Attachment_K_-_Division_1_RFP___15F06718R0000099.pdf
PDF 1 MB Posted
- Attached to
- Job Ordering Contract
- Solicitation number
- 15F06718R0000099
About this file
This notice announces a presolicitation for an indefinite delivery/indefinite quantity job order contract to provide construction, alteration, and repair services at multiple Federal Bureau of Investigation facilities. The contract will have a one-year base period and four one-year options, with individual task orders ranging from $2,000 to $750,000. Pricing for task orders will be determined by applying unit pricing from R.S. Means location factors and the contractor's coefficient schedule, with non-priced tasks negotiated using this same methodology. The contractor must manage numerous simultaneous projects while providing all associated costs, from planning to closeout. The solicitation will utilize a 100% small business set-aside with a NAICS code of 236220 and size standard of $36.5 million. Multiple awards are anticipated.
Not Listed
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JOB ORDER CONTRACT DIVISION 1 RFP # 15F06718R0000099
SENSITIVE BUT UNCLASSIFIED (SBU)
PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY
Do not remove this notice
Properly destroy documents when no longer needed
SECTION 01000 – SECURITY REGULATIONS
PART 1 - GENERAL
1.1 GENERAL SECURITY REQUIREMENTS
A. Clearances. Bidders shall be required to comply with security regulations imposed by the FBI, access to the project will be limited to specific times established by the
Government, including any clearances.
B. Construction Clearances: After award of the Contract, all Contractor employees shall be required to furnish information for security clearances and shall comply with security regulations as imposed by the FBI
C. Nonpublicity:
1. It is a specific condition of this contract that the Contractor, or any
Subcontractors performing work on this project shall not use or allow to be used any aspect of this project for publicity or advertising brochures.
D. Agency Security Regulations:
1.2 OCCUPYING AGENCY SECURITY REQUIREMENTS
A. Access to Federal Bureau of Investigation (FBI) Locations
Performance under this contract may require access to FBI locations to provide some service, product, or perform some other official function of interest to the FBI. Requirements, as identified below, to include approval by the FBI's Security Division, must be satisfied prior to access.
Contractors who will require escorted access, to include short-term, intermittent, or infrequent access, to an FBI facility must complete an "Access of Non-FBI Personnel to FBI Facilities, Background Data Information Form," (FD 816), a "Privacy Act of 1974 Acknowledgment Form"
(FD 484) and two Fingerprint Cards (FD 258). Completed forms should be provided to the assigned CO's Representative (COR) at least 10 days prior to required access.
Individuals requiring unescorted access to an FBI facility must complete the Standard Form 86
(SF-86), Questionnaire for National Security Positions, using the Office of Personnel
PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY
Do not remove this notice
Management’s Electronic Questionnaires for Investigations Processing (e-QIP) and provide two
Fingerprint Cards (FD 258). e-QIP is a secure website that can be accessed from any computer system which has an Internet connection. Only the signed release forms and FD 258 will need to be mailed to the identified Chief Security Officer, the SF-86 itself will be transmitted to the FBI electronically.
To complete the SF-86 using e-QIP, the individual requiring unescorted access to the FBI facility must contact (insert Chief Security Officer, Division, and telephone number) in order to be initiated into e-QIP. Once this action has been accomplished, the individual should be able to access e-QIP at the following link in order to initiate and complete the electronic process:
http://www.opm.gov/e-qip/browser- check.asp. Thoroughly read and follow the instructions for completing the SF-86. NOTE: To fully address suitability/security issues, the FBI requires individuals to provide responses to questions on the SF-86 for the last ten years. Failure to complete the application as instructed may lead to significant delays in processing the required investigation and approval for unescorted access.
Upon logging onto e-QIP, there will be a prompt to answer three “Golden” security questions to establish the user account. After completing the electronic SF-86, please print and sign the (1)
Certification Form (CER) - Certify Completeness and Accuracy of your Investigation Request; (2)
Medical Release Form (MEL) - Authorization for Release of Medical Information; and (3)
Release Form (REL) - Authorization for Release of Information. In addition to these SF 86 release forms, the completion of a Non-Personnel Consent to Release Information (FD-979a), the United States Department of Justice Disclosure and Authorization Pertaining to Consumer
Reports (DOJ 555) are required. Annotation of the assigned e-QIP Investigation Request Number on the upper right corner of each document transmitted to the identified Chief Security Officer is required for coordination with the electronic transmission and to facilitate the investigative process. The e-QIP Investigation Request Number, automatically generated by e-QIP, is located on both the header and footer of the signature forms. These release forms (five total) and FD
258 should be mailed via Federal Express or UPS Express mail directly to the following address:
(insert name and address of Chief Security Officer). The use of regular U.S. mail channels may cause significant delays in processing the unescorted access request.
