B01_RFP_Final.pdf

PDF 575 KB Posted

Attached to
Crow Creek Reservation Water Main Replacement Federal contract opportunity
Solicitation number
19-102-SOL-00014
Issued by
Department of Health and Human Services Indian Health Service

About this file

Request for Proposal (RFP)

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT TABLE OF CONTENTS:

Section Taxonomy Section A Standard Form 1442 Section B Schedule of Items Section C Description and Specification (Statement of Work) Section D Packaging and Markings Section E Inspection and Acceptance Section F Deliveries or Performance Section G Contract Administration Data Section H Special Contract Requirements Section I Contract Clauses Section J List of Documents, Exhibits Section K Representations and Certifications Section L Instruction, Conditions and Notices Section M Evaluation Factors for Award

Proposals must set forth full, accurate, and complete information as required by this request for proposal (including attachments). The penalty for making false statements in proposals is prescribed in 18 U.S.C. 1001.

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

19-102-SOL-00014

Indian Health Service (IHS) Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1650 Seattle, WA 98104

Indian Health Service – Division of Engineering Services Seattle is issuing a Request for Proposal (RFP)

19-102-SOL-00014

Project Number AB-14-F56

CROW CREEK WATER MAIN REPLACEMENT

Proposals are due at 1400 (2 P.M.) local Seattle time, May 16, 2019

In accordance with FAR 36.204, this project is estimated to be between $1,000,000 and $5,000,000.

A bid bond is required.

A Site Visit can be scheduled. See Provision L.10 52.236-27 Site Visit (Construction)

Indian Health Service (IHS) Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1650 Seattle, WA 98104

Matthew Phelps (206) 613-2153 or matthew.phelps@ihs.gov

AB-14-F56

1 4104/15/2019

05/16/2019

10 days after award

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Solicitation No.: 19-102-SOL-00014 Project: Crow Creek Water Main Replacement

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

B.1. PRICE SCHEDULE

BASE Line Items

Item Description QTY Unit Unit Cost Total Cost

1 Schedule A – Water Main Construction – Alignment A 1 JB $______________ $_______________

2 Schedule B – Lee Corner Tank Site 1 JB $______________ $_______________

3 Schedule C – Water Main Construction – Alignment B 1 JB $______________ $_______________

4 Schedule D – Water Main Construction – Alignment C 1 JB $______________ $_______________

5 Schedule E – Crow Creek Tank Site 1 JB $______________ $_______________

6 Schedule F – Crow Creek Community Valves & Hydrants 1 JB $______________ $_______________

7 Schedule G – Water Service Line Construction 1 JB $______________ $_______________

8 Schedule H – Bad Nation Water Storage Tank Abandonment 1 JB $______________ $_______________

9 TERO, state, and local taxes 1 LS $______________ $______________

Total Price $_______________ Total Price shall include all TERO, State, and Local Taxes

NOTES:

Bidders are required to fill out the price schedule above as well as Attachment J07 – Price Breakdown Worksheet. Failure to provide both with proposal submission could result in elimination from the competition.

As a reminder, all bidders are responsible for allowing for all applicable state, local and tribal (where applicable) taxes and fees within their prices and to perform their own due diligence in ascertaining them. The Contractor is responsible to pay all applicable Tribal fees and/or taxes, or applicable requirements that may be incurred as a result of this project. Failure on the part of the successful Bidder/Offeror not to include these fees or the appropriate impacts will not constitute a request for an equitable adjustment to the contract price.

B.2. SF1442, Block 24: Invoices for payment shall be reviewed and signed by the COR (signature) prior to submission to the Contracting Officer. The signed payment invoice shall be sent via e-mail to IHS Contracting Officer (Matthew.Phelps@ihs.gov).

B.3. Disclosure of the Magnitude of Construction Projects (FAR 36.204): In accordance with FAR 36.204, this project is estimated to be between $1,000,000 and $5,000,000.

