Attachement_1_1_REVISED_Statement_of_Work_0001.pdf
PDF 896 KB Posted
- Attached to
- BLM-CO ROAN CABIN REPAIRS
- Solicitation number
- 140L1723R0019
About this file
This statement of work outlines modifications required at the Roan Cabin administrative site located on the Roan Plateau in Colorado. The contractor will install compliant spark arrestors and chimney cleaning, add non-combustible barriers around wood stoves, and widen loft and deck stairs to meet NFPA and OSHA standards. This includes installing handrails and ensuring stair widths are at least 36 inches. The contractor must provide all equipment, materials, transportation, and safety/security for the project. Work must be completed by December 1, 2023 and will be inspected by the BLM contracting officer's representative for compliance with applicable building codes.
This statement of work is related to federal contract opportunity number 140L1723R0019 issued by the Bureau of Land Management Colorado Region to make repairs at the BLM's Roan Cabin facility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Roan Cabin Safety Compliance Modifications Colorado River Valley Field Office
2300 River Frontage Road Silt, CO 81652
Prepared by Matthew Ringer and Wesley Toews
Statement of Work
Government’s requirements: At the Roan Cabin Bureau of Land Management Administrative Site located on the Roan Plateau at 39.593830, -107.918118.
(a) What is to be done:
1. Install a compliant spark arrestor on chimney that meets NFPA 211 4.6.4.
2. Complete annual chimney cleaning.
Photo of chimney
3. Install a minimum of 24-gauge sheet metal or other compliant non-combustible material extending a minimum of 36 inches from the nearest corner of the stove and a minimum of 18 inches from the chimney. The non-combustible material must have spacers behind barrier allowing for 1 inch of ventilation. Materials and installation should meet NFPA 211 12.5.1.2 and 12.6.
4. Install a 24-guage sheet metal or other compliant non-combustible material behind the stove covering the wall from the floor to a height of 6 feet extending at least 18 inches on either side of the stove flue. One-inch spacers required to be installed behind non-combustible material. Materials and installation should meet NFPA 211 12.5.1.2 and 12.6.
Photo of wood stove
Photo of wood stove
5. Widen opening on loft stairs where necessary to meet NFPA compliance for stair width clearance and install OSHA-compliant handrails on loft and deck stairs.
The stairs leading to the A-frame cabin deck have eight risers. The stairs are equipped with a guardrail but no handrail. The stairs to the loft bedroom are 24 inches wide. The existing handrail begins at the third riser and extends to the fifth riser (right side ascending). The remaining risers are not equipped with a handrail.
Stairs must be 36 inches wide per NFPA 101, 7.2.2 - Stairs as outlined in the below table.
NFPA Existing Stairs Dimensions Table
A handrail is a rail used to provide employees with a handhold for support.
Handrails must be not less than 30 inches and not more than 38 inches, as measured from the leading edge of the stair tread to the top surface of the handrail. Handrails and stair rail systems must have smooth surfaces to protect employees from injury, such as punctures or lacerations, and to prevent catching or snagging of clothing. They must have the shape and dimension necessary so employees can grasp the handrail firmly. In addition, handrail and stair rail systems are required to have a minimum clearance between handrails and any other object is 2.25 inches. The ends of handrails and stair rail systems must not present any projection hazards.
Handrails and the top rails of stair rail systems must be capable of withstanding, without failure, a force of at least 200 pounds applied in any downward or outward direction within 2 inches of any point along the top edge of the rail.
A stair rail is a barrier erected along the exposed or open side of a stairway to prevent employees from falling to a lower level. OSHA requires each flight of stairs having at least three treads and at least four risers to be equipped with stair rail systems and handrails as outlined in the table below:
OSHA Handrail Table
A stair railing consists of a top rail, midrail, and posts, and must have a vertical height not more than 34 inches nor less than 30 inches from the upper surface of the top rail to the surface of the stairs. The length of the railing top rail must be smooth. The midrail must be located approximately halfway between the top rail and the stairs. Guardrail systems must be capable of withstanding, without failure, a force of at least 200 pounds applied in a downward or outward direction within 2 inches of the top edge, at any point along the top rail.
The height of stair rail systems installed before January 17, 2017, must be not less than 30 inches from the leading edge of the stair tread to the top surface of the top rail; the height of stair rail systems installed on or after January 17, 2017, must be not less than 42 inches from the leading edge of the stair tread to the top surface of the top rail.
For installations prior to January 17, 2017, the top rail of a stair rail system may serve as a handrail when the height of the stair rail system is not less than 36 inches and not more than 38 inches as measured at the leading edge of the stair tread to the top surface of the top rail.
For stair rail systems installed on or after January 17, 2017, the top rail and handrail must be separate. The top rail must be at least 42 inches high, and the handrail must be 30 to 38 inches high (as measured at the leading edge of the stair tread to the top surface of the rail).
