B01_RFP_Attachment_J07_Price_Schedule_Breakdown_Rev_1.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
Crow Creek Reservation Water Main Replacement Federal contract opportunity
Solicitation number
19-102-SOL-00014
Issued by
Department of Health and Human Services Indian Health Service

About this file

RFP Attachment J07 - Price Schedule Breakdown UPDATED

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Total of All Schedules

ScheduleTotals
Line Item 1 - Schedule AERROR:#VALUE!
Line Item 2 - Schedule BERROR:#VALUE!
Line Item 3 - Schedule CERROR:#VALUE!
Line Item 4 - Schedule DERROR:#VALUE!
Line Item 5 - Schedule EERROR:#VALUE!
Line Item 6 - Schedule FERROR:#VALUE!
Line Item 7 - Schedule GERROR:#VALUE!
Line Item 8 - Schedule HERROR:#VALUE!
Line Item 9 - TERO, state and local taxes
Total Price for All SchedulesERROR:#VALUE!

Abbreviations CY = Cubic Yards EA = Each FT = Foot JB = Job SQ FT = Square Feet HR = Hours

&"-,Bold"&URFP 19-102-SOL-00001 Attachment J07- Price Schedule Breakdown IHS Project AB-14-F56

Line Item 1 Schedule A

Schedule AWater Main Construction - Alignment A
ItemDescriptionQuantityUnitUnit CostTotal Cost
1.1Mobilization1JB$________________$________________
1.2STA. 0+00A Connection1JB$________________$________________
1.36-inch Gate Valve w/Box7EA$________________$________________
1.46-inch SDR-26 PVC Water Main7,492FT$________________$________________
1.56-inch SDR-21 PVC Water Main6,100FT$________________$________________
1.66-inch SRD-17 PVC Water Main2,700FT$________________$________________
1.76-inch Directionally Drilled DR-9 (250 psi) IPS HDPE Water Main500FT$________________$________________
1.810-inch Directionally Drilled SDR-21 Yelomine Casing100FT$________________$________________
1.96-inch SDR-26 Yelomine Water Main100FT$________________$________________
1.10Fire Hydrant w/Gate Valve & Box1EA$________________$________________
1.11Air Release Pit6EA$________________$________________
1.12Erosion Control Blanket16,168SQ FT$________________$________________

Total for Schedule A ERROR:#VALUE!

&"-,Bold"&URFP 19-102-SOL-00001 Attachment J07 - Price Schedule Breakdown IHS Project AB-14-F56

Line Item 2 Schedule B

Schedule BLee Corner Tank Site
ItemDescriptionQuantityUnitUnit CostTotal Cost
2.1Mobilization1JB$________________$________________
2.2Lee Corner Bolted SS Water Standpipe1JB$________________$________________
2.3Lee Corner Standpipe Control Vault1JB$________________$________________
2.4SCADA1JB$________________$________________
2.56-inch Gate Valve w/Box2EA$________________$________________
2.66-inch SDR-21 PVC Water Main83FT$________________$________________
2.7Fire Hydrant w/Gate Valve & Box1EA$________________$________________
2.8Lee Corner Standpipe Access Road1JB$________________$________________
2.9Erosion Control Blanket2,580SQ FT$________________$________________
2.10Power Service to Lee Corner Tank Site1JB$________________$________________

Total for Schedule B ERROR:#VALUE!

IHS Project AB-14-F56

Line Item 3 Schedule C

Schedule CWater Main Construction - Alignment B
ItemDescriptionQuantityUnitUnit CostTotal Cost
3.16-inch SRD-26 PVC Water Main4,196FT$________________$________________
3.26-inch SDR-21 PVC Water Main17,804FT$________________$________________
3.36-inch SDR-17 PVC Water Main12,517FT$________________$________________
3.46-inch Directionally Drilled DR-9 (250 psi) IPS HDPE Water Main500FT$________________$________________
3.56-inch Gate Valve w/Box10EA$________________$________________
3.610-inch Directionally Drilled SDR-21 Yelomine Casing200FT$________________$________________
3.76-inch SDR-26 Yelomine Water Main200FT$________________$________________
3.8Fire Hydrant w/Gate Valve & Box1EA$________________$________________
3.9Air Release Pit4EA$________________$________________
3.10Erosion Control Blanket2,576Sq FT$________________$________________

Total for Schedule C ERROR:#VALUE!