B.4. Incidental Payment Items – The intent of the contract is to provide for the complete work of the project described in the contract. Unless otherwise provided, the contractor shall furnish all labor, mailto:Matthew.Phelps@ihs.gov materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with the drawings, specifications, and provisions of the contract. Payment for contract work will be made for and under those pay items included in the Schedule of Items (which is one lump sum price for the contract). All other work and materials will be considered as incidental to and included in the payment for items shown.

B.5. Payment and Performance Bonds: In accordance with FAR 28.102, performance and payment bonds are required.

IMPORTANT INFORMATION:

Under no circumstances will any oral statements made be binding upon the Government unless such statements or agreements are issued in writing by the Contracting Officer.

Only a warranted Contracting Officer acting within their delegated limits has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract, you shall not proceed within the change and shall immediately notify the Contracting Officer.

END OF SECTION

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1. BACKGROUND AND PROJECT DESCRIPTION: The purpose of this project is to construct a rural waterline that extends the Fort Thompson water distribution system to the community of Crow Creek.

This project would connect the Fort Thompson Community water distribution system to the Crow Creek Community drinking water system, and abandon the community wells. It would expand the Fort Thompson water distribution system to the eastern part of the Crow Creek Indian Reservation by providing water from the Fort Thompson water distribution system to 105 existing homes located within the Crow Creek Reservation.

Please see Attachments J02.1-3 –detailed information about the project scope.

C.2. GENERAL: The Contractor shall provide all material, labor, and equipment to perform the work as detailed in the Final Construction Documents (CDs) specified below and as described in the Specifications (Attachment J02.1), Plans (Attachment J02.2), and Geotechnical Reports (Attachment J02.3).

C.3. PERIOD OF PERFORMANCE: The contractor shall proceed and complete the work, including cleanup within 240 days after issuance of the Notice to Proceed (NTP). Contract completion can be adjusted for any long lead items if requested in writing to the Contracting Officer.

SECTION D – PACKAGING AND MARKING

D.1. PACKAGING AND MARKING

(a) All shipments of materials, equipment and/or supplies to the project site shall be addressed to the Contractor and not the Indian Health Service. Preservation, packaging and packing shall be in accordance with industry standard packaging appropriate for the item(s) involved. The Indian Health Service is not responsible in any manner for deliveries intended for the project that are not generated by the Indian Health Service.

(b) Equipment and materials provided by the Contractor shall be new and, where appropriate, shall arrive on-site sealed in original manufacturer’s containers. The Government reserves the right to refuse any items deemed to not meet this requirement.

SECTION E – INSPECTION AND ACCEPTANCE

E.1. FAR 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not --

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may --

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

(End of Clause)

SECTION F – DELIVERIES OR PERFORMANCE

F.1. 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(s):

https://www.acquisition.gov/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Number Title Date 52.242-14 Suspension of Work Apr 1984

F.2. FAR 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 240 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause) https://www.acquisition.gov/

F.3. SUPERINTENDENT ON SITE

The Contractor shall ensure that the Project Superintendent is on site at all times work is being performed by the contractor or subcontractor(s). They shall directly oversee all apprentice and subcontractor work. The Project Superintendent is also responsible to ensure all labor and safety requirements are complied with; and ensure that the worksite is cleaned up at the end of each work day.

All communications between the IHS and contractor concerning the day-to-day workmanship on the project will be handled through the Project Superintendent and they MUST have the authority to act on behalf of the Contractor in all contractual matters.

F.4. REMOVAL OF PERSONNEL

The Contracting Officer may require the Contractor to remove from the job any employee who endanger persons or property; those who manufacture, distribute, dispense, possess or use controlled substances at the worksite (FAR 52.223-6, Drug-Free Workplace); and those whose continued employment under this contract is inconsistent with the interest of security or for any and all other reasons as determined by the Contracting Officer as objectionable.