OSHA diagram
Photo of loft stairs
Photo of deck stairs
(b) What is end product:
All identified modifications and construction completed per the regulations provided and consistent with International Building Code (IBC). Any wall removal or widening of area above steps must be replaced with an OSHA compliant railing and NFPA compliant stairs. Any structure modifications will also meet OSHA, NFPA and IBC. All construction debris will be disposed of by the contractor unless alternative disposal methods are specifically approved by the Contracting Officer Representative (COR).
(c) Any materials to be provided to accomplish:
Contractor will provide all equipment and materials needed for project. Electrical power may be provided by the BLM on site.
(d) Where materials come from:
Contractor will provide all equipment and materials needed for project completion.
(e) Volume of work (scope):
Contractor is responsible for completion of identified projects, supplying materials, repairing any damage to structure caused by construction or by accident, transportation to and from site, safety and security of construction site and bringing their own potable water.
(f) Work process (non - restrictive):
Site evaluation will be coordinated with BLM COR or another designated agency representative.
(g) Guides / controls pertinent to performance:
Compliance with NFPA, OSHA and other applicable building codes.
Delivery:
(a) Completion time and acceptable form and place:
Project completion by December 1st, 2023.
Inspection & Acceptance:
(a) Responsibility for and acceptability requirements:
BLM COR or designated agency representative will determine acceptance of completed work as meeting the requirements. BLM inspections may occur at any time during project work.
Project Inspector: Wesley Toews
COR: Alex Provstgaard
Market Research: Several local construction and fireplace companies were contacted to provide a cost estimate. Due to the remote location and type of work, the companies contacted did not respond or requested to be paid for a site visit to review the proposed work. As a result, no market research was able to be collected.
Pre-bid Tour: Thursday, August 31, 2023 9:00 AM-1:00 PM. Meet at the Rifle Ranger District Office at 0900 sharp. It's a long way up there!
| (a) What is to be done: |
| 1. Install a compliant spark arrestor on chimney that meets NFPA 211 4.6.4. |
| 2. Complete annual chimney cleaning. |
| Photo of chimney |
| 3. Install a minimum of 24-gauge sheet metal or other compliant non- combustible material extending a minimum of 36 inches from the nearest corner of the stove and a minimum of 18 inches from the chimney. The non-combustible material must have spacer... |
| 4. Install a 24-guage sheet metal or other compliant non-combustible material behind the stove covering the wall from the floor to a height of 6 feet extending at least 18 inches on either side of the stove flue. One-inch spacers required to be instal... |
| Photo of wood stove |
| Photo of wood stove |
| 5. Widen opening on loft stairs where necessary to meet NFPA compliance for stair width clearance and install OSHA-compliant handrails on loft and deck stairs. |
| The stairs leading to the A-frame cabin deck have eight risers. The stairs are equipped with a guardrail but no handrail. The stairs to the loft bedroom are 24 inches wide. The existing handrail begins at the third riser and extends to the fifth rise... |
| Stairs must be 36 inches wide per NFPA 101, 7.2.2 - Stairs as outlined in the below table. |
| NFPA Existing Stairs Dimensions Table |
| A handrail is a rail used to provide employees with a handhold for support. Handrails must be not less than 30 inches and not more than 38 inches, as measured from the leading edge of the stair tread to the top surface of the handrail. Handrails and ... |
| Handrails and the top rails of stair rail systems must be capable of withstanding, without failure, a force of at least 200 pounds applied in any downward or outward direction within 2 inches of any point along the top edge of the rail. |
| A stair rail is a barrier erected along the exposed or open side of a stairway to prevent employees from falling to a lower level. OSHA requires each flight of stairs having at least three treads and at least four risers to be equipped with stair rai... |
| stair tread to the top surface of the rail). |
| OSHA diagram |
| Photo of loft stairs |
| Photo of deck stairs |
| (b) What is end product: |
| All identified modifications and construction completed per the regulations provided and consistent with International Building Code (IBC). Any wall removal or widening of area above steps must be replaced with an OSHA compliant railing and NFPA compl... |
| (c) Any materials to be provided to accomplish: |
| Contractor will provide all equipment and materials needed for project. Electrical power may be provided by the BLM on site. |
| (d) Where materials come from: |
| Contractor will provide all equipment and materials needed for project completion. |
| (e) Volume of work (scope): |
| Contractor is responsible for completion of identified projects, supplying materials, repairing any damage to structure caused by construction or by accident, transportation to and from site, safety and security of construction site and bringing their... |
| (f) Work process (non - restrictive): |
| Site evaluation will be coordinated with BLM COR or another designated agency representative. |
| (g) Guides / controls pertinent to performance: |
| Compliance with NFPA, OSHA and other applicable building codes. |
| (a) Completion time and acceptable form and place: |
| Project completion by December 1st, 2023. |
| (a) Responsibility for and acceptability requirements: |
| BLM COR or designated agency representative will determine acceptance of completed work as meeting the requirements. BLM inspections may occur at any time during project work. |
File details come from the government source that posted it. Updated .