140L6220Q0084

AMD 0001

Collins Fence Removal and Construction

1. Drive post as an option instead of just digging wood post?

Yes, posts may be driven

2. Using a T post driven into ground with only 12" or so left above ground to use as deadman/ tie down and NOT use of rocks?

Yes, T-posts can be driven into the ground with only 12” left above ground and use as a deadman/tie down.

3. The four wheeler gate may need replaced concern about damage getting it out to reuse

BLM will supply a new gate if the old one cannot be reused and the vendor will need to install.

4. Mowing/ removing of sagebrush and trees.

a. Mowing and cutting of heavy brush will be permitted. No blading allowed.

b. Woody debris should be cut and scattered in heights of less than 18 inches, or added to slash piles.

c. If any trees greater than 7 inches diameter at breast height are removed, logs should not be added to slash piles. Disperse any other cleared debris adjacent to the fence.

5. How far out from fence can mowing or removal of trees?

a. 12 feet on either side