SECTION G – CONTRACT ADMINISTRATION DATA

G.1. CONTRACTING OFFICER

The Contracting Officer (CO) means a person who is the principal individual and responsible representative of the Government with the authority to enter into, administer and/or terminate contracts and make related determinations and findings pertaining to the contract. The Contracting Officer signs all contractual documents, approves and signs all modifications to contracts, processes and approves payment requests, reviews and makes final decisions on contractual discrepancies, and administers the contract. The Contracting Officer is the only authorized individual to make changes to the contract.

G.2. CONTRACTING OFFICER’S REPRESENTATIVE (COR)

(a) Contracting Officer's Representatives (COR), may be appointed for the purpose of representing the Contracting Officer and assuring compliance with the contract requirements.

(b) The COR has NO AUTHORITY to make any changes to the contract or any contract documents.

(c) The COR may approve minor field changes which do not affect the scope, period of performance and/or price of the contract. The COR is authorized to issue notices regarding noncompliance of contract requirements, and to stop work on any portion of the job if the Contractor's methods cause unsafe conditions or will result in noncompliant work which would be impracticable to correct or to replace while permitting other (conforming) portions of the work to continue. Issuance of a Notice of Noncompliance as described herein does not constitute a suspension of work as described in Section I, FAR Clause 52.242-14, Suspension of Work (April 1984).

(d) The COR is appointed in writing and the contractor will receive a copy of the appointment letter.

G.3. PAYMENT PROCESS

(a) FAR 52.232-5, Payments Under Fixed -Price Construction Contracts, requires that before the first progress payment under the contract is submitted, the contractor shall prepare a proposal with value(s) for each principal category of the work which when added together equal the total contract price. A sample format is available from the Contracting Officer. The following is the detail required by the Contracting Officer:

(1) The principle categories of work shall be broken into line items of sufficient detail to allow meaningful measurement of the work on a monthly basis as determined by the COR. Units of measure appropriate to the type of work shall be used. “Lump sum” pricing of line items shall be avoided except where payment for that line item is to be requested based on 100% completion of that line item or where there is no other practical unit of measure.

(2) The cost of preparatory work (e.g., shop drawings or product submittals), field and home office overhead, profit, insurance, taxes, warranties, as-built drawings, etc., shall be pro-rated into items of physical work and not listed as separate line items. Cost of Performance and Payment Bonds may be listed as a single line item and not pro-rated. Also, cost of mobilization and demobilization relating to transportation or installation costs associated with such items as site trailers, heavy equipment, temporary batch plants, temporary on-site manufacturing and assembly facilities, temporary on-site quarter’s facilities, temporary sanitation facilities, temporary utility connections, and/or temporary secured storage facilities may be listed as line items and not pro-rated. If mobilization is listed separately, a line item for demobilization must be included and shall be at least 20 percent of the mobilization cost. A detailed listing of the items included and the individual cost for each item shall be provided in support of proposed amounts for mobilization and demobilization.

(b) Material stored on site may be included in earned progress if the Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform in contract.

(c) The following are instructions for submitting pay requests:

(1) Requests are to be submitted with signature for the Contractor certification statement (scanned signature okay) to the Designated Billing Office. Use of a format that complies with all of the requirements of the “Payments” clause of the contract is mandatory. A sample format is available from the Contracting Officer.

(2) The Contractor is responsible for delivery of each request for payment to the billing office.

Hand delivery to the COR in the field does not constitute delivery to the billing office.

(3) If the contractor wishes to inquire concerning the status of any pay request, the contractor should contact the billing office.

(4) A completed Release of Claims that complies with the requirements of the “Payments” clause must be submitted with the request for final payment. A sample format is available from the Contracting Officer.

(d) The final payment request will be rejected and returned to the contractor if all items required under the contract have not been completed, submitted, approved, and accepted prior to the receipt of the request; e.g., deficient work items, as-built, payrolls, reports, O&M manuals, delivery of extra stock material, etc.

G.4. ADDRESS FOR CORRESPONDENCE

(a) It is the intent of the Government to use electronic means as much as possible while administering this contract.

