CONSTRUCTION METHODS. The Contractor shall field verify all dimensions prior to fabrication and shall maintain stream flow throughout all construction operations. Temporary non-invasive cofferdams shall be installed as necessary to isolate the work area and provide a dry working environment. Hand excavation shall be performed from above to expose deteriorated steel sheeting at repair locations. The Contractor shall furnish and install new 1/2-inch ASTM A36 steel repair plates and weld the plates full height to the existing steel sheeting. Plates shall be hammered as required to ensure full contact with the existing sheeting prior to welding. Continuous fillet welds shall be provided unless otherwise directed by the Engineer. Following installation of the repair plates, all voids behind the plates shall be completely filled with flowable fill. Dewatering operations shall prevent sediment migration, erosion, and downstream turbidity impacts. Upon completion of the work, all disturbed areas shall be restored to their original condition.

METHOD OF MEASUREMENT. This item will not be measured separately for payment and shall be considered a lump sum item.

BASIS OF PAYMENT. Payment for this work shall be made at the contract Lump Sum price and shall include all labor, materials, steel plates, welding, excavation, cofferdams, dewatering, flowable fill, environmental protection measures, restoration, equipment, tools, and incidentals necessary to complete the work as specified and as shown on the plans. No separate payment will be made for temporary works, excavation, dewatering, or restoration.

JS-13

Date: 6/26/26

CODE 938.1000

PRICE ADJUSTMENTS

DESCRIPTION:

a. Liquid Asphalt Cement.* The Base Price of Liquid Asphalt Cement as required to implement Subsection 938.03.1 of the Standard Specifications is $ 712.00 per ton.

* In the case of modified asphalt binder, this price adjustment provision shall only apply to the neat liquid asphalt component. This provision shall not apply to the modifier component, manufacture, storage, transportation or other associated costs.

b. Diesel Fuel. The Base Price of Diesel Fuel as required to implement Subsection

938.03.2 of the Standard Specifications is $ 3.7242 per gallon.

Current price adjustments can be found at the following web address:

http://www.dot.ri.gov/business/contractorsandconsultants.php

JS-14

CODE 999.9901

MISCELLANEOUS WORK

DESCRIPTION: This work shall consist of furnishing all labor, equipment, tools and materials to perform various supplemental items of work such as but not limited to installing new trees, isolated clearing, cleaning cross drain swales, removal of solid waste, or other items of work as directed by the Engineer.

MATERIALS and CONSTRUCTION METHODS: Materials and Methods of Construction shall conform to the applicable sections of the Rhode Island Standard Specifications for Road and Bridge Construction, February 2026, and all revisions.

METHODS OF MEASUREMENT: Item Code 999.9901 "MISCELLANEOUS WORK" shall be measured for payment by the actual cost, as approved by the Engineer for the cost of performing the work as directed by the Engineer.

BASIS OF PAYMENT: Item Code 999.9901 "MISCELLANEOUS WORK" will be paid for at the actual dollar amount. The estimated dollar figure for this item of work established by Department at 100,000 units at $1.00 each and is inserted in the proposal as an authorized amount from which the payments shall be drawn.

JS-15

CODE T11.9910

DUAL MAST ARM (25x50) GAL STEEL TRAFFIC SIGNAL POST & FNDN. STD 19.2.0

This item of work shall conform to the relevant sections of the Standard Specifications SECTION T11, Traffic Signal Mast Arms, Poles, and Foundations, and notably Subsection T11.02.4.3.

DESCRIPTION: This work includes furnishing and installing Steel Mast Arms and Poles with Foundations at the required locations.

MATERIALS: The materials for this item shall be in accordance with the applicable provisions of Subsection T11.02 of the Standard Specifications.

CONSTRUCTION METHODS: Install meter sockets with manual bypass in accordance with the applicable provisions of Subsection T11.03 of the Standard Specifications.

METHOD OF MEASUREMENT: DUAL MAST ARM (25x50) GAL STEEL TRAFFIC SIGNAL POST & FNDN. STD 19.2.0 will be measured by the unit each installed.

DUAL MAST ARM (25x50) GAL STEEL TRAFFIC SIGNAL

POST & FNDN. STD 19.2.0

EACH

The price constitutes full compensation for furnishing all labor, tools, equipment, materials, and for all other incidentals required to finish the work, complete and accepted.

JS-16

03/17/2025

CODE T12.0300

MODIFY EXISTING TRAFFIC SIGNAL CONTROLLER/CABINET

DESCRIPTION: The work under this item shall conform to the applicable requirements of Section T.12

“Traffic Signal Controllers and Cabinets”, Subsections T12.01.2; Modifications to Existing Installations, and

T12.03.2; Modifications to Existing Installations, of the Standard Specifications and the following additions:

The work consists of the necessary rewiring/wiring terminations and reprogramming in the existing controller as indicated on the plans to accommodate any phasing or timing modifications that are called for on the plans.

Also included in this item is the modification for the central cloud-based system Cubic ATMS.Now and the adaptive Synchrogreen system.

Ensure modifications are performed by a manufacturer(Cubic) authorized representative.

Three hardcopies of all programmable controller data shall be supplied by the Contractor. The recorded data shall reflect settings resident in the controller upon acceptance of the project by the Engineer and the

Owner. Modified box prints and revised cabinet door stickers are required as listed in the Standard

METHOD OF MEASUREMENT:

This item will be measured by the number of controllers modified.

BASIS OF PAYMENT:

The price for Modify Existing Traffic Signal Controller/Cabinet constitutes full compensation for furnishing all labor, equipment, tools, materials, rewiring, splicing, reprogramming, the central cloud-based system Cubic ATMS.Now and the adaptive Synchrogreen system, restoration, and incidentals required to finish the work, complete and accepted.

JS-17

CODE T12.9901

FIELD MONITORING UNIT

“Traffic Signal Controllers and Cabinets” of the Standard Specifications and the following additions. This item shall consist of furnishing and installing a Field Monitoring Unit (FMU) and software, as well as all needed accessories required for a full and complete installation, including but not limited to power adapters, Ethernet cables, and interface cables, as described herein.

MATERIALS: This work shall consist of furnishing, installing, configuring, and testing an FMU. The

FMU shall be manufactured by Applied Information (AI), Model AI-500-085-02 FMU with 4G Video and

4-Port Ethernet Switch that meets the following requirements:

A. The work under this item specifies the requirements for the FMU. The FMU shall operate independent of the brand/type of intersection controller, video or thermal detection system and battery backup system (if applicable) deployed in the traffic cabinet.

B. The FMU shall function correctly between -34 degrees C and +74 degrees C.

C. The FMU shall be provided with appropriately rated connectors that allows the FMU to be exchanged by unplugging connectors, without tools.

D. The Contractor shall develop a test plan that fully demonstrates that all requirements as defined in these specifications have been met. The test plan shall define in detail each test, and the expected result of each test. The test plan shall be submitted as part of the shop drawings and shall be subject to revisions based on review and comment by RIDOT and the design consultant. Where applicable, the Contractor shall provide manufacturer certificates of compliances to verify that the unit supplied meets a specific requirement. The test plan shall be included as part of the shop drawing submittal package.

E. The FMU shall be fully wired and integrated to the cabinet to provide monitoring and logging functions related to Controller and cabinet faults and or alarms as required by these specifications.

F. The FMU shall be configured by the Contractor to broadcast SPaT messages via the FMU manufacture mobile application. All configuration of the Geo Fences shall be completed by the Contractor including the setup of any informational messages that the Engineer or RIDOT requests.

G. The FMU shall be wired directly to the cabinet.

H. The FMU shall have an internal cellular modem running at 4G LTE.

▪ The Cellular modem shall be designed to be replaced / upgraded to 5G service when available.