Upon completion of processing the facility access request, the individual will be required to execute a non-disclosure agreement suitable for their approved access.
B. All information is deemed “Sensitive but Unclassified” by the FBI, both paper and electronic formats shall have the following imprinted on each page:
C. The following paragraph will be imprinted on the cover page of all documents and the label of all electronic media:
http://www.opm.gov/e-qip/browser-
PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY
Do not remove this notice
PROPERTY OF THE UNITED STATES GOVERNMENT COPYING, DISSEMINATING, OR
DISTRIBUTION OF THESE DRAWINGS, PLANS, OR SPECIFICATIONS TO
UNAUTHORIZED USERS IS PROHIBITED
Do not remove this notice.
D. It shall also be the successful firm’s responsibility to provide accountability of all
“Sensitive but Unclassified” documents by keeping a log of all copies. This log shall include the appropriate identifying information, the date it was issued, who the copies were given to and the date it was destroyed or returned to the government.
E. At least one (1) representative from the General Contractor and/or Subcontractor shall have at least one (1) unescorted access clearance. That person may escort up to five
(5) personnel with escorted access clearance and those personnel must be within visual observation at all times from the unescorted access person.
1. The government reserves the right to revoke any contract individual’s access to its facilities, property or information, where such access is no longer clearly consistent with the government’s mission and responsibilities, and the contractor agrees to immediately remove that individual from the work site in such circumstances. In cases of access revocation, the government will inform the individual of the basis for the renovation unless to do so would reveal classified or sensitive information; and, give the individual an opportunity to explain, rebut or refute such basis in writing. Access will remain revoked pending prompt review of any such submission by the individual.
2. The government occupied facilities are high security facilities with strict requirements for access and movement within the buildings of both persons and vehicles. All persons entering the property for the purpose of working under this contract shall comply with the security regulations of the Federal Bureau of
Investigation. The CO shall make it a specific provision of this contract that regulations be accepted and obeyed. The government reserves the right to exclude or remove from any site or building any employee or agent of the contractor or subcontractors that the government deems incompetent, careless, insubordinate, or who is otherwise objectionable, or fails to meet and obey security requirements.
Persons who cannot produce acceptable identification, including those cleared for access but without proper badges in possession at the time, will not be allowed to enter the building.
3. Clearance to move about within the buildings shall be limited to those areas where work is actually being performed. Individuals wandering from work areas will be subject to revocation of access privileges.
PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY
Do not remove this notice
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION
PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY
Do not remove this notice
SECTION 01140 - WORK RESTRICTIONS
1.1 CONTRACTOR USE OF PREMISES
A. The CO (CO) or COR (COR) will conduct a pre-construction survey with the Contractor for each task order to review and document the existing conditions surrounding the project premises prior to the beginning of any construction activity.
B. For each task order, the Contractor shall have full use of the premises for construction operations, including full use of the site, limited only by the Government's right to perform work or retain other contractors to perform work on portions of the project.
C. The Contractor shall limit use of the premises to the work in areas indicated, to allow for Government occupancy and public use.
1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which work is indicated.
2. Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees, and visitors. Do not use these areas for parking or storage of materials.
3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.
4. Maintain existing building in a safe and weathertight condition throughout the construction period. Repair damage caused by construction operations. Take precautions to protect the building, its occupants and the public during the construction period.
5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.
6. The Contractor shall coordinate with the Government for space required for the
Contractor's storage, laydown, and related activities, provided that its use will not interfere with operations of the Government. Arrange and gain approval for use of this space through the COR.
7. Use of the existing loading dock facilities will be coordinated with the
Government.
8. Existing materials and equipment that are removed as part of the construction
Do not remove this notice operations, and that are not reused or designated to be salvaged as Government or other's property, shall become the property of the Contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.
9. Pollution producing equipment or activities shall not be located near air intakes where airborne smoke or fumes could be drawn into the building. Where this equipment or activities are required to complete the work, care must be taken to limit the exposure to building occupants.
10. At JEH, no parking will be available to the Contractor and Contractor’s employees on site. . The Contractor and Contractor's employees shall make their own arrangements for vehicle parking off site.
11. For projects at other locations, parking may be available on site but shall be coordinated with the COR.
1.2 GOVERNMENT OCCUPANCY
A. The Government will occupy the site and the existing building(s) during the entire period of construction. Cooperate with the Government's representatives during construction operations to minimize conflicts and facilitate Government usage. Perform the Work in a manner that does not interfere with the Government's operations.
B. The Government reserves the right to occupy and to place and install equipment in completed areas of the job s i te prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. The Government's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.
1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.
2. Upon occupancy, the Government will assume responsibility for maintenance and custodial service for the occupied portions of the building/job site.
3. The warranty period for the occupied portion of the building will commence on the date of occupancy by the Government.
4. For projects not involving a building structure, or occupied building, such as utilities projects or storage facilities, the warranty period will commence upon Government acceptance of the project.
Do not remove this notice
1.3 WORKING HOURS
A. Government Occupied Hours: Government personnel are scheduled to occupy the building during the following hours on weekdays, Monday through Friday, except for established Government Holidays: 6:00 AM to 6:00 PM.
B. Government Unoccupied Hours: Government personnel are not scheduled to occupy the building during times not indicated as Government Occupied Hours, weekdays from
6:00 PM to 6:00 AM Monday through Friday and on weekends from Friday at 6:00 PM to Monday at 6:00 AM. There may be times when work is required to be performed at these times. Demolition and cross corridor work shall most likely be required to be performed during Government Unoccupied hours.
C. Contractor's General Working Hours: The Contractor’ s genera l working hours shall be established to occur during Government Occupied Hours.
D. Work accomplished during Government Unoccupied Hours shall be performed at no additional cost to the Government. Contractor shall submit a proposed schedule and gain the CO’s approval at least 48 hours before proceeding with any work during Government
Unoccupied Hours.
E. Temporary Suspension of Work: The Contractor shall suspend work during the period of some predetermined dates. Contractor shall not be entitled to an adjustment of the
Contract price or time of performance as a result of this suspension of work.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION
Do not remove this notice
SECTION 01310 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:
1. General project coordination.
2. Coordination drawings.
3. Conservation.
4. Administrative and supervisory personnel.
5. Conferences and meetings.
6. Utility service interruptions.
7. Cleaning and protection.
1.2 GENERAL PROJECT COORDINATION
A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the w ork. Coordinate construction operations included under different sections of the specifications that depend on each other for proper installation, connection or operation.
1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the work depends on installation of other components before or after that part.
2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.
3. Accommodate items scheduled for later installation.
4. Provide for coordinated incorporation of Art and Architecture elements, Contractor's accepted Value Engineering proposals and Change Orders.
B. Notification: Where necessary, prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. When applicable, include notices, reports and meeting minutes as part of the memoranda.
C. Administrative Procedures: Coordinate scheduling and timing of administrative
Do not remove this notice procedures with other construction activities to avoid conflicts and promote orderly progress of the work. Administrative procedures include but are not limited to the following:
1. Preparation of schedules.
2. Installation and removal of temporary facilities.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project closeout activities.
1.3 COORDINATION DRAWINGS
A. Prepare coordination drawings where careful coordination is needed for installation of products and materials fabricated by separate entities, and prepare coordination drawings where limited space availability necessitates maximum utilization of the space for efficient installation of different components.
1. Show the relationship of components shown on separate shop drawings.
2. Indicate required installation sequences.
3. Provide vertical and horizontal dimensions necessary to locate each component and avoid conflicts within the space.
4. Comply with shop drawing requirements for sheet size, digital format, and submittal methods specified in Division 1 Section "Submittal Procedures."
B. Refer to Division 23 Section "Basic Mechanical Requirements" and Division 26 Section
"Basic Electrical Requirements" for specific coordination drawing requirements for mechanical and electrical installations.
C. Provide coordination drawings for equipment and system installations in mechanical and electrical rooms and spaces where two or more entities will provide the work and separate shop drawings are insufficient to show coordination.
1.4 CONSERVATION
A. Consider conservation of energy, water and materials in the conduct of construction operation. Salvage materials and equipment involved in the performance of, but not incorporated into, the Work.
B. Energy Conservation Plan: Develop a program to minimize use of energy during construction related activities. .
Do not remove this notice
C. Implementation of Energy Conservation Plan: Contractor's energy conservation officer shall provide on- site instruction of workers in the methods to conserve energy, and shall manage the process for the duration of the Contract.
1. Contractor shall initiate the plan by issuing notices to the parties of the project, installation of meters or other instruments to record usage where practical, and other measures to encourage energy conservation.
2. The energy conservation officer shall report monthly, in writing, the measures taken to effect energy conservation, records or estimates of usage and savings, and other points of interest. Copies of each report shall be distributed to each significant party of the project, including the CO.
D. Waste Management Plan: Establish a program to maximize recycling of waste materials.
Program shall minimally include the following:
1. Designation of a waste management coordinator.
2. Identification of recyclable materials.
3. Identification of available local recycling firms and agencies to receive recyclable materials.
4. Establishment of quantity goals for collection of each recyclable material.
5. Designation of one or more locations on the project site for collection, sorting and temporary storage of recyclable materials.
6. Means and schedule for transporting and delivery of recyclable materials to recycling firms and agencies.
E. Implementation of the Waste Management Plan: Contractor's waste management coordinator shall provide on-site instruction of workers in the identification, separation and handling of recyclable materials, and shall manage the process for the duration of the
Contract.
1. Contractor shall layout and define specific areas to facilitate separation of materials for recycling, and shall maintain collection bins clearly marked to avoid contamination of the recyclable materials.
2. Contractor shall coordinate with the COR to obtain receptacles for collecting waste products to be recycled by government.
3. The waste management coordinator shall report monthly, in writing, the quantity of each recyclable material collected during the previous month and cumulatively to date, compared to the quantity goal, and other points of interest. Copies of each report shall be distributed to each significant party of the project, including the CO.
1.5 ADMINISTRATIVE AND SUPERVISORY PERSONNEL
A. In addition to the Project superintendent, the Contractor shall provide other
Do not remove this notice administrative and supervisory personnel as required for proper performance of the task order if required within the statement of work.
B. Project Coordinator: Provide a full-time project coordinator, experienced in the administration and supervision of building construction, including mechanical and electrical work. The project coordinator shall be authorized to act as the coordinator of construction activities, including but not limited to the following:
1. Scheduling and sequencing of Work.
2. Sharing access to work spaces.
3. Installations.
4. Protection of Work.
5. Cutting and patching.
6. Selections for compatibility.
7. Preparation of coordination of drawings.
8. Inspection and tests.
9. Temporary services and facilities.
10. The project coordinator shall speak fluent English.
C. Mechanical and Electrical Coordinator: Provide a mechanical and electrical coordinator on an as needed basis, experienced in the coordination of mechanical and electrical construction of the types required for the project, and experienced in coordination of mechanical and electrical construction with other operations. The mechanical and electrical coordinator shall be licensed to practice as a professional engineer in the location of the project, and shall be authorized to act as the coordinator for mechanical and electrical activities, including but not limited to the following:
1. Scheduling and sequencing of mechanical and electrical activities.
2. Sharing access to mechanical and electrical work spaces.
3. Integration of mechanical and electrical work into limited spaces available for mechanical and electrical installations.
4. Protection of mechanical and electrical work.
5. Cutting and patching for mechanical and electrical work.
6. Tolerances for mechanical and electrical work.
7. Preparation of mechanical and electrical coordination drawings.
8. Mechanical and electrical inspections and tests.
9. Utilization of mechanical and electrical temporary services and facilities.
D. Safety and Health Officer: Provide a safety and health officer whose duties shall consist of developing and implementing safety and health programs specified in Division 1
Section "Safety and Health."
E. Energy Conservation Officer: Provide an energy conservation officer whose duties shall
Do not remove this notice consist of developing and implementing a program for minimizing use of energy on the site.
F. Waste Management Coordinator: Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.
1.6 CONFERENCES AND MEETINGS - All applicable meeting shall be outlined in each task order
A. Preconstruction Conference: The CO shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor. Conference shall review responsibilities and personnel assignments.
1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:
a. CO, or their authorized representative.
b. COR
c. Contractor.
d. Major subcontractors.
e. Major suppliers.
f. Other concerned parties.
2. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:
a. Tentative construction schedule.
b. Critical work sequencing.
c. Designation of responsible personnel.
d. Procedures for processing field decisions and Change Orders.
e. Procedures for processing Applications for Payment.
f. Distribution of Contract Documents.
g. Submittal of Shop Drawings, Product Data, and Samples.
h. Preparation of Record Documents.
i. Use of the premises.
j. Parking availability.
k. Office, work, and storage areas.
l. Equipment deliveries and priorities.
m. Safety procedures.
n. First aid.
o. Security.
p. Housekeeping and progress cleaning.
Do not remove this notice
q. Working hours.
3. Reporting: No later than 3 calendar days after the conference, the Contractor shall distribute minutes of the conference to each party present and to other concerned parties, including the CO.
B. Pre-installation Conferences: The Contractor shall conduct a pre-installation conference at the Project Site before each construction activity that requires coordination with other construction.
1. Attendees: In addition to the Contractor’s representative, the installer and representatives of manufacturers and fabricators involved in or affected by the installation, and its coordination or integration with other materials and installations that have preceded or will follow, shall attend. Prior to conferences, advise the CO of scheduled conference dates.
2. Agenda: Review the progress of other construction activities and preparations for the particular activity under consideration at each pre-installation conference, including requirements for the following.
a. Contract Documents.
b. Options.
c. Related Change Orders, including accepted Value Engineering proposals.
d. Purchases.
e. Deliveries.
f. Submittals.
g. Review of mockups.
h. Possible conflicts.
i. Compatibility problems.
j. Time schedules.
k. Weather limitations.
l. Manufacturer’s recommendations.
m. Warranty requirements.
n. Compatibility of materials.
o. Acceptability of substrates
p. Temporary facilities and controls.
q. Space and access limitations.
r. Governing regulations.
s. Safety.
t. Testing and inspecting requirements.
u. Required performance results.
v. Protection.
