161102Q.A.pdf

PDF 215 KB Posted

Attached to
161102 Incidental Concrete Repairs, Fairfax
Solicitation number
IFB-124760
Issued by
Fairfax County, Virginia

About this file

This is a Question and Answers document issued by the Virginia Department of Transportation regarding IFB 161102 for Incidental Concrete Repairs in Fairfax County. The project involves providing labor, traffic control, supervision, equipment, concrete, materials, and all incidentals to complete incidental concrete repair work on an on-call, as-needed basis for Fairfax County in the Northern Virginia District. Bid item #3 specifies 5 square yards of CG-12 Detectable Warning Surfaces (Truncated Dome), as clarified in Addendum 1. The document was issued on August 24, 2026, and addresses questions regarding bid requirements and specifications.

The procurement does not require a bid bond. While there is no fixed minimum percentage requirement for DSBSD subcontractor participation for non-DSBSD-certified prime contractors, the Commonwealth has established a goal that 42% of its purchases be made from small businesses. Bidders may attach an equipment list to the bid package per Addendum 1. The clarification regarding bid item #3 being adjusted to square yards rather than cubic yards is referenced in Addendum 1, section 4, indicating modifications to the original specifications.

View the file

Other files

File Type Posted
161102.IFB.pdf PDF
161102Pre-bid Sign In.pdf PDF
161102ADD1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF TRANSPORTATION

Stephen C. Brich, P.E. 1221 East Broad Street (804) 482-5818 Commissioner Richmond, Virginia 23219

WE KEEP VIRGINIA MOVING

August 24, 2026

IFB 161102 Incidental Concrete Repairs, Fairfax Question and Answers #1

1. Is there a minimum DSBSD subcontractor participation percentage requirement on this project for those bidders that are not DSBSD-certified?

Answer: There is not a fixed minimum percentage required that a prime contractor must allocate to the DSBSD certified micro or small subcontractor. It is the goal of the Commonwealth that 42% of its purchases be made from small businesses.

2. Is a Bid Bond required for this bid? Answer: No

3. Bid item # 3 has a bid quantity and UOM of 5 CY. The description of this bid item is CG-12 Detectable Warning Surfaces (Truncated Dome). Could you please review and advise if this can be adjusted to 5 SY?

Answer: Reference Addendum 1, 4

4. Is there a form or can I attach an equipment list to the bid package?

Answer: Reference Addendum 1, 3.