(b) Most correspondence should be sent via e-mail directly to the Contracting Officer (Matthew.Phelps@ihs.gov) and/or COR. Include the Contract Number on all correspondence. Any overnight Mail and U.S. Mail shall be sent to the Contracting Officer, unless otherwise specified, at the following address:

Indian Health Service (IHS) / Division of Engineering Services (DES) Attn: Matthew Phelps 701 5th Ave, Suite 1650 Seattle, WA 98104 Telephone Number: (206) 613-2153

G.5. IDENTIFICATION OF CONTRACTOR EMPLOYEES

(a) Identification (ID) Badges. The contractor shall provide each employee with an ID badge on contract start date or on employment start date. The ID badge shall be made of non-metallic material. The badge shall be easily readable and include the employee's name, the contractor's name, functional area of assignment, and a color photograph. The contracting officer or their designee shall approve the ID badge template before the contract start date.

(b) Display of ID Badges. Contractor personnel shall wear the ID badge at all times when performing work under this contract on site and when attending Government meetings and conferences off-site.

Unless otherwise specified, each contractor employee shall wear the ID badge in a conspicuous place on the front of exterior clothing and above the waist except when safety or health reasons prohibit such placement.

(c) Utilizing Electronic Mail (e-mail). When prime Contractor or Subcontractor personnel send e-mail messages as part of contract performance or otherwise relating to contract matters, each sender shall include his/her name (both first and last names), e-mail address and the name of the individual’s employer.

G.6. INVOICE REQUIREMENTS

(a) Invoices shall be prepared, submitted and paid in accordance with the following FAR clauses specified in Section I:

(1) FAR 52.232-5, Payments Under Fixed -Price Construction Contracts (May 2014)

(2) FAR 52.232-27, Prompt Payment for Construction Contracts (Jan 2017)

(3) FAR 52.232-33, Payment by Electronic Funds Transfer-- System for Award Management (Oct

2018)

(4) FAR 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Dec

2013)

(b) The Designated Billing Office for this contract is the same as the address for correspondence, sent to the attention of the Contracting Officer. Invoices for payment shall be sent via e-mail to the COR and CO for processing and approval.

(c) Progress payments will be authorized for this project.

(d) The final invoice must be marked “Final” and be accompanied by a Release of Claims form, which lists the final payment as outstanding, in the Remarks field. The Release of Claims form is available from the CO. Final payment will be made within 30 Calendar days upon receipt of a properly executed invoice.

(e) The contractor will contact the Designated Billing Office with any payment issues or concerns.

Note: In accordance with FAR 52.232-40, Providing Accelerated Payments to Small Business

Subcontractors (Dec 2013) -- Upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract, to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, after receipt of a proper invoice and all other required documentation from the small business subcontractor. This applies to all small business subcontractors at all tier levels.

G.7. TEST RESULTS

Submit all results of test required by the contract to the COR/Project Manager for review.

G.8. PERMITS AND CERTIFICATES

Submit a copy of all permits and certificates as required by the contract to the COR/Project Manager.

G.9. CERTIFICATION OF PAYMENTS - RELEASE OF CLAIM (ROC)

The Contractor, when submitting final payment under this contract, shall submit to the Contracting Officer:

(a) A certification that the Contractor has made payment from proceeds of prior payments, or that he will make timely payment from the proceeds of the progress or final payment then due him, to any subcontractors and suppliers in accordance with established contractual arrangements;

and

(b) A properly executed Contractor's Release. The Release of Claims form is available from the Contracting Officer Failure to submit this completed release will result in a delay of final payment.

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1. SUBCONTRACTS

(a) Nothing contained in the contract shall be construed as creating any contractual relationship between any subcontractor and the Government. The divisions or sections of the specifications are not intended to control the contractor in dividing the work among subcontractors, or to limit the work performed by any trade.

(b) The contractor shall be responsible to the Government for acts and omissions of his own employees, and of subcontractors and their employees. The contractor shall also be responsible for the coordination of the work of the trades, subcontractors, and suppliers.

(c) The Government will not undertake to settle any differences between or among the contractor and their subcontractors or suppliers.

