I - ITIOSS_TO2_Award Fee Plan_SLAs.doc

DOC document 157 KB Posted

Attached to
Solicitation IT Infrastructure Operations Support Services (ITIOSS) Federal contract opportunity
Solicitation number
16PBGC19R0021
Issued by
Pension Benefit Guaranty Corporation

About this file

This request for information pertains to IT infrastructure operations support services for the Pension Benefit Guaranty Corporation. The RFI seeks vendor feedback on draft performance work statements to help shape a multiple award IDIQ contract for services such as operations and maintenance support, end-user support, data center operations, network infrastructure operations, IT service management, security services, disaster recovery and cloud integration. Concurrently awarded task orders will include development, modernization and enhancement work as well as SharePoint solution development and support services. Vendors are asked to provide any issues, concerns, strategies or suggestions regarding the RFI process by May 10, 2019. The resulting contract will require performance-based evaluation of service level agreements and metrics to continuously identify and report on measurable operational and development results.

Attch I The uploaded files are the latest and updated versions of the attachments. 7-17-2019 TP

View the file

Other files for this federal contract opportunity

Other files attached to Solicitation IT Infrastructure Operations Support Services (ITIOSS), newest first.
File Type Posted
QandA_R190021_AMD_4.pdf PDF
C_-_ITIOSS _SharePoint_Solutions_Development_Task_Order_PWS_Amd_004.pdf PDF
G_-_LA~1.XLS XLS spreadsheet
D_-_ITIOSS__TO1_QASP_SLAs.pdf PDF
16PBGC19R0021-004__IT_O&M.pdf PDF
B_-_ITIOSS_O&M_and_DM&E_Task_Order_PWS_Amd_004.pdf PDF
16PBGC19R0021_IT_O&M_Final.pdf PDF
K- TO-1 Supporting and Sample Documentation.zip ZIP file
B - ITIOSS O&M and DM&E Task Order PWS.docx DOCX document
L - TO-2 Supporting and Sample Documentation.zip ZIP file
E - ITIOSS _TO2_QASP_SLAs.docx DOCX document
D - ITIOSS _TO1_QASP_SLAs.docx DOCX document
M - Reading Room.docx DOCX document
F - Labor Categories Pricing Workbook IT Infrastructure Technical Services —
H - ITIOSS_TO1_Award Fee Plan_SLAs.docx DOCX document
N - Network Overview.vsd VSD drawing
C - ITIOSS SharePoint Solutions Development Task Order PWS.docx DOCX document
A - ITIOSS2019_IDIQ w Sharepoint PWS.docx DOCX document
G - Labor Categories Pricing Workbook IT Infrastructure SharePoint Solutions Development TO.xlsx XLSX spreadsheet
E - ITIOSS _TO2_QASP_SLAs.docx DOCX document
I - ITIOSS_TO2_Award Fee Plan_SLAs.doc DOC document
A - ITIOSS2019_IDIQ w Sharepoint PWS.docx DOCX document
G - Labor Categories Pricing Workbook IT Infrastructure SharePoint Solutions Development TO.xlsx XLSX spreadsheet
H - ITIOSS_TO1_Award Fee Plan_SLAs.docx DOCX document
M - Reading Room.docx DOCX document
K- TO-1 Supporting and Sample Documentation.zip ZIP file
F - Labor Categories Pricing Workbook IT Infrastructure Technical Services —
B - ITIOSS O&M and DM&E Task Order PWS.docx DOCX document
N - Network Overview.vsd VSD drawing
16PBGC19R0021_ITIOSS__IT_O&M_-_Sharepoint.pdf PDF
C - ITIOSS SharePoint Solutions Development Task Order PWS.docx DOCX document
L - TO-2 Supporting and Sample Documentation.zip ZIP file
D - ITIOSS _TO1_QASP_SLAs.docx DOCX document
Attachment_2_-_Ops_and_DME_TO_Pricing_Workbook.xlsx XLSX spreadsheet
Supplies_or_Services_and_Prices-Costs.pdf PDF
Attachment_1_-_SSD_TO_Pricing_Workbook.xlsx XLSX spreadsheet
SharePoint_Solutions_Development_(SSD)_PWS_-_Task_Order.pdf PDF
Indefinite_Delivery_Indefinite_Quantity_(IDIQ)_-_PWS.pdf PDF
OM_and_DME_PWS_-_Task_Order.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pension Benefit Guaranty Corporation

