This document is a Statement of Work for a federal contract solicitation seeking proposals for relocatable tower systems. The solicitation is seeking 80-foot and 120-foot relocatable towers to support a Remote Video Surveillance System Upgrade. The towers must meet various technical requirements including withstanding winds up to 90 mph when erected and 120 mph when retracted, extending and retracting within one hour, accommodating various payloads including cameras and antennas, and including self-contained power generation capable of continuous operation for 30 days. Contractors must also provide operation, maintenance, and repair documentation as well as participate in first article testing of their proposed solutions. The selected contractors will support the Department of Transportation Federal Aviation Administration Franchise Acquisition Services.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Remote Video Surveillance System Upgrade Acquisition of

80’ and 120’ Relocatable Towers

1.0 Introduction

This document defines the qualification requirements (QR) to procure relocatable towers (RTs) that will be utilized for Remote Video Surveillance System Upgrade (RVSS-U). The requirements are defined for the RTs that will be utilized in various climates, terrains and in varying heights. The performance of the RTs should meet or exceed the criteria listed.

2.0 Qualification Requirements

2.1 RT Requirements

1. When retracted, the RT payload equipment will be accessible for maintenance. The “retracted” position is defined as the position where the tower is fully lowered but the system is still deployed; i.e., it is not configured for transport (compare to “stowed” position).

2. The RT will protect mounted equipment against lightning strikes.

3. The RT will provide grounding protection, and grounding interface for the mounted equipment.

4. When set up, the RT site footprint will be no greater than 50 foot by 50 foot. If larger footprint is required, Contractor shall provide those details.

5. When retracted, the RT payload equipment will be accessible for maintenance without removing antennas or cameras that are mounted below the payload.

6. The RT local controls will have an emergency stop capability at any position between retracted and extended.

7. The RT will accommodate two (2) standard RVSS-U sensor suites, and supporting equipment on top of the RT. Each sensor suite is about 200 lbs. A sensor suite consists of one (1) electro-optical (EO) camera and one (1) infrared (IR) camera. The supporting equipment may include any or all of the following: pan-tilt unit (PTU), laser illuminator, spotlight, wide angle camera, and loud hailer. Separation between the two sensor suites is a minimum of six (6) feet.

8. The RT will accommodate each sensor suite, which has 8 square feet of average sail area.

9. The RT will not obstruct the sensor suite view.

10. The RT will accommodate two (2) wide angle cameras one foot below the sensor suites on top of the RT. The wide angle camera is about 12.50 pounds.

11. The RT will accommodate the wide-angle camera 0.9 square feet of sail area.

12. The RT will accommodate three (3) six (6) foot microwave dishes ten (10) feet below the top of the tower. Total approximate sail area is 102.7 square feet (two (2) sensors, three (3) antennas, and two (2) wide-angle cameras). The standard installation kits and feed lines are to be used for microwave dishes installations. Microwave dishes are paraboloid with radome.

The RT will accommodate a minimum of 2,000 pounds of payload mounted on the tower.

This payload includes (is not in addition to) the cameras, supporting equipment, and microwave dishes described in SOW Section 2.2 – 2.7.

13. The RT trailer will be able to accommodate an equipment cabinet measuring a minimum of 50 inch height x 34 inch depth x 25 inch width.

14. The RT equipment cabinet will be enclosed in a lockable drip proof enclosure.

15. If guy wires are necessary to support the RT, the guy wires will attach to the RT trailer outrigger infrastructure, without ground penetration.

16. The RT will survive sustained wind conditions up to 90 miles per hour (mph).

17. When retracted, the RT will survive sustained wind conditions up to 120 mph.

18. The RT will retract, upon local command.

19. The RT will extend, upon local command.

20. The time to fully extend the RT from the retracted position will be less than one (1) hour

(Target), and fifteen (15) minutes (Objective).

21. The time to retract the RT from the fully extended position will be less than one (1) hour (T), and fifteen (15) minutes (O).

22. The RT will have a backup manual crank to retract the tower.

23. The RT will have a backup manual crank to extend the tower.

24. To retract and stow the RT trailer will take no more than two (2) people. The “stowed” position is defined as the tower being fully retracted and the entire system is configured for transport.

25. The RT controls will be on the trailer.

26. The RT controls will be inside a lockable compartment.

27. The RT trailer will be non-ground penetrating.

28. The RT outriggers will be non-ground penetrating.

29. The RT trailer will be level when deployed up to a ten (10°) degree slope

30. The RT will have a visual indicator that shows if the trailer is level.

2.2 Trailer(s) Requirements

1. The RT trailer(s) will be towable by a pick-up truck using a standard commercially available hitch. All payload equipment will be removed from the RT prior to transport.

1. The stowed RT will be transported per Department of Transportation (DOT) limitations in accordance with applicable State Department of Motor Vehicles, State Size and Weight Limits.

Example:

https://www.txdmv.gov/motor-carriers/oversize-overweight-permits/texas-size-weight-limits

2. The stowed RT will be transportable on rugged, e.g., uneven, sloped, non-graded, and remote roads.

2.3 RT Power Generation Requirements

1. The RT power generation will be capable of interfacing with grid power.

2. The RT will have self-contained diesel power generation.

3. The RT will be capable of switching between grid power, solar power

(provided by a 3rd party), and the self-contained power source.

4. Upon unexpected loss of grid power, the RT will be capable of automatically switching to self-contained power without loss of power to the RT.

5. Upon unexpected loss of self-contained power, the RT will be capable of automatically switching to self-contained backup power without loss of power to the RT.

6. The RT will have power connections running on the top of the fully extended RT.

7. The RT will have 120 VAC running to the top of the RT.

8. The RT will have 120 VAC at ground level (minimum three (3) feet above ground level) on the trailer.

9. The RT self-contained power generation system will deliver a minimum of 900w standard and

2000w peak power continuous runtime capacity operating 24-hours/day, and 7-days/week.

10. The RT self-contained backup power generation will produce a minimum of 900w power with

72 hours of continuous runtime capacity.

11. Mean time between diesel refueling is greater than 30 days.

2.4 Environmental Requirements

1. If liquid fuels, e.g., diesel are used, the generator and any fuel storage containers (tanks, drums, bladders, etc.) will have a secondary spill containment system compliant with local, state, and federal requirements.

2. Secondary spill containment systems compliant with local, state, and federal requirements will be provided for any liquid lubricants, hydraulic fluids, or any other oil based liquids used in the tower system.

3. Air emissions from the generators will not exceed the Environmental Protection Agency (EPA) levels for any criteria pollutants.

4. The Contractor must provide the decibel (dBA) output at 20 feet with generator operating at maximum load.

In addition to these environmental requirements for the system, Contractors must provide the following: 1) a Spill Prevention, Control, and Countermeasure Plan; and 2) greenhouse gas emissions and energy reduction and conservation plans.

2.5 Selective RT Requirements

For each of the required RT heights, there will be a separate RT unit manufactured. The deflection, tilt, and twist of the RT will be provided for each height of tower proposed following all of the ANSI/TIA- 222 Standard topographical categories and exposures with the above payload package at a wind speed of 90 mph fully erected. The analysis shall be run with 0.25 and 2.20 inches of ice loading. The deflection, tilt, and twist of an RT under tower governing load combination at a basic three (3) second wind speed of 90 MPH will not be considered if the proposed solution includes any of the following:

Deflection > 3.50 inches Tilt > 0.25 degrees Twist > 0.25 degrees

2.5.1 80 foot RT Requirements

1. The RT tower height will be at least 80 feet (T) above ground level when fully extended.

2.5.2 120 foot RT Requirements

1. The RT tower height will be at least 120 feet (T) above ground level when fully extended.

2.5.3 Options

1. Capability for remote monitoring of generator status including voltage, fuel level, and run hours. (Service to be provided by Government)

2. Capability for remote tower lowering capability via cellular service. (Service to be provided by Government)

3. Capability for remote power system monitoring: battery storage levels, charge rate, and output voltage to tower sensor suites. (Service to be provided by Government)

4. Alternative power sources including solar, hydrogen, wind, etc. Proposed power sources may be standalone or integrated to the relocatable tower.

5. Government obstruction lighting

6. Infrared lighting

3.0 RT Testing Method

The initial testing conditions performed by the Federal Aviation Administration Logistics Center (FAALC) in Oklahoma City, OK will consist of a technical evaluation based on Contractor submitted documents.

After Contractor selections are made, a First Article Test (FAT) will be conducted based on the RT requirements. The selected Contractor(s) will perform a FAT at a location chosen by the contractor with FAALC/CBP representative(s) present.

4.0 RT Repair Documentation

Contractor awardees must provide RT repair documentation. The Contractor must provide information for the replacement of the RT power generation, any electronics built-in (including software) and necessary for the RT’s performance. The documentation must include the procedure to repair or replace damaged or out of warranty components as provided by the manufacturer. Training for repair is a requirement either at the manufacturer site or defined by FAALC. A bill of material must be provided with repair documentation.

Note: RT repair documentation is not required during the testing of the Qualification Requirement (QR), but must be readily available after FAT acceptance.

5.0 RT Operation and Maintenance (O&M) Documentation

Contractor awardees must provide a RT operation and maintenance manual. The Contractor must provide information for the O&M of the RT including power generation or any electronics built-in and necessary for the RT’s performance. The documentation must include the procedure to operate the RT including setting up, raising, lowering, and preparing the RT for transport. Training for O&M is a requirement either at the manufacturer site or defined by Government.

Note: RT (O&M) documentation is not required during the testing of the Qualification Requirement (QR) but must be readily available after FAT acceptance.

6.0 Communication of Results

The test results will be communicated by the Governments contracting office. Results will be communicated as either pass or fail based on the above requirements or for any other reason the Government deems as an unsafe condition relating to the operation of the RT.

7.0 Deliverables

• Operation and Maintenance manual

• Repair documentation

• Power systems maintenance intervals and manuals

1.0 Introduction
2.0 Qualification Requirements
2.1 RT Requirements
2.2 Trailer(s) Requirements
2.3 RT Power Generation Requirements
2.4 Environmental Requirements
2.5 Selective RT Requirements
2.5.1 80 foot RT Requirements
2.5.2 120 foot RT Requirements
2.5.3 Options
3.0 RT Testing Method
4.0 RT Repair Documentation
5.0 RT Operation and Maintenance (O&M) Documentation
6.0 Communication of Results
7.0 Deliverables