(d) The contractor shall, without additional expense to the Government employ specialty subcontractors where required by the specifications. "Specialty Subcontractors," when specified as a requirement, means a subcontractor regularly engaged in the manufacture or installation of the contract items. The specialty subcontractor shall select and combine the materials involved, maintain and have available for the purpose, workmen skilled in the specified work. The specialty subcontractor shall be the manufacturer, be licensed by the manufacturer as an installer, or work under direct supervision of the manufacturer.

H.2. SUBCONTRACTING

(a) In connection with the performance of work under this contract, the contractor shall not subcontract with any subcontractor who, at the time of subcontract award, is listed on the current System for Award Management (SAM) Lists of Parties Excluded from Procurement and Non-procurement Programs, unless otherwise authorized by the Government in accordance with Subpart 9.4 of the Federal Acquisition Regulations.

(b) The List of Parties Excluded from Procurement and Non-procurement Programs is available at https://www.sam.gov/portal/SAM/#1.

(c) In the event of the contractor's noncompliance with the foregoing requirements, the Government may terminate this contract for default or take other appropriate action, including, but not limited to, requiring the contractor to terminate any such subcontract and substitute an eligible subcontractor in lieu thereof, at no increase in the contract price or time for performance.

(d) The term "subcontractor," as used in this clause, shall mean the individual or firm with whom the contractor proposes to enter into a subcontract for manufacturing, fabricating, installing, or otherwise performing work under this contract.

(e) Within ten (10) days after contract award, the contractor shall furnish to the Contracting Officer in writing a list of all subcontractors scheduled to perform work under the contract on Form SF-1413.

(f) The contractor shall include the provisions of paragraphs a., b., and d. of this clause in every subcontract hereunder.

H.3. COORDINATION OF TRADES

The drawings are in part diagrammatic and show the general arrangement of ducts, piping, conduits, etc., of mechanical and electrical work. The contractor shall have a competent and registered engineer to coordinate all fieldwork and shop drawings of the various trades prior to installation and for submission of coordinated shop drawings for approval. Spaces shall be allotted to the various trades prior to the installation of the work. In spaces where all the various installations cannot be accommodated, the contractor shall, prior to fabrication or installation of work, notify the Contracting Officer and submit suggestions as to the solution. The contractor shall be responsible for the coordination of the various trades involving location and size of all sleeves, electric outlets, inserts, piping, shafts, conduits, hangers, ducts, and similar installations.

H.4. STANDARD REFERENCES

(a) Any materials, equipment, or workmanship specified by reference to the number, symbol, or title of any specific standard shall comply with the latest edition or revision thereof, and any amendment or supplement thereto, in effect on the date of the solicitation, except as limited to type, class or grade, or modified in the specifications.

(b) Standards referred to in the plans and specifications, except as modified, shall have full force and effect as though printed in the plans and specifications.

(c) The contractor shall maintain on the site, a complete current set of manufacturers' and standards referenced from work under the contract.

H.5. INSURANCE

FAR 52.228-5, Insurance Work on a Government Installation, states that "The contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds https://www.sam.gov/portal/SAM/#1 and minimum amounts of insurance required in the schedule or elsewhere in the contract." The following is the minimum insurance required by the Contracting Officer:

1. Workers' Compensation and Employer's Liability: Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so comingled with a contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in states with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.

2. General Liability: Bodily injury liability insurance coverage written on the comprehensive form of a policy of at least $500,000 per occurrence.

3. Automobile Liability: Automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

H.6. PRODUCT APPROVAL

FAR 52.236-5, Material and Workmanship, states "[w]hen required by this contract or by the Contracting Officer, the contractor shall also obtain the Contracting Officer's approval of the materials or articles which the contractor contemplates incorporating into the work. When requesting approval, the contractor shall provide full information concerning the material or articles. When directed to do so, the contractor shall submit samples for approval at the contractor's expense, with all shipping charges prepaid. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection."