IHS Project AB-14-F56

Line Item 4 Schedule D

Schedule DWater Main Construction - Alignment C
ItemDescriptionQuantityUnitUnit CostTotal Cost
4.16-inch SDR-21 PVC Water Main16,500FT$________________$________________
4.26-inch SDR-17 PVC Water Main18,611FT$________________$________________
4.36-inch Directionally Drilled DR-9 (250 psi) IPS HDPE Water Main250FT$________________$________________
4.46-inch Gate Valve w/Box16EA$________________$________________
4.54-inch Directionally Drilled SDR-21 Yelomine Casing90FT$________________$________________
4.610-inch Directionally Drilled SDR-21 Yelomine Casing585FT$________________$________________
4.76-inch SDR-17 Yelomine Water Main585FT$________________$________________
4.8Air Release Pit5EA$________________$________________
4.9Gravel Road Restoration149FT$________________$________________
4.10Erosion Control Blanket6096SQ FT$________________$________________
Total for Schedule DERROR:#VALUE!

IHS Project AB-14-F56

Line Item 5 Schedule E

Schedule ECrow Creek Tank Site
ItemDescriptionQuantityUnitUnit CostTotal Cost
5.1Mobilization1JB$________________$________________
5.2Crow Creek Standpipe Renovation1JB$________________$________________
5.3Crow Creek Standpipe Control Vault1JB$________________$________________
5.4Abandonment of Existing Pump House, Wells, and Well Site1JB$________________$________________
5.54-inch SDR-21 PVC Water Main40FT$________________$________________
5.6Fire Hydrant w/Gate Valve & Box1EA$________________$________________
5.74-inch Gate Valve w/Box2EA$________________$________________
5.8Power Service to Crow Creek Tank Site1JB$________________$________________
Total for Schedule EERROR:#VALUE!

IHS Project AB-14-F56

Line Item 6 Schedule F

Schedule FCrow Creek Community Valves & Hydrants
ItemDescriptionQuantityUnitUnit CostTotal Cost
6.14-inch Gate Valve w/Box8EA$________________$________________
6.2Fire Hydrant w/Gate Valve & Box7EA$________________$________________
6.3Bituminous Road Restoration30SY$________________$________________
6.4Concrete Sidewalk Restoration10SY$________________$________________
6.5Gravel Road Restoration50FT$________________$________________
Total for Schedule FERROR:#VALUE!

IHS Project AB-14-F56

Line Item 7 Schedule G

Schedule GWater Service Line Construction
ItemDescriptionQuantityUnitUnit CostTotal Cost
7.11-inch Curb Stop14EA$________________$________________
7.21-1/2-inch Corporation Stop17EA$________________$________________
7.31-1/2-inch Curb Stop22EA$________________$________________
7.41-1/2-inch SDR-26 PVC Water Service Line160FT$________________$________________
7.51-1/2-inch SDR-21 PVC Water Service Line540FT$________________$________________
7.61-1/2-inch SDR-17 PVC Water Service Line3,179FT$________________$________________
7.72-inch Corporation Stop8EA$________________$________________
7.82-inch Curb Stop14EA$________________$________________
7.92-inch SDR-26 PVC Water Service Line3,791FT$________________$________________
7.102-inch SDR-21 PVC Water Service Line1,303FT$________________$________________
7.112-inch SDR-17 PVC Water Service Line4,122FT$________________$________________
7.122-inch Gate Valve W/Box1JB$________________$________________
7.132-inch Post Flush Hydrant2EA$________________$________________
7.14Meter Pit49EA$________________$________________
7.15Gravel Road Restoration45FT$________________$________________
7.16Exploratory Digging35HR$________________$________________
Total for Schedule GERROR:#VALUE!

IHS Project AB-14-F56

Line Item 8 Schedule H

Schedule HBad Nation Water Storage Tank Abandonment
ItemDescriptionQuantityUnitUnit CostTotal Cost
8.1Abandonment of Bad Nation Water Storage Tank & Site1JB$________________$________________
8.2Fire Hydrant w/Gate Valve & Box1EA$________________$________________

Total for Schedule H ERROR:#VALUE!