ATTACHMENT I:

IT Infrastructure Technical Services (ITIOSS)

Task Order 2

SharePoint Solution Development Services (SSDS)

Award Fee Determination Plan 7-1-19

Table of Contents

3SECTION 1:

INTRODUCTION

3SECTION 2:

EVALUATION TIMELINE

3SECTION 3:

AWARD FEE POOL AND ALLOCATION FORMULA

3SECTION 4:

AWARD-FEE PLAN ROLES AND RESPONSIBILITIES

5SECTION 5:

AWARD FEE DETERMINATION PROCESS

SECTION 1: INTRODUCTION

This Award Fee Determination Plan (AFDP) provides procedures for evaluating the contractor's performance of the ITIOSS Contract. The objective of this document is to: (a) providing a workable award fee plan with a high probability of successful implementation; (b) clearly communicate evaluation procedures that provide effective two-way communication between the contractor and the Government; and (c) focus the contractor on areas of greatest importance in order to motivate outstanding performance. The contractor may earn all, part, or none of the Award Fee allocated to the evaluation period based on the “Total Score” transferred from “Award Fee Calculation,” Table 1 below. At the end of each quarter and after the award fee is assessed and scored per the AFDP, the Contracting Officer will inform the Contractor to invoice PBGC for the award fee amount.

SECTION 2: EVALUATION TIMELINE

The Contract will be evaluated every quarter. Award fee determinations will be made by the 20th business day following the end of each evaluation period as described in section 5 award fee determination process and the corresponding timeline, unless an alternate schedule is required and agreed to by the COR and contractor PM due to schedule, monitoring and/or SLA data gathering constraints. There shall be no overlap between the performance periods for purposes of earning award fee. In other words, the contractor cannot earn multiple award fees for performance during the same time period. Please note: The first award fee period after the 2 months transition evaluation will be 4 months, after which each award fee period will be quarterly.

SECTION 3: AWARD FEE POOL AND ALLOCATION FORMULA

For each quarter, the contractor may receive a maximum award fee of one-fourth of 9% of the total estimated labor cost of the performance period (base year or option year) inclusive of all modifications and excluding other direct costs (ODCs).

SECTION 4: AWARD-FEE PLAN ROLES AND RESPONSIBILITIES

Award Fee Determination Official (AFDO) The AFDO is the Director, Information Technology Infrastructure Operations Department.

The AFDO's responsibilities are to:

· Appoint the PRB and the chairperson.

· Approve changes to the award fee plan in consultation with the CO.

· Review the PRB report and determine, in conjunction with CO, the award fee earned and payable.

· Provide written documentation of the decision.

· Ensure the rating and the amount of award fee payable accurately reflects the contractor's performance during the rated period.

AFDO decisions regarding the award fee include but are not limited to: The amount of award fee, the methodology used to calculate the award fee; and the contractor's entitlement to the award fee.

Performance Review Board (PRB) The following table provides the individuals that are members of the PRB. Additional non-voting board members may document meetings as deemed appropriate by the PRB chairperson. Substitutions will be permitted on an infrequent basis in the event of a schedule conflict, subject to approval by the PRB chairperson. Attendance of the non-voting members is not required to convene a board.

Board Position
Organization
Chairperson –Voting Member (VM) 1
ITIOSS COR
PRB Voting Member – VM 2
ITIOD Sr. IT Program Specialist
PRB Voting Member – VM 3
ITIOD Infrastructure Operation Division Manager
PRB Non-Voting Member
PD CO

The responsibilities of the Board members are to:

· Understand thoroughly the award fee plan

· Conduct evaluations of the contractor's performance based on the QASP

· Ensure all criteria are evaluated thoroughly and accurately for the specified rating period

· Review contractor's self-assessment according to the QASP

· Prepare the Performance Review and recommendation report for AFDO approval/comment