(a) Approval of proposed materials or articles shall be only for the characteristics or use named in such approval and shall not be construed to change or modify any contract requirements, or relieve the Contractor from any contract requirement. Before submitting requests for product approval, the Contractor shall assure himself that the materials or equipment will be available in the quantities required. No change or substitution of approved materials or articles will be permitted after a request has been approved.

(b) Materials and equipment incorporated in the work shall match the approved materials or articles. If requested, approved samples, including those that may be damaged in testing, will be returned to the contractor, at his expense, upon completion of the contract. Samples not approved will also be returned at Contractor expense, if so requested.

(c) Failure of any material to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further requests for approval of the same brand or make of that material.

The Government reserves the right to disapprove any material or equipment that previously has proved unsatisfactory in service.

(d) Deviations from the contract requirements shall be specifically pointed out in transmittal letters.

Failure to point out deviations may result in subsequent rejection and removal of such work at no additional cost to the Government.

(e) Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals. The contractor shall replace such materials or equipment to meet contract requirements, or there shall be an adjustment of the contract price as determined by the Contracting Officer.

(f) When tests are required, only one test of each sample proposed for use will be made at the expense of the Government. Samples which do not meet specification requirements will be rejected. Testing additional samples will be done by the Government at the expense of the contractor.

(g) The contractor shall furnish additional certification on conformance to the specification requirements as may be requested by the Contracting Officer.

H.7. OPERATIONS AND STORAGE AREAS

Reference FAR 52.236-10 Operations and Storage Areas. The Contractor shall coordinate its operations and storage areas with the COR.

H.8. ACCIDENT PREVENTION

Reference FAR 52.236-13 Accident Prevention. The Contractor shall submit for approval a written Safety and Accident Prevention Plan showing how they will comply with FAR 52-236-13. The Contractor shall also designate in writing the individual who is responsible for identifying and correcting safety hazards or violations on the job site.

H.9. AVAILABILITY AND USE OF UTILITY SERVICES

Reference FAR 52.236-14 Availability and Use of Utility Services. The Government anticipates that the proposed work will place a small demand on available utility services and therefore will not charge the Contractor for their use.

H.10. SCHEDULES FOR CONSTRUCTION CONTRACTS

Reference FAR 52.236-15 Schedules for Construction Contracts. The Contractor shall provide a schedule for approval prior to commencing work. During the execution of the work, the Contractor shall notify the COR of any proposed changes to the approved schedule on a weekly basis.

H.11. PRECONSTRUCTION CONFERENCE

Reference FAR 52.236-26 Preconstruction Conference. The Contracting Officer will conduct a pre-construction conference. Location is TBD until award, but will most likely be at the site. The CO, COR, and Contractor are required to participate. The CO may designate required attendance for subcontractors. The CO and COR may attend the conference via conference or video call.

H.12. WARRANTY OF CONSTRUCTION

Reference FAR 52.246-21 Warranty of Construction. All warranties the Contractor receives from sub-contractors, manufacturers and suppliers shall be executed in writing for the benefit of the Government.

The Contractor shall provide the COR with copies of all warranties obtained.

H.13. AS BUILT DRAWINGS

The contractor shall maintain during the progress of the work one (1) set of completed and up to date blue line drawings, which shall be available for inspection by the Contracting Officer at any time. These drawings shall be marked up to record all changes in the work as they occur, and the exact location of all exposed and concealed pipe runs, valves, plugged outlets, cleanouts and other control points including, but not limited to, electrical conduits, and ducts, mechanical valves, shut-off switches, etc., in such a manner as will provide a complete, accurate as built record. The location of pipes or control points concealed underground, under concrete, in chases or above hung ceilings shall be dimensioned. In-progress as-built documentation will be reviewed with each progress payment request as a required element. The completed set of as built paper reproducible drawings shall be delivered to the Contracting Officer, in a condition satisfactory to him. As built shall be submitted for review/approval as a condition precedent to the request for final inspection of the work.

H.14. MATERIALS ON SITE

Unless otherwise provided in the specifications or drawings, materials removed and not reused under the contract shall become the property of the contractor. The contractor shall remove the materials from the work site. Storage or sale of the materials on the site will not be permitted.