3. Reporting: Record significant discussions, agreements, and disagreements of each conference. No later than 3 calendar days after each conference, the Contractor shall
Do not remove this notice distribute minutes of the conference to each party present and to other concerned parties, including the CO.
4. Do not proceed with the installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to the performance of the Work, and reconvene the conference at the earliest feasible date.
1.7 Progress Meetings: The COR shall conduct progress meetings at each site at regular intervals. Dates of meetings shall be coordinated with the On-site Government representative.
1. Attendees: In addition to the Contractor and COR, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of the previous progress meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.
a. Contractor's Construction Schedule: Review progress for each task order since the last meeting. Determine where each activity is in relation to the Contractor's
Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to insure that current and subsequent activities will be completed within the
Contract Time.
b. Review the present and future needs of each entity present, including but not limited to the following:
1) Interface requirements.
2) Time.
3) Sequences of operations.
4) Status of submittals.
5) Deliveries.
6) Off-site fabrication.
7) Access.
8) Site utilization.
9) Temporary facilities and controls.
10) Hours of work.
11) Hazards and risks.
12) Housekeeping and progress cleaning.
13) Quality and work standards.
14) Change Orders.
Do not remove this notice
15) Documentation of information for payment requests.
16) Updating of Record Documents.
3. Reporting: No later than 3 calendar days after each meeting, the Contractor shall distribute minutes of the meeting to each party present and to other concerned parties, including the CO. Include a brief summary, in narrative form, of progress since the previous meeting and report.
4. Schedule Updating: The Contractor shall revise the Contractor's Construction
Schedule after each progress meeting where revisions to the schedule have been made or recognized. The revised schedule shall be issued concurrently with the report of each meeting.
B. Coordination Meetings: The Contractor shall conduct project coordination meetings as required to verify detailed coordination procedures for the upcoming construction operations in order to avoid potential problems and misunderstandings.
1. Attendees: In addition to the Contractor and COR, each subcontractor, supplier or other entity involved in coordination or planning construction activities shall be represented. All participants shall be authorized to conclude matters relating to the Work.
2. Agenda: Review the plans and requirements of each entity present, including but not limited to the subjects listed for Progress Meetings.
3. Reporting: No later than 3 calendar days after each meeting, the Contractor shall distribute minutes of meeting to each party present and to other concerned parties, including the CO.
1.8 UTILITY SERVICE INTERRUPTIONS
A. Utility Service Interruption Plan: Contractor shall submit a utility service interruption plan for task orders where applicable. Plan shall include dates and times of each scheduled interruption, with estimated period of outage, list of existing equipment that will be affected by the interruption, proposed sequence of equipment shut-down and start-up, and responsible personnel.
1. Keep interruptions and periods of interruption to a minimum.
2. Schedule interruptions during times when the facility is unoccupied or will cause the least disruption to Government activities.
3. Plan must be approved in writing by the Government ’s Construction Manager
(CM), the CO or the COR. If not approved, consult with the CM or COR, and revise and resubmit the plan until approved.
4. Coordination of Interruptions: Sufficiently in advance of each scheduled utility interruption, the Contractor shall issue a notice to all affected parties, confirming each provision of the interruption. Coordinate w i t h t h e CM or the COR, and confirm that the responsible personnel are prepared to execute the shut-down and
Do not remove this notice start-up of affected existing equipment, prior to each interruption.
1.9 SUBMITTALS
A. Coordination Drawings: Comply with the shop drawing requirements specified in
Division 1 Section "Submittal Procedures."
B. Energy Conservation: Within 15 calendar days after commencement of construction, submit the energy conservation plan, followed by monthly implementation reports.
C. Waste Management: Within 15 calendar days after commencement of construction, submit the waste management plan, followed by monthly implementation reports.
D. Staff Names: Within 15 calendar days after task order award, submit a list of principal staff assignments, including the superintendent and other primary personnel at the project site. Identify individuals by name, duties and responsibilities, home address, and business and home telephone numbers.
E. Conference and Meeting Minutes: Within times specified for reporting, distribute minutes to concerned parties.
F. Utility Service Interruptions: No later than 15 calendar days prior to the first planned interruption, submit the utility service interruption plan, followed by confirmed scheduled shut-down notices at least 3 calendar days prior to each interruption.
PART 2 - PRODUCTS (Not applicable)
PART 3 – EXECUTION
3.1 GENERAL COORDINATION PROVISIONS
A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.
1. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
2. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.
