WICA Bison Corral Specifications 6-5-20_Base.pdf
PDF 2 MB Posted
- Attached to
- Construct Bison Corrals at Wind Cave NP Federal contract opportunity
- Solicitation number
- 140P6320B0009
About this file
This invitation for bids solicits offers to construct bison corrals at Wind Cave National Park for the National Park Service Midwest Region. The project involves demolishing remaining structures from an old corral system; constructing new bison pens with open rail and solid fences using government-provided steel pipe posts and fencing; installing 300-gallon watering troughs, catwalks, a viewing platform, alleys, and gates; placing the government-provided squeeze chute and scale; and building concrete pads and a foundation for a pre-engineered metal building. Bids are due by 2:00 PM Central Time on July 15, 2020 and will be publicly opened at that time. The contract is expected to be awarded within 30 days thereafter with work to be completed within 300 calendar days of the notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WICA Bison Corral Drawings 7-1-2020_Base.pdf | ||
| Sources Sought Market Survey.docx | DOCX document | |
| Sol_140P6320B0009_Amd_0001.pdf | ||
| WICA Bison Corral Drawings Rev 1_Amd_0001.pdf | ||
| Sol_140P6320B0009_Base.pdf | ||
| BID Schedule_Base.docx | DOCX document | |
| Construction Wage Det_Base.docx | DOCX document | |
| Solicitation CPARS Notice_Base.pdf | ||
| Presolicitation Notice Bison Corrals.pdf | ||
| QA Site Visit 7.31.20_0002.pdf | ||
| Sol_140P6320B0009_Amd_0002.pdf | ||
| Site Visit Roster 7.21.20_0002.pdf | ||
| Site Visit Handout Document_0002.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BISON/ELK CORRALS
PMIS #: 310622
FINAL CONSTRUCTION DOCUMENTS
Construction Specifications
Division 1 – 33 Specs
NPS SOW ADDENDUM - REVISION #1
15 May 2020
WIND CAVE NATIONAL PARK
22 May 2019
Anderson Hallas Architects, PC 715 Fourteenth Street
Golden, CO 80401 303.278.4378
PAGE INTENTIONALLY BLANK
WICA - 310622 00 01 10 - 1
TABLE OF CONTENTS
NPS SOW ADDENDUM - REVISION #1
SECTION 00 01 10 - TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 10 - Table of Contents
SPECIFICATIONS
DIVISION 01 -- GENERAL REQUIREMENTS
01 11 00 - Summary of Work 01 26 01 - Contract Modification Procedures 01 27 00 - Definition of Contract Line Items 01 31 00 - Project Management & Coordination 01 32 16 - Construction Schedule
01.32.33 - Photo Documentation 01 33 23 - Submittal Procedures 01 35 23 - Safety Requirements 01 40 00 - Quality Requirements 01 42 00 - Reference Standards 01 50 00 - Temporary Facilities and Controls 01 57 23 - Temporary Storm Water Pollution Prevention 01 67 00 - Product Requirements 01 73 40 - Execution 01 74 19 - Construction Waste Management and Disposal 01 77 00 - Closeout Procedures 01 78 23 - Operation and Maintenance Data N.I.C. – SECTION REMOVED
DIVISION 02 -- EXISTING CONDITIONS
DIVISION 03 -- CONCRETE
03 30 00 - Cast-in-Place Concrete
DIVISION 04 -- MASONRY
DIVISION 05 -- METALS
05 50 00 - Metal Fabrications
WICA - 310622 00 01 10 - 2
05 51 00 - Metal Stairs 05 52 13 - Pipe and Tube Railings 05 53 05 - Metal Gratings and Floor Plates
DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES
DIVISION 07 -- THERMAL AND MOISTURE PROTECTION
07 92 00 - Joint Sealants
DIVISION 08 -- OPENINGS
08 11 13 - Hollow Metal Doors and Frames 08 36 13 - Sectional Doors 08 51 13 - Aluminum Windows 08 71 00 - Door Hardware
DIVISION 09 -- FINISHES
09 91 13 - Exterior Painting
DIVISION 10 -- SPECIALTIES
DIVISION 11 -- EQUIPMENT
DIVISION 12 -- FURNISHINGS
DIVISION 13 -- SPECIAL CONSTRUCTION
13 34 00 – Pre-Engineered Building Systems
DIVISION 14 -- CONVEYING EQUIPMENT
DIVISION 21 -- FIRE SUPPRESSION
DIVISION 22 -- PLUMBING
22 11 23 - Water Pumps N.I.C. – SECTION REMOVED 22 12 19 - Facility Ground-Mounted, Potable-Water Storage Tank N.I.C. – SECTION REMOVED
DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
DIVISION 26 -- ELECTRICAL
26 05 00 - Common Work Results for Electrical N.I.C. – SECTION REMOVED