▪ During the period of the Connectivity and Service Agreement, the manufacturer shall supply a

5G or newer cellular modem (when available) to be installed by RIDOT with tech support to be provided by the manufacturer.

I. The FMU shall incorporate an integrated GPS and cell modem.

JS-18

J. The configuration of the FMU shall be accomplished by accessing the internal web server with a browser. It shall be possible to configure the FMU without any special software.

K. The FMU shall be powered via a standard 120 VAC input power.

L. The FMU shall allow for the routing of the controller configuration packets to and from the controller by Ethernet for any type of controller utilized by RIDOT. In this way it shall be possible to configure the controller and utilize the controller specific software to interrogate the controller.

M. The FMU shall be configured by the Contractor to allow for the remote display and control of the connected traffic signal controller via the FMU manufacturer cloud hosted web-based software. This feature shall not require the end user to create a separate VPN connection to the FMU.

N. The FMU shall be configured by the Contractor to provide access to view the video detection camera system, including the video image of each approach, via the FMU manufacturer cloud hosted web-based software. This feature shall not require the end user to create a separate VPN connection to the FMU.

O. The FMU shall provide the VPN tunnel between the traffic signal controllers and adaptive system and

ATMS, as such the FMU will serve as the primary form of communication for adaptive signal control.

P. The FMU shall be connected to the traffic signal controller to provide for GPS time sync pulse for the traffic signal internal clock, or as directed by RIDOT of the Engineer.

Q. The FMU shall operate without requiring a static IP address. The only configuration required at the

FMU is to enter the URL of where the FMU management software is hosted.

R. The FMU shall include Ethernet communications via an Ethernet Port with RJ45 connector.

S. The FMU shall include an integrated four port Ethernet switch.

T. The FMU shall be supplied and installed to include weatherproof antennas to support operations.

U. The FMU shall be supplied, installed, and configured by the Contractor with map display management software that has the following features:

• The FMU shall include a scrollable, zoomable map display, with the intersections and other monitored devices shown as representative icons on the map. The map shall include the ability to see the intersections using Google Streetview or similar.

• The alarm status of the intersection shall be clearly indicated on the icon on the map so that the user can see at a glance which intersections are in an alarm condition.

• The map display shall also include a list of intersections, with the number and priority of alarms indicated on the list. Intersections in high priority alarm shall be moved to the top of the list, followed by medium priority, low priority and then finally by intersections not in an alarm state.

• The icons shall dynamically change to be able to clearly indicate if an intersection is offline.

• Clicking on the icon on the map shall expose a display window with the current parameters of the

JS-19

intersection shown.

• The default map display position and zoom shall be configurable by user so that the user’s view will default to show the intersections that the user is responsible for managing.

V. The FMU shall be supplied, installed and configured by the Contractor with intersection detail display management software that has the following features:

• It shall be possible to drill down, either from the map icon or from the list to a device level detail for the intersection. The following constitutes the minimum level of parameters that shall be displayed:

▪ The alarm status, with priority indicated, and a text description of the alarm (if an alarm is present for this device).

▪ The time since the last communication with the device.

▪ The following parameters (real time values, minimum for the day values, maximum for the day values, and average for the day values).

▪ The AC mains voltage (value)

▪ The battery back-up voltage (value)

▪ The cabinet temperature (value)

▪ The cabinet humidity (value)

▪ The presence of AC power (OK or Fail)

▪ The flashing status of the intersection (OK or Flashing)

▪ Stop Time status (OK or Stop Time Active)

▪ The cabinet door status (Open or Closed)

▪ The intersection fan status (Fan on or Fan off)

• It shall be possible to view graphs of each of the value parameters in graphical form over the most recent two-week period. This includes real time graphs of:

▪ The AC mains voltage

▪ The battery back-up voltage

▪ The cabinet temperature

▪ The cabinet humidity

W. The FMU shall be supplied, installed and configured by the Contractor with a diagnostics and log display management software that meets or exceeds the following:

• From the device level detail within the FMU management software, it shall be possible to drill down to get the raw data; the error logs; and the communications logs to allow a technician to fault-

JS-20

find problems.