H.15. SALVAGE

The Government does not assume responsibility for any loss or damage to materials removed and not reused under the contract that become the property of the contractor.

H.16. CONTRACTOR LIABILITY FOR PERSONAL INJURY AND/OR PROPERTY DAMAGE

(a) The Contractor assumes responsibility for all damage or injury to persons or property occasioned through the use, maintenance, and operation of the Contractor’s vehicles or other equipment by, or the action of, the Contractor or the Contractor’s employees and agents.

(b) The Contractor, at the Contractor’s expense, shall maintain adequate public liability and property damage insurance during the continuance of this contract, insuring the Contractor against all claims for injury or damage.

(c) The Contractor shall maintain Workers’ Compensation and other legally required insurance with respect to the Contractor’s own employees and agents.

(d) The Government shall in no event be liable or responsible for damage or injury to any person or property occasioned through the use, maintenance, or operation of any vehicle or other equipment by, or the action of, the Contractor or the Contractor’s employees and agents in performing under this contract, and the Government shall be indemnified and held harmless against claims for damage or injury in such cases.

H.17. PHYSICAL BARRIER AND ACCESS CONTROL

(a) Subject to prior submittal and approval of the IHS, the Contractor shall install or construct a physical barrier between the construction activity/work zone and ongoing hospital/clinic operations. The barrier shall be installed prior to the commencement of all other work and shall control the access of all Contractor personnel to the approved construction activity/work zone. The Contractor must further prohibit all Contractor personnel authorized to perform work under this contract from entering any area of the facility other than those areas where work is being performed and is cordoned off from facility operations. The barrier shall be removed upon completion of all work and as approved by the IHS.

(b) Failure to adhere to this requirement may result in permanent removal of the Contractor employee found to be outside of the approved construction activity/work zone. Repeated failure to adhere to this requirement may result in termination of this contract for default in accordance with FAR 52.249-10.

H.18. INSTRUCTIONS FOR SUBMISSION OF PAYROLLS

(a) One copy of all payrolls pertaining to the work (including payrolls of all subcontractors performing work on the job) will be submitted weekly to the procurement office by the prime contractor. Each such payroll must be accompanied by a fully executed Contractor's Weekly Payroll Statement, indicating that no deductions have been made from weekly wages of employees other than those authorized. The statements must be signed by person supervising payment. Contractor's Weekly Payroll Statement can be found on the U.S. Department of Labor Payroll Form WH 347).

(b) The contract number and project number must be shown on each payroll.

(c) Complete address, classification, straight time hours worked each day, total straight time hours worked in week, rate of pay, overtime hours worked each day, total overtime hours worked in week, overtime rate of pay, gross earnings, each deduction and net pay must be shown for each employee.

(d) Employees must be classified within one of the classifications as shown on the Wage Rate Schedule of the contract. The exact classification, as shown on the Schedule which conforms to the work performed, must be shown on the payroll; that is, when a truck driver is shown, indicate type of vehicle listed in the Schedule under these headings; when a laborer is shown, indicate whether air tool operator, building, etc.; when a welder is shown, list the craft to which the welding is incidental; when an electrician is shown, list the type and zone. Whenever a foreman or superintendent is listed, show the class of workers he is supervising, such as electricians, plumbers, carpenters, etc., as his pay should be as much or more than those he supervises. Classifications not shown on Wage Rate Schedule contained in the contract will not be accepted. In those cases in which the contractor feels that the work performed by his employees will not conform to a craft shown in the Schedule, the problem shall be presented to the Contracting Officer.

(e) All employees must be paid time and one-half their basic rate of pay for all hours worked in excess of 40 hours in any one week.

(f) The prime contractor is responsible for the correct submission of his and subcontractor payrolls. The prime contractor must submit payrolls and/or statements for each week during the life of the contract.