WICA - 310622 00 01 10 - 3
26 05 19 - Low-Voltage Electrical Power Conductors and Cables N.I.C. – SECTION REMOVED 26 05 26 - Grounding and Bonding for Electrical Systems N.I.C. – SECTION REMOVED 26 05 29 - Hangers and Supports for Electrical Systems N.I.C. – SECTION REMOVED 26 05 33 - Raceway and Boxes for Electrical Systems N.I.C. – SECTION REMOVED 26 05 44 - Sleeves and Sleeve Seals for Electrical Raceways and Cabling N.I.C.–SECTION REMOVED 26 05 53 - Identification for Electrical Systems N.I.C. – SECTION REMOVED 26 24 16 - Panelboards N.I.C. – SECTION REMOVED 26 27 26 - Wiring Devices N.I.C. – SECTION REMOVED 26 28 16 - Enclosed Switches and Circuit Breakers N.I.C. – SECTION REMOVED 26 51 00 - Lighting Fixtures N.I.C. – SECTION REMOVED
DIVISION 27 -- COMMUNICATIONS
DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY
DIVISION 31 -- EARTHWORK
31 10 00 – Site Clearing N.I.C. – SECTION REMOVED 31 20 00 – Earth Moving N.I.C. – SECTION REMOVED 31 23 16 – Topsoil N.I.C. – SECTION REMOVED 31 23 33 – Trenching and Backfilling N.I.C. – SECTION REMOVED
DIVISION 32 -- EXTERIOR IMPROVEMENTS
32 13 13 - Concrete Paving 32 13 73 - Concrete Paving Joint Sealants 32 15 00 – Aggregate Surfacing 32 15 40 – Crushed Stone 32 31 00 - Fences and Gates 32 91 13 - Soil Preparation
DIVISION 33 -- UTILITIES
33 05 27 – Tracer Wire Systems N.I.C. – SECTION REMOVED 33 11 00 - Water Utility Distribution Piping N.I.C. – SECTION REMOVED
END OF SECTION 00 01 10
WICA - 310622 01 11 00 - 1
051520 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Government Furnished Materials.
3. Quality Assurance.
4. Contractor use of premises.
5. Public use of site.
6. Occupancy requirements for buildings.
7. Conduct of operations
8. Work Restrictions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Wind Cave National Park, Northern border of the park, 5 miles north of Highway 385, Hot Springs, South Dakota. The site is southeast of Highway 87, on NPS 5.
B. The Work consists of the following:
1. The Work includes bison pens with open rail and solid panel fences, 300-gallon watering troughs, catwalks, a viewing platform, alleys, bud boxes, and gates for the management of bison movement, materials for a pre-engineered building (metal building), concrete pads for mounting remote equipment, water storage tank and a foundation for the pre-engineered building.
2. Refer to Section 01 27 00 for the division of the above into contract line items.
C. Project will be constructed under a single prime contract.
D. Period of performance: Work shall be completed within approximately 300 calendar days of notice to proceed.
1.3 GOVERNMENT-FURNISHED MATERIALS
A. Government will furnish products indicated.
1. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.
2. Contractor is responsible for handling Government-furnished items at Project site.
3. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
WICA - 310622 01 11 00 - 2
4. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
5. Contractor shall install and otherwise incorporate Government-furnished items into the Work.
B. Government-Furnished Products:
1. Located at the construction area:
a. 7500 LF of used pipe to be used for corral fence posts.
1) Reclaimed steel drilling pipe
a) 3 ½” outside diameter
b) 0.265” to 0.328” wall thickness
c) 30’ to 45’ lengths
d) Steel pipe was purchased under contract in 2018 for $18,525
b. Squeeze chute with portable hydraulic pump.
1) Purchase of squeeze chute is not part of the contract
2) Installation of squeeze chute is part of contract.
c. Scale to be installed under squeeze chute.
1) Purchase of scale is not part of contract
2) Installation of scale anchor bolts is part of contract
1.4 QUALITY ASSURANCE
A. The work shall be performed by competent craftsmen skilled in the trade involved and shall be done in a manner consistent with normal industry standards. All work shall conform to the applicable state and local codes or standards.