• It shall be able to filter the logs by Device; by Device Type and/or by Group as well as between dates.

• It shall be able to print these selected logs to a local printer or a PDF file.

• It shall be able to export these logs to Excel on the local computer for further analysis.

X. The FMU shall be supplied, installed and configured by the Contractor with an alarm management software that meets or exceeds the following:

• The FMU management software shall have a comprehensive alarm generation capability.

• It shall be able to configure alarms to be generated on any parameter that indicates a value that is out of tolerance, including analog values, digital values and enumerated values.

• Alarms shall be configurable to be of Low, High or Critical Priority.

• The alarm priority shall be displayed throughout the FMU management software, on all displays using color codes such as red-critical; yellow–high; and amber-low to indicate the priority of the alarm.

• The current active alarms shall be accessible for viewing via an expandable window, to observe which alarms are active and when the alarm occurred. The highest priority alarms shall rise to the top of the list.

Y. The FMU shall be supplied, installed and configured by the Contractor with alerts management software that meets or exceeds the following:

• The FMU management software shall have a comprehensive alerting function to enable the response personnel to be notified when an abnormal situation has occurred.

• It shall be able to configure alerts to one or more personnel for each alarm. This will cause, as selected, an SMS and/or an email to be sent to the person when an alarm occurs.

• The alert notification system shall be configurable by the system user to optionally send via email and/or via SMS message when an alarm clears.

• The SMS and email alerts shall be issued within 30 seconds of the occurrence of an event which results in an alert being issued.

Z. The FMU shall be supplied, installed and configured by the Contractor with connectivity and server management software that meets or exceeds the following:

• The contractor shall supply the FMU with the FMU manufacturer’s 10-year options for

Connectivity and Service, as part of the purchase price. The activation of the cellular data plan shall not start until so directed by the Engineer. The Connectivity and Service agreement shall include at a minimum:

▪ Cellular Connectivity

▪ No cellular overage charges

JS-21

▪ Video Streaming

▪ Extended warranty on the hardware for the period of the Connectivity and Service

Agreement

▪ Over-the-air software updates

▪ Over-the-air security updates

▪ Remote Front Panel of the connected traffic signal controller

▪ SPaT Message broadcast to mobile device application

AA. The FMU shall be supplied with the unlimited video/data streaming service.

BB. The FMU shall be configured with Traffic Signal Controller remote front panel access.

CC. The FMU shall be configured to supply streaming video from the video detection system. The FMU manufacturer shall provide a web page interface to access and retrieve stored video files when paired with a video detection system.

DD. At the time of the shop drawing submittal, Contractor shall supply a detailed list of available FMU functions for RIDOT’s consideration. The returned submittal will identify which functions shall be enabled on the field deployed FMUs.

The manufacturer shall provide 2 complete sets of hard copy maintenance/user manuals for the installed equipment. Additionally, an electronic copy of the manuals shall be supplied on a USB hard drive to be left in each individual cabinet, and electronic copies shall also be provided in the shop drawing submittal. These manuals shall have complete set-up, maintenance and troubleshooting procedures presented in an organized format.

The Contractor shall submit manufacturer’s shop drawings, layout drawings and specifications for equipment and appurtenances for the approval of the Engineer, in accordance with Subsection 105.02;

Plans and Shop Drawings, of these Specifications.

The Contractor shall provide warranty and submit copies of manufacturer’s warranties, in accordance with

Subsection T10.02.1 Warranties for Traffic Signal Systems, of these Specifications.

