Pre-bid_meeting_tjs_20210709_0001.pdf
PDF 156 KB Posted
- Attached to
- ROSS POINT RECREATION SITE IMPROVEMENTS PHASE 1
- Solicitation number
- 140L2621R0006
About this file
This document outlines requirements for the Ross Point Recreation Site Improvements Phase 1 federal contract opportunity. The Bureau of Land Management Idaho Region is soliciting offers for construction services to improve facilities at the Ross Point Recreation Site. Offerors must provide pricing for site work including constructing a new floating pier, installing riprap, and upgrading utilities and site amenities. The period of performance is from September 13, 2021 to July 30, 2022. Questions are due by July 14th and offers must be submitted electronically by July 10th. Award will be made to the lowest priced technically acceptable offer. The pre-bid meeting notes provide additional details on submittal requirements, site access, and clarifications to the solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ross Pt Rec Site Improvements Ph 1, Coeur d’Alene District July 9, 2021 Solicitation 140L2621R0006, Pre-bid Tour Meeting Notes
T. Syverson Page 1 of 3
NOTES AND RECOMMENDATIONS
Attendees:
Name and Company Address Phone Number E-mail Address Thane Syverson, District Engineer, BLM-DOI
3232 W. Nursery Rd, Coeur d’Alene, ID 83815
208-769-5013 tsyverson@blm.gov
Jake Bachtel, Outdoor Recreation Planner
3232 W. Nursery Rd, Coeur d’Alene, ID 83815
208-769-5041 jbachtel@blm.gov
Matt Pacotti, Project Manager, NNAC Construction
3901 N. Schreiber Way, Coeur d’Alene, ID 83815
208-635-5400 matt.pacotti@nnac.com
The meeting started at 9:00 a.m. on site at the parking area of Ross Point Rec Site on the Coeur d’Alene District.
Thane Syverson, the Contracting Officer’s Representative, described the scope of the project and the following items:
1. SF 1442
a. Item 11. The Contractor shall begin performance within 10 calendar days and complete it within 320 calendar days after receiving notice to proceed.
b. Item 13. Sealed offers are due by 10 MDT 7/22/2021.
2. OF 336, Period of Performance: 9/13/2021 to 7/30/2022
3. Page 4, Project Description
a. Questions Due Date: Wednesday, July 14, 2021, at 10:00 a.m. MDT
b. Proposal Due Date: Thursday, July 22, 2021 at 10:00 a.m. MDT
c. Award Selection Process: Lowest Price Technically Acceptable
4. Section F: Deliveries or Performance
a. F.2 52.211-10 Commencement, Prosecution and Completion of Work
i. The anticipated length of the seasonal delay for this project is 0 days. This number of days has been included in calculating the stated period of performance. Therefore, the contract period of performance will not be extended due to normal seasonal weather delays.
5. Section H: Special Contract Requirements
a. H.1 Work Hours:
i. The performance period established for this contract is based upon all work being conducted during regular working hours between 7:30 a.m. and 5:30 p.m., Monday through Friday, excluding government holidays.
mailto:tsyverson@blm.gov mailto:jbachtel@blm.gov
T. Syverson Page 2 of 3
ii. This conflicts with Section 011000 – Summary of the Specifications, 1.3. Use of Premises, which states Schedule operations so that Work is conducted during regular office hours which are 7:00 a.m. – 7:00 p.m.
iii. The Special Contract Requirements govern over the Specifications. So, the allowed regular working hours are between 7:30 a.m. to 5:30 p.m., Monday through Friday, excluding government holidays.
6. Section L: Instructions, Conditions and Notices to Offerors
a. L.16 Proposal Submittal: The offeror is to submit a fully compliant proposal to the following email address: pfort@blm.gov.
b. L.17 Volume Format Instructions
i. (c) There are page limitations to two volumes of the proposal.
c. L.18 Volume 2: Factor 1, Technical Approach/Capabilities
i. Thane Syverson, COR, discussed the volumes and factors in general terms.
7. Section M: Evaluation Factors for Award
a. M.1 Basis for Contract Award:
i. Thane Syverson, COR, discussed paragraph (b) in general terms.
8. Section C: Specifications/Drawings
a. Section 011000 – Summary
i. 1.3 Use of Premises, A. Contractor shall have full use of premises for construction operations, including use of Project site, during construction period.
b. Section 013300 – Submittal Procedures
i. There are many submittals required for this contract. See the individual construction specification sections for submittal requirements.
ii. (c) Processing Time. The Government is allowed up to 14 days for review of initial submittals and resubmittals. Thane Syverson (COR) expressed that he generally responds much more quickly than this, a day or two for simple submittals and less than a week for more involved or complex submittals.
c. Section 015000 – Temporary Facilities and Controls
i. 2.1 Temporary Utility Installation, A. Sanitary Facilities, 1. Toilets: Use of
Government’s existing toilet facilities will be permitted as long as facilities are cleaned and maintained in a condition acceptable to Government. At Substantial Completion, restore these facilities to condition existing before initial use.
1. Otherwise, provide sanitary facilities in accordance with 2.1.A.
ii. 2.3 Security and Protection Facilities Installation
1. D. Furnish and install site enclosure fence in a manner that will prevent people and animals from easily entering site except by entrance gates.
d. Section: 015723 – Temporary Storm Water Pollution Prevention
i. 3.2 Regulatory Requirements, A. Permits: Obtain required NPDES permits in manner resulting in no impacts to scheduled work. File notices of intent and termination.
mailto:pfort@blm.gov
T. Syverson Page 3 of 3
ii. 3.5 Housekeeping and Site Management
1. C. Provide spill prevention and control plan with provisions place in
SWPPP.
Questions and Answers:
1. Question: Sheet 12 of the plans, drawing sheet C502, Dock Requirements: Item 3 requires 2’ x 2’ Reinforced Concrete Deck Panels. How are these secured in place?
Answer: We believe they are typically contained by plates around the edges of the dock.
Examples of docks with these panels can be seen at the Hauser Lake Boat Launch and Sun-up Bay Boat Launch. We believe the Sun-up Bay Boat Launch was designed by Welch Comer & Associates.
2. Question: Are there any restrictions regarding pile driving for the pier and dock, i.e. vibratory
vs. impact hammer?
Answer: According to the Letter of Concurrence from Fish and Wildlife Service, USDOI, pilings will be driven using an impact hammer with a wooden block cushion to reduce noise.
3. Question: What are the requirements for sediment control for in water work? Is dewatering required to install the rip rap if installed during low flow?
Answer: Type 2 turbidity curtains are required for sediment control for in water work.
Dewatering is not required if rip rap is installed at ordinary low water stage of flow.
Proposed Amendments:
Section C: Specifications/Drawings:
Section 011000 – Summary, 1.3 Use of Premises: Delete all of item B and replace with “Schedule operations so that Work is conducted during regular office hours which are 7:30 a.m. – 5:30 p.m.”
Section 312000 – Earth Moving, 3.1 Preparation: Add item “D. Type 2 turbidity curtains shall be installed before the start of any excavation work for the installation of rip rap in the Spokane River, or adjacent to the river where water may infiltrate the excavated area. The turbidity curtains shall envelop the excavated areas and be maintained until the installation of the rip rap is completed to above the water level. Turbidity curtains shall be compliant with Clean Water Act, NPDES and Idaho DOT requirements.”
Section 355113 – Floating Pier, 3.1 Installation: Add to the end of Item B “All pilings shall be driven using an impact hammer with a wooden block cushion to reduce noise.”