B. All work will be completed in a professional manner. Unless otherwise specified, all materials and equipment shall be new, unused, and undamaged. Materials and equipment shall be the current and standard designs of manufacturers regularly engaged in their production.
C. All material will need to fit into existing locations.
D. Contractor is responsible for all work including any disruptions to any electrical, water, and other utilities and operational functions as originally designated.
E. Comply with the manufacturer’s instructions for rigging and handling equipment.
F. Install all parts plumb and level, firmly anchored in locations of previous footprint, and maintain manufacturer’s recommended clearances.
G. Comply with all applicable OSHA and National Park Service DO-50 regulations and directives (available online) pertaining to security, safety, occupational health, fire, traffic, and personnel clearances. Primary contractor shall brief subcontractors on safety, occupational health, and fire prevention regulations at all times. Maintain documentation that all subcontractors have been briefed.
WICA - 310622 01 11 00 - 3
H. Contractor to adhere to all Park policies and procedures regarding Force Protection/Anti-Terrorism Standards. This includes, but is not limited to securing vehicles, tools and materials, as well as access to facilities with keys, door codes, etc. Under no circumstances will contractors be allowed to escort unauthorized personnel without written notification from park Contracting Officer Representative (COR). Contracting Officer (CO) to provide list of names of all contractors/sub-contractors to COR who will be on the job site.
I. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.5 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Storage of Materials: Confine storage of materials to existing corral site, or on open land immediately to the west of the site, all as discussed with the park and agreed to by the Contracting Officer. No materials may be stored to the north of the site due to the presence of a sensitive resource area.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
WICA - 310622 01 11 00 - 4
1.6 PUBLIC USE OF SITE
A. The driveway to the site will be closed to the public during construction.
1.7 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Maintain access to existing roads and adjacent storage building. Do not obstruct roadways or buildings without written permission from the Contracting Officer (CO).
1.8 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.9 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 5 a.m. to 6 p.m., Monday through Friday, except when otherwise indicated.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. Existing Utilities
1. There are no existing utilities located in the project area.
E. Nonsmoking Area:
1. Smoking is only permitted within a vehicle.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
WICA - 310622 01 11 00 - 5
Map of Wind Cave National Park
Route between construction site and storage location of corral building materials is approximately 19.5 highway miles. (Shown in yellow)
END OF SECTION 01 11 00
WICA - 322610 01 26 01 - 1
051520 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
4. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.
All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
5. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
http://www.nps.gov/dscw/publicforms.htm#ct http://www.nps.gov/dscw/publicforms.htm#ct
WICA - 322610 01 26 01 - 2
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
WICA - 322610 01 26 01 - 3
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………15% Profit………………10%
2. OH&P for Subcontractor Work shall not exceed 15% combined (General Contractor OH&P plus subcontractor OH&P).
3. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
4. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
5. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
6. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 01 26 01
WICA - 310622 01 27 00 - 1
051520 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 001: Bison Corrals
1. This item consists of:
a. Demolition, and removal, of the remaining 4 components from the old corral system,
1) Log building,
2) Observation tower,
3) 2 Crowder tubs.
b. Construction of new bison pens with open rail and solid fences (note government provided steel pipe posts and steel fencing rod), 300-gallon corral watering troughs, catwalks, a viewing platform, alleys, bud boxes, and gates for the management of bison movement,
c. Installation of government provided squeeze chute in its entirety.
d. Concrete anchor bolts for scale. Government will provide anchor locations.
Government will install the Tru-Test HD Series Load Bars scale.
2. No separate measurement of quantities shall be made. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 002: Concrete Pads and Building Footing/Foundation/Slab
1. This item consists of:
a. 4 reinforced concrete equipment slabs for:
1) Squeeze chute work area (reference drawings A1.1 & S1.1),
2) Portable hydraulic power unit (5’ X 5’),
3) 150 KW generator (12’ X 15’),
4) Generator resistor bank (4’ X 7’)
b. 1 reinforced concrete slab (14’ X 14’) for the location of an 8,900 gal water tank.
c. A foundation / floor system / stem wall system (reference drawings A1.1 & S1.1) for the pre-engineered building in Line item No. 003 below.
WICA - 310622 01 27 00 - 2
051520 DEFINITION OF CONTRACT LINE ITEMS
d. Securing government provided generator and resistor bank to concrete slabs with anchor bolts.
2. No separate measurement of quantities shall be made. Payment will be made at the contract lump sum price.
C. Contract Line Item No. 003: Pre-Engineered Building
1. This item consists of a 25’ X 40’ overall (25’ X 25’ enclosed) pre-engineered metal building materials package to include detailed shop drawings and materials list. Building materials will be delivered to the project site, offloaded, inventoried, but not assembled.
Assembly and electrical wiring will be performed by Park employees.
2. No separate measurement of quantities shall be made. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
WICA - 310622 01 31 00 - 1
051520 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. Project meetings.
7. Environmental Coordination.
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj
WICA - 310622 01 31 00 - 2
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
8. Commissioning activities.
1.4 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.
Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form obtained from the Contracting Officer.
WICA - 310622 01 31 00 - 3
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select
“CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
WICA - 310622 01 31 00 - 4
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Site access.
4. Jobsite Safety.
5. Resolution of comments on required Division 01 documents.
6. Coordination of Subcontractors.
7. Labor law application.
8. Modifications.
9. Payments to Contractor.
10. Payroll reports.
11. Contract time.
12. Liquidated damages.
13. Contractor Performance Evaluation.
14. Display of Hotline posters.
15. Notice to proceed.
16. Correspondence procedures.
17. Acceptance/rejection of work.
18. Progress meetings.
19. Submittal procedures.
20. NPS Final Accessibility Inspection.
21. Environmental requirements.
22. Permit requirements.
23. As-constructed drawings/operation and maintenance (O&M) manuals.
24. Reference materials.
25. Value engineering.
B. Progress Meetings:
1. The Contracting Officer has the discretion of scheduling weekly progress meetings with the Contractor.
2. The Contractor, or their appointed designee, shall have the responsibility to administer each of the progress meetings.
3. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.
All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
4. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
WICA - 310622 01 31 00 - 5
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections,
h. Construction Schedule update (provide updated CPM).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Review of mockups.
i. Possible conflicts.
j. Compatibility requirements.
k. Time schedules.
l. Weather limitations.
m. Manufacturer's written instructions.
n. Warranty requirements.
o. Compatibility of materials.
p. Acceptability of substrates.
q. Temporary facilities and controls.
r. Space and access limitations.
s. Regulations of agency(ies) with jurisdiction.
t. Testing and inspecting requirements.
u. Installation procedures.
v. Coordination with other work.
w. Required performance results.
x. Protection of adjacent work.
y. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
WICA - 310622 01 31 00 - 6
6. Anticipated Pre-installation Conferences as listed in specifications, including but not limited to:
a. Fencing/Gates
b. Catwalks
1.7 PERMITS
A. General:
1. Potential Permits: No permits were identified during the design process as likely to be required based on typical means and methods of construction.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
WICA - 310622 01 32 16 - 1
051520 CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Float: The measure of leeway in starting and completing an activity.
1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
WICA - 310622 01 32 16 - 2
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: All schedules and reports submitted shall be emailed to the Contracting Officer and provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.
B. Schedule of Values:
1. After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.
2. Provide separate labor and material breakouts for each material division or trade scope.
C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit electronic copy of baseline schedule, large enough to show entire schedule for entire construction period.
D. CPM Reports: Concurrent with CPM schedule, submit electronic copy of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of predecessor and successor tasks for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of all activities sorted in ascending order of total float.
E. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two paper copies.
1.4 QUALITY ASSURANCE
A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:
1. Review software limitations, content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints, including access and lead times.
4. Review delivery dates for Government-furnished products.
WICA - 310622 01 32 16 - 3
5. Review schedule for work of separate Government contracts.
6. Review time required for review of submittals and re-submittals.
7. Review requirements for tests and inspections by independent testing and inspecting agencies.
8. Review time required for completion and startup procedures.
9. Review time required for obtaining and activating permits.
10. Review and finalize list of construction activities to be included in schedule.
11. Review baseline schedule comments, resolve issues and progress on incorporating them
12. Review procedures for updating schedule.
13. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.
B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.
2. Secure time commitments for performing critical elements of the Work from parties involved.
3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
WICA - 310622 01 32 16 - 4
B. Do not break down unit price items. Use only the contract price for unit price items.
C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.
D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, resource-loaded, time-scaled CPM network analysis diagram for the Work.
1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.
2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.
4. The Construction Baseline Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Baseline Schedule shows a coordinated plan of the work.
5. Resource loading of each activity shall include all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown.
6. Consider seasonal weather conditions in planning and scheduling all work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of all work within the contract time.
7. Time Frame: Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.
WICA - 310622 01 32 16 - 5
a. An early finish date may be shown but the late finish date must be the same date as the last day of the contract period. An early completion schedule must contain the following:
1) Insert an activity titled “Project Float” as a successor to the last activity in the early project completion schedule network.
2) Add a milestone titled “Contract End Date” as a successor to the activity “Project Float”.
3) Add duration to the activity “Project Float” as required so the milestone “Contract End Date” equals the last day of the Contract Period.
b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.
c. The Contractor shall limit use of lead or lag duration’s between schedule activities.
d. Project Calendars: Develop and incorporate the following calendars:
1) Administrative Calendar: Include a calendar that is based on a 7 day week to be used on any activities that are based on calendar days. Apply this calendar to administrative tasks or any other tasks that are not affected by non-working days (Federal Holidays, weather, etc.).
2) Project Calendar: Include a calendar that is based on the planned work week for the project. Include Federal Holidays, weekends, and any other non-work days indicated in the contract documents. Apply this calendar to activities which are not anticipated to be affected by weather.
3) Weather Calendar: Utilize the Project Calendar and show anticipated normal downtime related to weather as non-working time. Weather days shall be based on data for the local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park Service records, or source acceptable to the Contracting Officer. Apply this calendar to activities that are anticipated to be affected by weather.
e. Activity Duration: Define activities so no activity is longer than 15 days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.
f. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 calendar days, as separate activities in the schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
g. Submittal Review Time: Include review and re-submittal times indicated.
Coordinate submittal review times in Construction Baseline Schedule.
h. Startup and Testing Time: Include not less than 14 days for startup and testing.
i. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion. (For more information, refer to Division 01 Specification 01 77 00 Closeout Procedures.)
8. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
a. Work Restrictions: Show the effect of the following items on the schedule:
WICA - 310622 01 32 16 - 6
1) Coordination with existing construction.
2) Limitations of continued occupancies.
3) Uninterruptible services.
4) Use of premises restrictions.
5) Provisions for future construction.
6) Seasonal variations.
7) Environmental control.
8) Permit provisions.
b. Work Stages: Indicate important stages of construction for each major portion of the Work.
1) Subcontract awards.
2) Submittals.
3) Purchases.
4) Mockups.
5) Fabrication.
6) Sample testing.
7) Deliveries.
8) Installation.
9) Tests and inspections.
10) Adjusting.
11) Curing.
9. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed and Substantial Completion.
C. Joint Review, Revision, and Acceptance:
1. Within seven calendar days of receipt of the Contractor's proposed Construction Baseline Schedule, the Contracting Officer and Contractor shall meet for joint review, correction, or adjustment of the initial Construction Baseline Schedule. Any areas which, in the opinion of the Contracting Officer, conflict with timely completion of the project shall be subject to revision by the Contractor.
2. Within seven calendar days after the joint review between the Contractor and Contracting Officer, the Contractor shall revise and resubmit the Construction Baseline Schedule in accordance with agreements reached during the joint review.
3. In the event the Contractor fails to define any element of work, activity, or logic, and the Contracting Officer review does not detect this omission or error, such omission or error, when discovered by the Contractor or Contracting Officer, shall be corrected by the Contractor within seven calendar days and shall not affect the contract period.
4. Upon acceptance of the Construction Baseline Schedule by the Contracting Officer, save the schedule as a baseline and update on a monthly basis. The construction schedule update will be used to evaluate the Contractor's monthly applications for payment based upon information developed at the monthly Construction Schedule update meeting.
D. Recovery Schedule: When periodic schedule update indicates the Work is 14 or more calendar days behind the current accepted schedule, a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule must also be submitted.
Indicate changes to working hours, working days, crew sizes, and equipment required to achieve compliance, and date by which recovery will be accomplished.
WICA - 310622 01 32 16 - 7
E. Computer Software: Prepare schedules using a program that has been developed specifically to manage construction schedules.
1. Use Microsoft Project or Primavera for Windows operating system.
PART 3 - EXECUTION
3.1 CONSTRUCTION SCHEDULE UPDATES
A. Progress Meeting Updates: Provide a 2 week look-ahead schedule, derived from the currently accepted schedule, before each weekly progress meeting. Utilize the look-ahead schedule to facilitate and take notes on discussions held during the progress meeting.
B. Monthly Schedule Updates:
1. General: Update the Construction Schedule on a monthly basis to reflect actual construction progress and activities throughout the entire contract period and until project substantial completion. The status date of each schedule update shall be the 7th day preceding the progress payment request date.
2. Procedure: The Contractor shall meet with the Contracting Officer each…