Amendment_2_-_Q_A_0002.docx

DOCX document 13 KB Posted

Attached to
BASIN VIEW PIPELINE Federal contract opportunity
Solicitation number
140L3423Q0001
Issued by
Department of the Interior Bureau of Land Management Montana-Dakotas

View the file

Other files for this federal contract opportunity

Other files attached to BASIN VIEW PIPELINE, newest first.
File Type Posted
Sol_140L3423Q0001_Amd_0002.pdf PDF
B09_Questions_and_Answers_0001.pdf PDF
Sol_140L3423Q0001_Amd_0001.pdf PDF
B03_Wage_Determination.pdf PDF
A06_WBI_Energy_-_Line_Crossing_and_Encroachment_Permit.pdf PDF
A06_WBI_Energy_Checklist.pdf PDF
A06_Attachment_A_BasinViewPipeline3.pdf PDF
A06_Specifications.pdf PDF
Sol_140L3423Q0001.pdf PDF
A06_Schedule_of_Items.pdf PDF
Past_Performance_Questionnaire.doc DOC document
A06_Maps_and_Drawings.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT #2 – Clarification

Question: There is a wet crossing in this pipeline and I’m wondering how to bid that crossing if we have to do a bore on this schedule of items on the bid sheet?

Answer: Section 02229 1.3 C. identifies that subsurface water and caving soils may also exist along the alignment. Trenching, pulling or plowing pipe through water or caving soils will be considered as trenching/plowing (common), except if conditions require the use of a backhow or excavator to install pipe to the proper installation depth which will be paid for under trenching/plowing (rock). (Please full set of specifications for all details)

To clarify: A contractor can choose to trench or bore this area. BLM does not have a preference as it is part of the linear feet quantities. To keep everyone on the same page, include trenching and/or boring costs associated with this area to line-item number 3. Do not add additional items or quantities to the schedule.

It is important to emphasize that the best value quote will result in a firm-fixed price contract. The quantities listed on the schedule of items are estimated quantities only. Only quote the quantities listed. Any quantities that decrease or increase within a 15% barrier either way, will be paid at the unit price quoted on the Schedule of Items but must be pre-approved by the Contracting Officer. Any quantities outside of the estimated quantities on the Schedule of Items must be pre-approved by the Contracting Officer and, if approved, the price will be negotiated between the Contracting Officer and the Contractor.