B. Construction in Progress: Keep construction in progress, and adjoining materials in place, clean during handling and installation. Apply protective coverings where required for
Do not remove this notice protection from damage or deterioration.
C. Completed Construction: Clean completed construction, and provide maintenance, as frequently as necessary to prevent damage or soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components as necessary to assure operability without damage.
D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period. Such conditions include but are not limited to the following:
1. Excessive static or dynamic loading.
2. Excessive internal or external pressures.
3. Excessively high or low temperatures.
4. Thermal shock.
5. Excessively high or low humidity.
6. Pollution and air contamination.
7. Water or ice.
8. Chemicals and solvents.
9. Light.
10. Radiation.
11. Puncture.
12. Abrasion.
13. Heavy traffic.
14. Soiling, staining, and corrosion.
15. Bacteria.
16. Rodent and insect infestation.
17. Combustion.
18. Electrical current.
19. High-speed operation.
20. Improper lubrication.
21. Unusual wear or other misuse.
22. Contact between incompatible materials.
23. Destructive testing.
24. Misalignment.
25. Excessive weathering.
26. Unprotected storage.
27. Improper shipping or handling.
28. Theft or vandalism.
END OF SECTION 01310
Do not remove this notice
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION
A. This section includes certain schedules and reports required for documenting the progress of construction during performance of the Work.
B. Requirements for construction progress scheduling are included in this Section.
C. Requirements for construction progress scheduling are specified in Division 1 Section
"Network Analysis Schedules."
D. Coordinate the timing for preparation and processing of schedules and reports with the performance of other construction activities, and maintain a consistent and logical correlation between updated schedules and reports.
1.2 CONSTRUCTION PROGRESS SCHEDULING
A. Construction Schedule for all task orders: Prepare a preliminary horizontal bar-chart-type construction schedule for the project. Submit the Preliminary Construction Schedule to the CO within 7 calendar days after the date established for commencement of the
Contract, unless otherwise required by the Construction Contract Clauses.
1. Provide a project schedule using MS Project scheduling software. Coordinate each element on the schedule with other construction activities. Schedule each construction activity in proper sequence.
2. Schedule shall be time-scaled in not more than weekly increments, with the dates of the first day of each week indicated.
3. Completion of the Work shall be indicated in advance of the date established for completion of the Contract.
4. With the submission of the Construction Schedule, include a tabulation by date of submittals required during the duration of construction, or show the submittals on the schedule. Include the submittals required to maintain orderly progress of the Work and those required early because of long lead-time for manufacture or fabrication.
Do not remove this notice
B. Construction Schedule for task order over $250,000: Prepare and periodically update a comprehensive, fully developed, horizontal bar-chart-type construction schedule. Base the Contractor's Construction Schedule on the construction schedule for all task orders and whatever updating and feedback received since the start of construction.
1. Within each construction activity's time bar, indicate estimated completion percentages in not more than 10 percent increments and, as work progresses, place marks in the bars to indicate actual completion percentages.
2. Cost Correlation: If requested by the CO, provide a cost correlation line at the head of the schedule to indicate planned and actual cost. As work progresses, show dollar volume of Work performed as of the dates used for applications for payment.
3. Phasing: Arrange schedule to show how sequence of work is affected by requirements for phased completion, work by separate contractors, work by
Government, Government-furnished items, coordination with existing work, limitations of continued occupancies, non-interruptible services, partial completion for occupancy, site restrictions, provisions for future work, seasonal variations, environmental control, and similar provisions of the project.
4. Individual Work Stages: Show significant stages for each category or unit of work, including where applicable, but not necessarily limited to, submittals, purchases, mockups, fabrication, sample testing, deliveries, installation, testing, adjusting, curing, start-up and placement into final use and operation.
5. Area Separations: Arrange the schedule to separately show each major category or unit of work for each major area of construction. Indicate where each major category or unit of work must be sequenced or integrated with other work as necessary for structural completion, permanent space enclosure, and completion of mechanical and electrical work or completion of some other recognized stage of completion for overall work in that area. A major area is defined as a story of construction, a separate building or similar separation.
6. Updating: Provide an updated schedule in conjunction with each project meeting specified in Division 1 Section "Project Management and Coordination." In addition, revise the schedule after each event or activity that causes a significant change in the planned progress of the Work. Highlight or otherwise emphasis revisions for ease of identification.
7. Distribution: Print and distribute copies of the initial Contractor's Construction
Schedule, and each updated or revised schedule, to the CO, as well as to subcontractors and other parties required to comply with upcoming scheduled dates. Post copies in the project meeting room and temporary field office.
1.3 SUBMITTAL SCHEDULE
A. The submittal schedule shall list all submittals required by the specifications, listed in
Do not remove this notice order by the specification section in which they are required. Coordinate the Submittal
Schedule with the Contractor's Construction Schedule and other related documents. The
Submittal Schedule shall include the following information, when a material has been approved for one task order it shall be considered approved for all task orders, unless otherwise noted within the statement of work:
1. Submittal Number.
2. Submittal Description.
3. Related specification section and paragraph numbers.
4. Category of Submittal (Sample, Shop Drawing, Certified Test Report, etc.)
5. Name of Subcontractor, if applicable.
6. Description of the part of the Work covered by the submittal.
7. Corresponding activity or event number on the Contractor's Construction Schedule, if applicable.
8. Scheduled date for first submittal (planned and actual dates).
9. Schedule dates for resubmittal of disapproved submittals (planned and actual dates).
10. Type of action by COR (approved; approved as noted; not approved, revise and resubmit).
11. Date of action by COR (planned and actual dates).
B. Schedule a resubmittal for each submittal. Except where specified otherwise in the contract documents, provide not less than 14 calendar days for the Government review of each submittal and resubmittal.
1. Provide not less than 30 calendar days for review of each fire protection submittal.
C. Distribution: Initially submit 3 copies of the Submittal Schedule to the CO for review.
After the CO's response, print and distribute revised copies to the CO and entities designated by the CO, and to subcontractors and other parties required to comply with upcoming submittal dates.
1. Post copies in the project meeting room and temporary field office.
2. When the submittal schedule is updated, repeat distribution and posting.
D. Updating: The Submittal Schedule shall be kept up-to-date by the Contractor. A current updated copy of the Submittal Schedule shall be submitted with each Contractor payment request, and at other times as requested by the CO, until all submittals are approved.
Failure to provide the requested information, or delay in submitting required submittals may result in the payment request being returned to the Contractor until the required schedule or submittals are received.
1.4 SCHEDULE OF INSPECTIONS AND TESTS
Do not remove this notice
A. Prepare and submit a schedule of inspections, tests and similar services required for each task order.
B. Coordinate the schedule of inspections and tests with the Contractor's Construction
Schedule and other related documents. Prepare the schedule in tabular form, including but not limited to the following information:
1. Specification section number.
2. Description.
3. Identification of applicable standards.
4. Identification of methods to be used.
5. Number of inspections, tests or similar services.
6. Time schedule or time span.
7. Responsible entity.
8. Requirements for taking samples.
9. Unique characteristics.
C. Distribution: Submit copies of the schedule of inspection and tests to the CO, entities designated by the CO, and each party involved in performance of portions of the Work where inspections, tests and similar serviced are required.
1.5 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at the site. Submit duplicate copies to the CO or COR at weekly intervals.
1. List of subcontractors at the site.
2. List of separate contractors at the site.
3. Count of personnel at the site.
4. High and low temperatures, general weather conditions.
5. Accidents.
6. Meetings and significant decisions.
7. Unusual events.
8. Stoppages, delays, shortages, and losses.
9. Meter readings and similar recordings.
10. Emergency procedures.
11. Orders and requests of governing authorities.
12. Change Orders received or implemented.
13. Services connected or disconnected.
14. Equipment or system tests and startups.
15. Partial completions or occupancies.
16. Summary of all work performed.
Do not remove this notice
B. Material Location Reports: At not more than weekly intervals, prepare a comprehensive list of materials delivered to and stored at the site. The list shall be cumulative, showing materials previously reported plus items recently delivered. Include a statement of progress on and delivery dates for materials or items or equipment fabricated or stored away from the site. Submit copies of the list to the CO or COR.
C. Field Correction Reports: When the need to take corrective action requires a departure from the Contract Documents, prepare a detailed report. Include a statement describing the problem and recommended changes. Indicate reasons the Contract Documents cannot be followed. Submit a copy to the CO or COR for approval.
D. Unusual Event Reports: When an event of an unusual and significant nature occurs at the site, prepare a detailed report. List the chain of events, persons participating, response by the Contractor's personnel, evaluation of the results or effects, and similar pertinent information. Submit a copy to the CO or COR immediately. Advise the CO or COR in advance when such events are known or predictable.
PART 3 - EXECUTION (Not applicable)
END OF SECTION 01320
Do not remove this notice
SECTION 01330 - SUBMITTAL PROCEDURES
A. This Section includes certain administrative and procedural requirements for shop drawings, coordination drawings, schedules, samples and certain other quality assurance submittals.
B. This section does not include requirements for the following submittals:
1. Inspection and test reports specified in Division 1 Section "Quality Control."
2. Warranties specified in Division 1 Section "Product Requirements."
3. Closeout submittals specified in Division 1 Section "Closeout Procedures."
4. Record documents specified in Division 1 Section "Project Record Documents."
5. Operation, maintenance and instruction manuals specified in Division 1 Section "Operation and Maintenance Documentation."
6. Reports, schedules and other submittals specified in Division 1 Section
"Construction Progress Documentation".
C. For clarity purposes, shop drawings, coordination drawings and schedules may be provided electronically, and are further categorized as follows:
1. Shop drawings include drawings and schedules specifically prepared for the project, except for coordination drawings.
2. Coordination drawings are specified in Division 1 Section "Project Management and Coordination."
3. Product data includes manufacturer's standard catalogs, pamphlets and other printed materials, and includes but is not limited to the following:
a. Product specifications.
b. Installation instructions.
c. Color charts.
d. Catalog cuts.
e. Rough-in diagrams and templates.
f. Wiring diagrams.
g. Performance curves.
h. Operational range diagrams.
i. Mill reports.
Do not remove this notice
D. Samples may include samples of such scale to allow delivery for review, as well as field samples or mock-ups of full-size physical examples erected on-site or elsewhere, o establish a true-scale standard by which the corresponding work will be judged or a standard for compliance testing.
E. Other quality assurance submittals include materials specifically prepared for the project, except drawings and schedules, may also be provided electronically, and include but are not limited to the following:
1. Design data and calculations.
2. Certifications of compliance or conformance.
3. Manufacturer's instructions and field reports.
1.2 GENERAL SUBMITTAL REQUIREMENTS
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities and with the Submittal Schedule specified in Division 1 Section
"Construction Progress Documentation". Submittals shall be transmitted to the CO's designated representative as required for each task order Transmit each submittal sufficiently in advance of the scheduled performance of related construction activities to avoid delaying the Work, allowing for the review times specified for submittals in
Division 1 Section "Construction Progress Documentation" and elsewhere in the
Contract documents.
1. Coordinate each submittal with other submittals and related activities that require sequential scheduling, to allow for testing, purchase, fabrication and product delivery in a timely manner.
2. Schedule transmittal of different categories of submittals for the same element of
Work and for different elements of related parts of the Work at the same time.
3. Allow sufficient time for submittal review, corrections following the initial review and resubmittal review before activities scheduled after the submittal approval.
4. Any resubmission required after Government review shall be made within 10 calendar days after return of the submittal, unless specifically authorized otherwise by the CO.
5. Submittals which are determined to be incomplete or otherwise substandard will be returned to the Contractor with no further review. Delays due to incomplete or rejected submittals will not be excused.
6. Construction will not be allowed to proceed if submittals are not received in a timely manner. Failure by the Contractor to provide the required submittals in a timely manner will not result in an extension to the Contractor's Construction
Schedule.
Do not remove this notice
7. Failure by the Contractor to provide the required submittals in a timely manner may result in progress payment requests being returned to the Contractor until submittals are up-to-date.
B. Submittal Preparation: Identify and prepare drawing copies and electronic files and samples as specified in the Construction Contract Clauses. Minimally include the following information for other submittals:
1. Task Order name and number.
2. Date.
3. Name, address and telephone number of firm or entity that prepared the submittal.
4. Name and address of the Contractor.
5. Name of the manufacturer.
6. Number and title of appropriate specification section.
7. Drawing number and detail references, as appropriate.
8. Space to record Contractor's review and approval markings, and for CO's or COR’s action.
C. Submittal Transmittal: Package each submittal for transmission and handling. Transmit each submittal from the Contractor to the CO or COR by use of a transmittal form.
Minimally include the following information on the transmittal form.
1. Task order name and number.
2. Date.
3. Destination (To:).
4. Source (From:).
5. Names of subcontractor, manufacturer and supplier, as applicable.
6. Category of submittal.
7. Description of submittal
8. Number and title of appropriate specification section.
9. Submittal number, including means to separately identify initial submittal and each resubmittal.
10. Certification by Contractor stating that submittal complies with the Contract
Documents, or statement of deviations from the requirements of the Contract
Documents including minor variations and limitations. Deviations may be listed on an attached sheet referenced on the transmittal form.
11. Signature of transmitter.
1.3 SHOP DRAWINGS AND COORDINATION DRAWINGS
A. Submit originally prepared information, drawn accurately to scale. Do not reproduce
Contract Documents or copy standard printed materials as the basis for Shop Drawings
Do not remove this notice and Coordination Drawings.
B. Minimally include the following information on Shop Drawings and Coordination
Drawings:
1. Dimensions.
2. Identification of products and materials.
3. Compliance with specified standards.
4. Notation of coordination requirements.
5. Notation of dimensions established by field measurements, if any.
6. Highlighted deviations from the Contract Documents, if any.
C. Hard copy sheet size: Except for templates, patterns and similar full-size drawings, e l ec t ron ica l l y fo…