2-Inspection Quantity Schedule.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- Request for Proposals - Materials Testing and Special Inspections Horace Mann Elementary
- Solicitation number
- 2025-26-0020
- Issued by
- Cass County, North Dakota
About this file
This is an Inspection Quantity Schedule for materials testing and special inspections services for the Horace Mann Elementary School construction project in Fargo Public Schools, North Dakota. The schedule outlines estimated inspection quantities across nine categories of work: earthwork and soils, concrete construction, masonry construction, structural steel and metal fabrications, precast concrete field erection and connections, structural framing, roofing systems, fire-resistive assemblies, and other required inspections. Specific inspection items include subgrade observation and bearing capacity verification (8 visits), soil compaction testing (40 tests), concrete sampling and testing (60 sets for sampling with 60 sets for cylinders and 240 individual cylinder breaks), reinforcing steel inspection (25 visits), field weld inspection (8 visits), non-destructive testing (10 tests), and roof-related inspections including insulation observation (6 visits), fastener verification (4 visits), and flashing detail verification (4 visits). The schedule also includes project management and reporting requirements as lump sum items, specifically project coordination and scheduling (1 lump sum) and a final summary report with certificate of compliance (1 lump sum).
Respondents are required to provide their own anticipated quantities based on professional judgment and experience with similar projects, with actual billing on a time-and-materials basis at agreed-upon unit rates. The schedule includes sections for hourly rates by personnel classification (Project Manager, Senior Special Inspector, Field Technician roles, Certified Welding Inspector, NDT Technician, and Laboratory Technician) and reimbursable expenses including mileage, per diem, nuclear density gauge daily rental, and other equipment costs. Respondents must provide narrative justification for any quantities that differ significantly from the Owner's estimates. The document requires firm name, date, and authorized signature upon submission.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Inspection Quantity Schedule
| Fargo Public Schools — Horace Mann Elementary School |
| Materials Testing & Special Inspections — Inspection Quantity Schedule |
| INSTRUCTIONS: Green cells show the Owner’s estimated quantities for evaluation reference. Yellow cells must be completed by the Respondent. |
| Respondents shall provide their own anticipated quantities based on their professional judgment and experience with similar projects. Provide a brief narrative justification for any quantities that differ significantly from the Owner’s estimate. Actual billing will be on a T&M basis at the agreed-upon unit rates. |
| Item | Description | Owner’s | |
| Est. Qty | Unit | Respondent’s | |
| Anticipated Qty | Unit Rate | Extended Price |
(Col E × Col F)
| A. EARTHWORK / SOILS | ||||
| A1 | Subgrade observation and bearing capacity verification | 8 | Each visit | $0.00 |
| A2 | Soil compaction testing — nuclear density gauge (ASTM D6938) | 40 | Each test | $0.00 |
| A3 | Structural fill placement observation | 10 | Each visit | $0.00 |
| A4 | Backfill compaction testing | 25 | Each test | $0.00 |
| A5 | Proof roll observation | 4 | Each visit | $0.00 |
| B. CONCRETE CONSTRUCTION | ||||
| B1 | Concrete sampling — slump, air, temp, unit weight (per load tested) | 60 | Each set | $0.00 |
| B2 | Compressive strength cylinders — cast and cure (set of 4) | 60 | Each set | $0.00 |
| B3 | Compressive strength testing — cylinder breaks | 240 | Each break | $0.00 |
| B4 | Concrete placement observation | 30 | Each visit | $0.00 |
| B5 | Reinforcing steel inspection — sizing, spacing, cover, positioning | 25 | Each visit | $0.00 |
| B6 | Anchor bolt / embed inspection | 8 | Each visit | $0.00 |
| C. MASONRY CONSTRUCTION | ||||
| C1 | Mortar / grout compressive strength sampling and testing | 8 | Each set | $0.00 |
| C2 | CMU / masonry installation observation | 8 | Each visit | $0.00 |
| C3 | Brick masonry pilaster construction observation | 6 | Each visit | $0.00 |
| C4 | CMU infill inspection at elevator door frames | 2 | Each visit | $0.00 |
| D. STRUCTURAL STEEL & METAL FABRICATIONS | ||||
| D1 | Field weld inspection (visual) | 8 | Each visit | $0.00 |
| D2 | Non-destructive testing (NDT) — UT or MT | 10 | Each test | $0.00 |
| D3 | High-strength bolt installation / torque verification | 6 | Each visit | $0.00 |
| D4 | Base plate and anchor bolt inspection | 4 | Each visit | $0.00 |
| E. PRECAST CONCRETE — FIELD ERECTION & CONNECTIONS | ||||
| E1 | Panel placement verification per erection drawings | 10 | Each visit | $0.00 |
| E2 | Panel connection / weld plate inspection | 10 | Each visit | $0.00 |
| E3 | Bearing pad and grouted joint inspection | 6 | Each visit | $0.00 |
| E4 | Panel bracing and temporary support observation (periodic verification of erection plan compliance — continuous on-site monitoring excluded) | 6 | Each visit | $0.00 |
| E5 | Panel joint sealant preparation inspection | 4 | Each visit | $0.00 |
| F. STRUCTURAL FRAMING | ||||
| F1 | Metal stud framing inspection — spacing, gauge, anchorage | 8 | Each visit | $0.00 |
| F2 | Load-bearing element and lateral bracing inspection | 6 | Each visit | $0.00 |
| G. ROOFING SYSTEMS | ||||
| G1 | Roof insulation and membrane installation observation | 6 | Each visit | $0.00 |
| G2 | Fastener pattern verification and pull tests | 4 | Each visit | $0.00 |
| G3 | Parapet, flashing, and drainage detail verification | 4 | Each visit | $0.00 |
| H. FIRE-RESISTIVE ASSEMBLIES | ||||
| H1 | Firestopping systems inspection at penetrations and joints | 6 | Each visit | $0.00 |
| I. OTHER REQUIRED INSPECTIONS | ||||
| I1 | Under-slab vapor barrier inspection | 4 | Each visit | $0.00 |
| I2 | Below-grade waterproofing inspection | 4 | Each visit | $0.00 |
| I3 | Anchors in concrete / masonry — post-installed | 4 | Each visit | $0.00 |
| I4 | Smoke control / damper inspections (if required) | 2 | Each visit | $0.00 |
| J. PROJECT MANAGEMENT & REPORTING | ||||
| J1 | Project management — coordination, scheduling, meetings | 1 | Lump sum | $0.00 |
| J2 | Daily field reports and documentation | — | Included | |
| J3 | Final summary report and certificate of compliance | 1 | Lump sum | $0.00 |
| TOTAL ESTIMATED PROJECT FEE | $0.00 | |||
| QUANTITY VARIANCE JUSTIFICATION: If your anticipated quantities differ significantly from the Owner’s estimates, provide a brief explanation below or in your proposal narrative. |
| HOURLY RATE SCHEDULE | ||
| Personnel Classification | Hourly Rate | |
| Project Manager | ||
| Senior Special Inspector | ||
| Field Technician — Soils | ||
| Field Technician — Concrete | ||
| Field Technician — Masonry | ||
| Certified Welding Inspector (CWI) | ||
| NDT Technician (UT/MT) | ||
| Laboratory Technician | ||
| REIMBURSABLE EXPENSES | ||
| Expense Type | Rate | |
| Mileage (per mile) | ||
| Per diem (if applicable) | ||
| Nuclear density gauge (per day) | ||
| Other equipment (describe) | ||
| Firm Name: | ||
| Date: | ||
| Authorized Signature: |