· Review Award Fee Plan for any proposed changes PRB Chairperson (Voting Member) The responsibilities of the PRB Chairperson are to:

· Sit as a voting member of the PRB

· Chair the Evaluation Board

· Nominate PRB members

· Nominate PRB meeting recorder (Optional)

· Select monitors

· Ensure timely submission of monthly reports

· Ensure the PRB is conducted in accordance with the Award Fee Plan

· Resolve any inconsistencies in the PRB evaluations

· Ensure timely submission of PRB Report to the AFDO for review, comment, or approval

· Recommend proposed changes to the Award Fee Plan to AFDO Contract Monitors (See QASP for detail) Contract Monitors are the representatives closest to technical work performed. The responsibilities of the Contract Monitors are:

· Review technical performance

· Interact with the contractor on a regular basis

· Provide oral or written feedback monthly to the COR and the Award Fee Board Members before the Board on the Contractor's performance

· Attend Board meeting at the discretion of the PRB chair

SECTION 5: AWARD FEE DETERMINATION PROCESS

The PRB will evaluate contractor performance according to the SLAs and their Accepted Quality Levels (AQL), Target Quality Level (TQL), and weighted score. The PRB will use this information to evaluate these service areas and to determine the appropriate award fee. The PRB calculates a score for each Service Area and a total for the overall program. The Award Fee Determination Plan (AFDP) consists of award fee provisions for following SLA metrics:

Table-1 – Award Fee Calculation Table

Quarterly Performance Result (Only One Must Be Selected)

Metric Name
Weight (W)/ Percentage (%)
Acceptable Quality Level (AQL)
Targeted Quality Level (TQL)
Meet (0 Pt)
Incentive Exceed (+W)
Disincentive- Failed To Meet (-W)
SLA Quarterly Score Achieved (0/+W/-W)
SharePoint Solution Development Timeliness
58%
70%
80%
SharePoint Stakeholders Survey (Quarterly)
30%
Acceptable
Good
Time to resolve incident (priority 1)
4%
85%
90%
Time to resolve incident (priority 2)
4%
85%
93%
Time to resolve incident (priority 3)
4%
85%
93%
Time to resolve incident (priority 4)
4%
85%
94%
Totals
Total 100%
% Of SLAs Met=
% of SLAs exceeded=
% of SLAs did not meet=
Total % Achieved

Procedures for Award Fee Calculation The PRB calculates the total percentage of available award fee using the total of the score achieved for all SLAs. The score achieved for each SLAs is transferred to the Award Fee Calculation Table from the Contractor final self-assessment.

Example: If total % Achieved is 80% and if the available award fee pool for the period/quarter is $50,000.00, the award fee would be 80% x $50,000 = $40,000.

Performance below the AQL results in a negative score for that SLA, while performance at or above the TQL results in a positive score for that SLA. The available score for any given SLA is its percentage (weight). The Total score for the quarter is the sum of the percentage scored for all active SLAs.

Procedures for Final Evaluations The PRB will review and discuss all performance information. The contractor shall provide its self-assessment to the PRB chairperson according to the following Award Fee Plan Timeline:

11th business day after end of the period
15th business day after the end of the period
20th business day after the end of the period
Contractor’s Self-Assessment Report Issued
PRB Meets and Issues Memo to AFDO
AFDO Issue Final Determination

The PRB should have 100% of voting members present to make an official recommendation of the amount of award fee. The PRB Report will be a memorandum to the AFDO with the PRB's recommendation. The AFDO will consider the final PRB report and discuss with the board as necessary. The AFDO may accept, reject, or modify the PRB recommendation. The AFDO will document the award fee earned (and the basis of the determination) in an Award Fee Determination Memo, which will be forwarded to the PD CO within (5) business days.

SLA Changes and Exclusions within a Review Period SLAs may be removed from active scoring for a review period. Adverse performance data may also be excluded from the total score following any disruption beyond the control of the contractor. The Contract Monitors will present the exclusions to the PRB and, if necessary, the PRB will ask the contractor to justify the exclusion. The PRB will have the final say on the decision to exclude the data.

� The Board may request an oral self-assessment from the Contractor.

PAGE