These weeks will begin with the weeks as listed on contract progress schedule. For any week in which no work is performed by the prime contractor, only the "CONTRACTOR'S WEEKLY PAYROLL STATEMENT" need be submitted. These payrolls and/or statements will be numbered consecutively. The prime contractor will list, on the face of his form, the names of all approved subcontractors and whether or not they worked during this period (week). If any of the subcontractors did work during the period, their payrolls and statements should accompany the prime contractor's payroll and/or statements. Each subcontractor needs to submit payrolls and statements only for those weeks in which he works, but these must be numbered consecutively.

(g) All apprentices must be registered in a bona fide apprenticeship program, registered with a State Apprentice Agency recognized by the Federal Committee on Apprenticeship, U.S. Department of Labor.

Evidence of such registration must be furnished the procurement office prior to or together with submission of payroll on which apprentice's name first appears. If an apprentice is employed on such contract, and is not a registered apprentice, the contractor will be required to pay journeyman rates of the craft for which the employee was shown as apprentice. Also, period of apprenticeship under which the employee is serving must be indicated on the payroll.

H.19. EMPLOYEE APPEARANCE

The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The Contracting Officer reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for required passes or badges.

H.20. EQUITABLE ADJUSTMENTS DUE TO CHANGES

(a) The Contractor shall submit a proposal for all changes in the work within fifteen (15) days from the effective date of the change order or request for proposal. With each proposal for a change involving an increase or decrease in the amount of the contract, the Contractor shall submit separately an itemized breakdown that will include, but not be limited to, the following:

(1) Material quantities and unit price (Separated into trades)

(2) Labor costs (separate into labor classifications and hourly rates)

(3) Construction equipment

(4) Workmen's compensation

(5) Overhead

(6) Profit

(7) Employment taxes under FICA, FUTA and SUTA

(8) Bond (Prime Contractor only)

(9) Sales Tax

(10) Direct Performance Time of Change

(11) Impact on Schedule, if any

(12) Impact Costs, if any

(b) In considering proposals for changes involving added work, omitted work, or any combination thereof, estimates will be checked in detail by the Contracting Officer, utilizing unit prices where specified or agreed upon, with the view of arriving at equitable adjustments.

(c) When the necessity to proceed with a change does not allow sufficient time to properly check a proposal, or because of failure to reach an agreement, the Contracting Officer may direct the Contractor to proceed immediately with the work.

(d) Proposals and breakdown should be submitted as promptly as possible but in no event later than thirty (30) days.

(e) Should a proposal cost exceed $750,000 or is required for a lesser amount at the direction of the Contracting Officer for a change, certified cost or pricing data shall be submitted in a format which satisfies the requirements of FAR 15.4. When certified cost or pricing data are required, the Contractor shall submit an executed Certificate of Current Cost or Pricing Data (FAR 15.406-2) as soon as practicable after price agreement is reached.

(f) Allowable overhead, profit, and percentages are given below. These percentage shall be limited to three tiers only and shall be considered to include, but not limited to, all insurance other than FICA, FUTA, SUTA and Workmen's Compensation, field and office supervisors, assistants, and clerical personnel, use of small tools, incidental job burdens, and general office expense. Incidental job burdens include, but are not limited to, review and coordination, and estimating and expediting relative to contract changes that are associated with field and office supervision.

No percentages for overhead and profit shall be allowed on FICA, FUTA, or SUTA.

The percentages of overhead to be allowed by the Contracting Officer will be 10% for all contract changes performed by the Prime Contractor personnel and 5% for all contract change work performed by subcontract personnel.

The percentage for profit to be allowed by IHS will vary according to the nature, risk, extent, and complexity of work involved, but in no case shall exceed 10%. Percentages for overhead and profit will be as follows:

Overhead Profit To subcontractors and/or to the Contractor for work performed with his own forces: 10% 1% - 10% To subcontractors and/or to the Contractor on work performed by other than his own forces: 5% 1% - 5%

The percentage of profit is to be negotiated. The burden is on the Contractor to propose and justify to the Government the percentage of profit to be paid on each modification to the contract.

On proposals involving both increases and…