The Contractor shall provide up to sixteen (16) hours of personnel training in the use of the FMU. The training schedule on the FMU will be TBD by RIDOT. The training may be required to be broken into two

(2) separate groups at the discretion of RIDOT. The Contractor is to coordinate with the RIDOT as to the exact location and time of the training. It is the responsibility of the Contractor to provide training manuals, class notes, and other instructional materials for up to 20 attendees at the training session. No training shall begin unless and until the final inspection process indicates, in the opinion of the Engineer, that the FMU is sufficiently complete and operational such that training would be useful at the time.

CONSTRUCTION METHODS: The Contractor shall configure and integrate the FMU to all ethernet capable devices in the Controller Cabinet (as applicable), including but not limited to the Traffic Signal

Controller unit, MMU2, video detection system and the battery backup system (if applicable). All connections shall be encrypted VPN tunnels. The Contractor shall connect the FMU to RIDOT ATMS systems via a secure VPN tunnel. The Contractor shall coordinate all configuration settings with the RIDOT

DoIT and the Engineer.

JS-22

METHOD OF MEASUREMENT: “FIELD MONITORING UNIT” will be measured by

“EACH” unit installed and accepted by the Engineer.

BASIS OF PAYMENT: The accepted quantity of “FIELD MONITORING UNIT” will be paid for at the contract unit price bid per “EACH”, which price shall include full compensation for all materials, cables, equipment, tools, configuration (including but not limited to connections to monitored in-cabinet devices and alarm configuration as requested by RIDOT), software, connectivity and service (including hardware replacement and cellular modem replacement), testing, system maintenance, final inspection and acceptance, guaranties/warranties, training, labor and work incidental thereto complete in place and accepted by Engineer.

JS-23

Date: 3/18/2026

CODE T12.9904

POINT-TO-POINT ETHERNET RADIO UNIT

DESCRIPTION: The Contractor shall furnish, install and integrate a wireless communications system as part of the traffic signal control assembly. The antennas shall be provided in pairs

(access point and client) and shall be located as shown on the plans. The wireless Ethernet radio unit shall contain provisions to link video feeds from the video detection cameras to allow remote computer monitoring and control capabilities.

MATERIALS: The radio shall be 5.8 GHz point-to-point wireless broadband Ethernet system for ITS communications. 5.8 GHz is to be used for broadband connectivity applications. The system shall consist of connectorized radios and/or radios with integrated panel antennas including but not limited to POE Injectors and POE Surge Suppression. All radios and antennas shall all be the same as to make and model. The following specifications are the minimum requirements for the 5.8 GHz broadband wireless network.

GENERAL REQUIREMENTS

The 5.8 GHz wireless broadband system shall have the following minimum general operating characteristics:

1. Shall operate in an environment with an ambient temperature range of –40˚ C to +75˚ C without the assistance of fan-forced cooling.

2. Shall operate in an environment with relative humidity of 5% to 95% (non-condensing).

3. The module shall support IEEE 802.3 protocol using the 802.11a/n standard. The module shall feature 2(two) 10/100/1000TX RJ-45 ports that support one port as an 802.3af/at PoE

Powered Device and the other port as an 802.3at PoE Power Sourcing Equipment. The module shall support two antennas utilizing MIMO technology and a maximum throughput of 500Mbps. The modules shall be encased in an IP67 dust and water immersion housing.

The module shall provide power, link, and signal strength status indicating LED’s for monitoring proper system operation. The module shall have a lifetime warranty to reduce system life cycle cost in an event of a module failure.

4. The module shall be configurable for either Client, single point Access Point or multi-point

Access Point operation.

5. Shall support transmission distances up to 2 miles (line-of-sight).

6. Shall support Spanning Tree Protocol.

7. All modules shall support passive PoE and IEEE802.3af/at PoE PD.

8. The module shall provide either auto-selectable or user static selectable frequency modes of operation.

9. The module shall support Dynamic Frequency Selection (DFS) and Transmit Power Control

(TPC) operation.

JS-24

10. The module shall provide up to +26dBm RF power output.

11. The module shall have selectable channel bandwidth capacity 20, 40 or 80MHz.

12. The module shall provide antenna alignment, signal strength, and site survey tools.

13. The module shall be available with 16 dBi gain integral antenna

14. The module shall use WPA2 – either AES or TKIP encryption.

15. The module radiated emission shall be compliant with ETSI standards.

16. The module shall be supplied in an IP67 compliant housing.

17. All modules and system parameters shall be configurable via a Graphical User Interface

(GUI).

18. The following IEEE Networking Standards shall be supported:

IEEE 802.3 10Base-T Ethernet

IEEE 802.3u 100Base-TX Fast Ethernet

IEEE 802.3ab 1000Base-T Gigabit Ethernet

IEEE 802.3af Power over Ethernet

IEEE 802.3at Power over Ethernet

IEEE 802.3D Spanning Tree Protocol (STP)

IEEE 802.11h DFS & TPC

IEEE802.1X Port-based Network Access Control

NTP Client

19. Wireless Radio Performance:

Bandwidths 20, 40, 80MHz

20. Wireless Antenna Performance:

Standard Internal Antenna Dual Polarized Directional

Gain 16dBi

Azimuth 30˚ Hor/Ver Elevation 30˚ Hor/Ver

21. Management

Configuration: Web, HTTPS, TFTP/Web Update for firmware and configuration backup/restore, DHCP Client, User configurable Watchdog and Auto-Reboot Mechanism, Reset to default, Multi-Level Configuration and Monitoring Login Accounts, User

Configurable Long Range Parameters, Admin password, Port Speed/Duplex control, status, SNMP v2c.

NTP: Network Time Protocol to synchronize time from Internet

802.1x: Port-based Network Access Control

DHCP Server

System Log

22. Electrical Specifications

JS-25

Operating Voltage: 48 - 57VDC @ 170 mA

PoE Support: IEEE 802.3af/at PD compliant, IEEE 802.3at PSE compliant

Power Consumption: 5W max

METHOD OF MEASUREMENT: “POINT-TO-POINT ETHERNET RADIO UNIT” will be measured by the number of units (antennas shall be provided in pairs - access point and client) installed.

BASIS OF PAYMENT: The Department will pay for the completed and accepted quantities at the Contract unit prices as follows:

POINT-TO-POINT ETHERNET RADIO UNIT EA

The price constitutes full compensation for furnishing and installing all materials (antennas shall be provided in pairs - access point and client), equipment, tools, testing, field adjustments, labor, and all incidentals required to finish the work, complete and accepted.

JS-26

Date: 11/20/25

CODE T12.9910

REMOVE EXISTING CONTROLLER AND APPURTENANCES AND INSTALL IN

NEW CABINET ON NEW FOUNDATION

CODE T12.9911

REMOVE EXISTING CABINET, CONTROLLER, AND APPURTENANCES AND

INSTALL ON NEW FOUNDATION

DESCRIPTION. This work includes relocating the cabinet, controller, and all other components to a new foundation supplied as part of this item, or relocating the controller and all other appurtenances to a new cabinet on a new foundation, all in conformance with Section T12 – TRAFFIC SIGNAL CONTROLLERS AND CABINETS, of the Rhode Island Standard

Specifications for Road and Bridge Construction, Edition as included under this contract.

MATERIALS. Ensure new materials conform to Section T12 – TRAFFIC SIGNAL

CONTROLLERS AND CABINETS, of the Rhode Island Standard Specifications for Road and

Bridge Construction, Edition as included under this contract.

• Furnish and install a new traffic signal cabinet(P-size) on new foundation or furnish a new foundation for an existing cabinet to be transferred to. Ensure cabinet and foundation are appropriately sized to accommodate transferred equipment.

• Ensure any locations with Battery Backup Systems are properly accommodated with applicable foundations to support BBS cabinet and include any stainless steel…

This is the start of the file's text. The full file is on GovTribe.

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .