01009 General BFO BLM Collins Fence Project Final.pdf
PDF 885 KB Posted
- Attached to
- COLLINS FENCE REMOVAL & CONSTRUCTION Federal contract opportunity
- Solicitation number
- 140L6220Q0084
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L6220Q0084_Amd_0001.pdf | ||
| Site Visit_0001.pdf | ||
| 140l6220Q0084 AMD 0001 QUESTION AND ANSWERS_0001.docx | DOCX document | |
| Collins Fence Project Bid Schedule Final.xlsx | XLSX spreadsheet | |
| Sol_140L6220Q0084.pdf | ||
| Collins Fence Project Section 01505 Mobilization Final.pdf | ||
| 02834 Collins Wire and Gates Fence Project Final.pdf | ||
| Collins Fence Project 02827 Fence Removal Specs Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIVISION 1 SECTION 01009
GENERAL REQUIREMENTS GENERAL INFORMATION AND REQUIREMENTS
BFO BLM COLLINS FENCE REMOVAL AND REALIGNMENT PROJECT
01009-1
PART 1: GENERAL
1. BACKGROUND
The proposed fence will be a four-wire fence with a maximum wire height of 42 inches. The top three wires will be barbed wire and the bottom wire would be smooth. The wire spacing will be 16, 22, 30 and 42 inches from the ground to the top wire with new steel T posts and new wooden posts.
Steel T posts will be used every 16.5 Ft with wire stays equally spaced approximately every 8 feet in-between. Every fifth post will be a wood line post. There will be four 16-foot steel frame gates installed along the fence in accordance with the specifications in Figure 4. Proposed steel gate locations would be the same as existing wire gates, and where 2-track trails on the west side connect to the main road. Posts and adjacent fencing will be designed to discourage undesignated access and gate theft. On the southern end of the fence, an ATV cattleguard and walk-through gate will be moved and re-installed in line with the new fence.
The wire fence will follow relatively straight lines along rolling hills and gullies in loamy and clay topsoil. The elevational change from the highest point to the lowest point along the fenceline is approximately 150 feet, with one steep hill (approximate 50 foot elevational change in 350 feet of fence run) with a narrow margin for the fence to fit along the two track road. There is a 50-foot buffer on either side of the approved line in some portions where the fence could be moved to mitigate terrain issues. This fence line crosses rolling topography with several gullies and multiple hilltops. Type II End Panel (Double H) or Type I End Panel (HN combination) braces (see Figure
3) would be utilized on topography changes, the edge of a gully, or any time the fence starts and stops at a gate or the end of the line. This is expected to occur at approximately 48 locations.
Stress panels (Single-H) braces would be installed anytime that a stretch between a Double-H stress panel brace exceeds 650 feet or down in a large gully bottom. These are anticipated to be installed at approximately 12 locations. 3-Post Corner Panels will be installed at directional changes and corners. This is expected to occur at 12 locations. See Figures 3 and 5 for design specifications.
The fenceline crosses rolling terrain, including many low spots. These locations will require a Panel at Minor Depression including an extra wire and rock deadman, following the diagram in Figure 3.
This is anticipated to be necessary at up to 50 locations.
Motorized vehicles including skid steers, UTV’s, and tractors, will be authorized along the entire fenceline.
The entire fenceline has been surveyed and will be flagged before site tours and construction.
Specific flagging will be placed for locations of gates. Timing of the installation of the fence is expected to occur between October 1, 2020 and June 30, 2021. Exact dates of installation will be coordinated with the Contracting Officer.
01009-2
1.1 SUMMARY
A. Description of Work: Furnishing labor, equipment, and supplies, to remove and dispose of 3.16 miles (16,661 feet) of wire fence, and furnishing labor, equipment, and supplies to construct 3.04 miles (16,032 feet) of barbed wire fence. The fence construction will follow specifications from BLM Fencing Manual H-1741-1.
B. Location: The fence is located approximately 35 miles north of Gillette, Wyoming. The project site can be accessed by traveling on US Highway 59 north from Gillette for 33 miles, and then turning west into the Weston Hills USFS/BLM Recreation Area and traveling along the main road for 3 miles to the crest of the ridge. The project can then be accessed by a two-track dirt road that roughly parallels the fenceline to the north and south.
Available access routes to the project will be identified for use during the project site tour.
Access to project site for project activities will be coordinated with the BLM and BLM grazing lessees. Please see Figure 2 for the location of the fence in relation to Gillette, Wyoming. Please see Figure 1 for a map of project depicting the fence location.
C. Work Data Sheet: Designates the type and quantity of work required at each project location, and dimensions required for typical drawings.
1.2 REFERENCES
A. Referenced Specifications and Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications and standards referred to herein may be procured by the Contractor from the following sources:
ASTM American Society for Testing and Materials 100 Barr Harbor Dr.
West Conshohocken PA 19428-2959
AWPA American Wood Preservers' Association
P.O. Box 286 Woodstock MD 21163
OSHA Occupational Safety and Health Administration
US Department of Labor 200 Constitution Ave., NW
Washington DC 20210
01009-3
1.3 DEFINITIONS
A. Approvals: Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer's attention in writing. After approval of an item, submit a substitute for approval when the approved item cannot be purchased or delivered in time to avoid delay in completion of the project.
1.4 CERTIFICATES OF CONFORMANCE
A. Requirements: The Contracting Officer may permit use, prior to sampling and testing, of materials when accompanied by Certificates of Conformance. Materials used on the basis of a Certificate of Conformance may be sampled and tested. Installation of materials on the basis of Certificates of Conformance shall not relieve the Contractor of responsibility for incorporating materials which conform to the requirements of the drawings and specifications. Material not conforming to those requirements will be subject to rejection, whether in place or not.
B. Format: The Certificate of Conformance provided by the supplier shall:
1. State that the named product conforms to the Contract requirements.
2. Either be accompanied with a certified copy of the test results or certify that such test results are on file with the manufacturer and will be furnished to the Contracting Officer upon request.
3. Provide the name and address of the manufacturer, the testing agency, and the date of tests.
4. Set forth the means of identification which will permit field determination of the product delivered as being the product covered by the certification.
1.5 QUALITY ASSURANCE
A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.
B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.
01009-4
1.6 DELIVERY, STORAGE, AND HANDLING
A. Delivery: Protect products incorporated into the work from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated.
B. Storage: Provide temporary storage facilities for products. Storage shall comply with the manufacturer's instructions. The storage area shall permit access for inspection and handling.
C. Handling: Load and unload products protecting them from damage.
1.7 PROJECT/SITE CONDITIONS
A. Access to the Work: Access to the project site is by County roads and two track trails.
B. Environmental Considerations: Removal of brush eight feet along the fence line will be allowed.
1.8 SEQUENCING AND SCHEDULING
A. Work Schedule: The schedule shall be submitted at the pre-work conference. When requested, submit an updated schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the estimate.
PART 2: PRODUCTS
(There are no applicable requirements.)
PART 3: EXECUTION
3.1 PROJECT MEETINGS
A. Pre-Work Conference:
1. A Pre-Work Conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
2. The Contractor, subcontractors, and the persons responsible for coordination of the work shall be present at the meeting.
3. Contractor shall ne prepared to summarize and explain procedures planned for the project.
B. Progress Meetings:
1. To be held at the project site, or as determined by the Contracting Officer.
01009-5
2. May be called by either the Contracting Officer or the Contractor. Request shall state who should attend and include an agenda.
C. Final Inspection:
1. To be held at the project site, or as determined by the Contracting Officer.
2. Notify the Contracting Officer in writing at least 5 working days before the completion date so the Government can schedule final inspection.
3. The Contractor’s superintendent shall be present during this inspection.
3.2 PREPARATION
A. Work Layout: The Contractor will set stakes for measurements, lines, and grades necessary for the work executed under the Contract.
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: The work described in this section will not be measured for payment.
4.2 BASIS OF PAYMENT
A. Payment: No direct payment for the work described under this section will be made.
Consideration for this item shall be included in the bid price for other items of the Contract.
01009-6
Figure 1: Collins Fence Replacement and Realignment Project Area
01009-7
Figure 2: Collins Fence Project Area in Relation to Gillette, Wyoming
END OF SECTION
PART 1: GENERAL
File details come from the government source that posted it. Updated .