B09_Solicitation_Amendment_3_Attach_10__Seeding_Specifications_0003.pdf
PDF 108 KB Posted
- Attached to
- BADL Rehab South Unit Wastewater System
- Solicitation number
- 140P6324B0001
About this file
This solicitation package includes specifications for seeding work at Badlands National Park. The solicitation seeks hydroseeding, mulching and fertilizer application services to rehabilitate the south unit wastewater system. Key specifications include using a seed mixture suited for the local biotype, as well as a hydraulically-applied fiber mulch blend that is 100% biodegradable, non-toxic and composed of recycled wood and cellulose fibers. A slow-release nitrogen-based fertilizer must be uniformly incorporated into the hydromulch slurry at a rate of 400 pounds per acre. The work must be performed in accordance with the detailed seeding, fertilizing and hydroseeding specifications.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 32 92 19
SEEDING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Preparation of subsoil.
B. Placing topsoil.
C. Hydroseeding , mulching and fertilizer .
1.02 RELATED REQUIREMENTS
A. Section 31 22 00 - Grading: Preparation of subsoil and placement of topsoil in preparation for the work of this section.
B. Section 31 23 23 - Fill: Topsoil material.
1.03 REFERENCE STANDARDS
A. ASTM D7322/D7322M - Standard Test Method for Determination of Erosion Control Product (ECP) Ability to Encourage Seed Germination and Plant Growth Under Bench-Scale Conditions 2017.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Deliver grass seed mixture in sealed containers. Seed in damaged packaging is not acceptable. Deliver seed mixture in containers showing percentage of seed mix, year of production, net weight, date of packaging, and location of packaging.
B. Deliver fertilizer in waterproof bags showing weight, chemical analysis, and name of manufacturer.
PART 2 PRODUCTS
2.01 REGULATORY REQUIREMENTS
A. Comply with regulatory agencies for fertilizer and herbicide composition.
2.02 SEED MIXTURE
A. Seed Mixture: seed materail to be of local biotype. Contracotr shall coordinate with park superintendent for seed mix list
2.03 ACCESSORIES
A. Mulching Material: Fiber Mulch Blend shall be thermally refined virgin wood fiber, 30% cellulose fibers. Specifies a hydraulically-applied, erosion control product category of Hydraulic Mulch (HM) – Blend. The Blend HM must be 100% biodegradable, non-toxic, made in the United States and composed of 100% recycled thermally refined (within a pressure vessel) virgin wood fibers and cellulose fibers. The HM shall be phytosanitized, free from plastic netting, and upon application form an intimate bond with the soil surface to create a continuous, porous, absorbent and flexible erosion resistant blanket that allows for rapid germination and accelerated plant growth B. Tackifier shall be Non-toxic linear anionic polymer, synthetic, free of weed seed and organic containments, bonding mulch matrix to the soil.
C. Fertilizer: Recommended for grass, slow release nitrogen; (15-25-10) having 50% Neutalene slow release nitrogen applied at a rate of 400 pounds per acre, uniformily mixed in hydromulch slurrytopsoil.
D. Water: Clean, fresh and free of substances or matter that could inhibit vigorous growth of grass.
E. Erosion Fabric: Jute matting, open weave, biodegradable- no plastic or polypropylene netting allowed with shredded wood fiber or approved equal. 24 month biodegradability
Matrix Color Natural Netting Placement Top and Bottom Netting Type Organic Netting Degradability Regular (not photodegradation) Stitching Organic Stitch Spacing 2 inches on center Matrix Excelsior Matrix Degradability Completely Degradable Unit Weight 11.5 oz/yd^2 (390 g/m^2) Thickness 0.47 in (12 mm) Tensile Strength (MD) 16.0 lb/in Tensile Strength ((TD) 11.0 lb/in Coverage 28% open Longevity 18-24 months
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that prepared soil base is ready to receive the work of this Section.
3.02 PREPARATION
A. Prepare subgrade in accordance with Section 31 22 00.
B. Place topsoil in accordance with Section 31 22 00.
3.03 FERTILIZING
A. Apply fertilizer in accordance with manufacturer's instructions.
B. Apply after smooth raking of topsoil and prior to roller compaction.
C. Mix thoroughly into upper 2 inches (50 mm) of topsoil.
D. Lightly water to aid the dissipation of fertilizer.
3.04 SEEDING
A. Apply seed at the following rates; <1V: 4H= 2,000 lb/ac, >1V:3H= 2,500 lb/ac B. Do not seed areas in excess of that which can be mulched on same day.
C. Do not sow immediately following rain, when ground is too dry, or during windy periods.
D. Apply water with a fine spray immediately after each area has been mulched. Saturate to 4 inches (100 mm) of soil.
E. Following initial germination, immediately re-seed any bare areas than 4 by 4 inches (100 by 100 mm) with remaining seed mix.
3.05 HYDROSEEDING
A. Apply seeded slurry with a hydraulic seeder at a rate of 2,500 lbs per 1 acre (____ Kg per sq m) evenly in two intersecting directions.
B. Do not hydroseed area in excess of that which can be mulched on same day.
C. Immediately following seeding, apply mulch to a thickness of 1/8 inches (3 mm). Maintain clear of shrubs and trees.
D. Apply water with a fine spray immediately after each area has been mulched. Saturate to 4 inches (100 mm) of soil.
E. Following germination, immediately re-seed areas without germinated seeds that are larger than 4 by 4 inches (100 by 100 mm).
3.06 MAINTENANCE
A. Provide maintenance of seeded areas for three months from Date of Substantial Completion.
END OF SECTION
BADLANDS PREAPPROVED SEED MIXTURE: