A04 MVNWR.Revised SOW. 7-24-20_0003.pdf
PDF 296 KB Posted
- Attached to
- NV-MOAPA VALLEY NWR D/B NEW STREAM CHANN
- Solicitation number
- 140F0120R0019
About this file
This statement of work describes a design-build contract opportunity for a federal agency. The selected contractor will be responsible for designing and constructing approximately 500 feet of naturalized stream channel at the Moapa Valley National Wildlife Refuge in Nevada to restore habitat connectivity for an endangered fish species. Key deliverables include design development drawings, construction documents, permitting support, demolition of an existing culvert, construction of the new stream channel and associated features, installation of a reinforced concrete box culvert if opted for, site restoration including revegetation, and project closeout documentation. The period of performance is estimated from October 2020 to September 2021. The solicitation number is 140F0120R0019 and was issued by the U.S. Fish and Wildlife Service. Evaluation criteria include the offeror's experience with similar aquatic habitat and stream construction projects.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Design/Build New Stream Channel in Lower Pedersen Stream and Design/Build Option Items if Awarded
U.S. Fish and Wildlife Service
Moapa Valley National Wildlife Refuge (NWR) – Moapa, Nevada
Revised July 124, 2020
Z:\CONSTRUCTION - AE\CONTRACT FILES\TEAM 3\Cindy Salazar\1. FY 20 Working\140F0120R0019 Moapa Valley DB Stream Channel\3 - MVNWR.Revised SOW. 7-24-20.docx
1.0. GENERAL INFORMATION.
1.1 Contractor shall provide Design-Build Services for the Design and Construction of
Approximately 500 Feet of Naturalized Stream Channel in Pedersen Stream and All Associated Appurtenances. The Project / Contract is located at Moapa Valley NWR in Moapa, Nevada. No Design Development Drawings or Construction Drawings and Specifications have been prepared in advance for this Project / Contract. The Contractor shall be responsible for Developing, Preparing, and Submitting Design Development and Construction Documents (Drawings and Technical Specifications) at the 35%, 65%, and 100% Construction Document Milestones.
1.2 Contractor’s Qualifications: Contractors shall be experienced and have demonstrated positive past performance with the Design and Construction / Installation of Naturalized Stream Channels and In-Stream Channel Design and Construction.
Contractors shall demonstrate extensive knowledge, ability, and skill in Design and Construction of Stream Channels and Restoration of Aquatic Habitat typical of the area.
Contractors shall demonstrate knowledge of All Relevant State and Federal Accessibility Laws, Codes, Regulations, Standards, and Provisions.
Furthermore, Contractors shall demonstrate extensive experience applying this knowledge in Construction and Stream Design to restore habitat for native fish and other aquatic species.
Refer to Section L and M of the Solicitation for Evaluation Factors. Bidding Contractors shall provide five (5) specific example Naturalized Channel and In-Stream Channel Design and Construction Projects and/or Similar Scope Projects as part of their Past Experience (i.e. Recent Relevant Experience) and Past Performance Narrative, which have occurred over the last 5 years. In addition to Past Experience (Recent Relevant Experience) and Past Performance Evaluation Factors, the Design-Build Contractor (Contractor) shall be required to submit on Technical Capability and Technical Approach Evaluation Factors.
1.3 Regulatory Requirements: It is the Contractor’s responsibility to construct the Project in compliance with applicable requirements of federal and state laws, codes, rules, regulations, ordinances, and standards, including, but not limited to, those outlined below. Contractor shall have copies available of applicable codes and regulations for ready reference. These shall include, but are not limited to:
- State and Local Regulatory Requirements
- Federal Regulatory Requirements
- FWS Policies
- Codes
- NFPA 101 Fire and Life Safety Code, latest edition
- International Building Code as adopted by the Local Authority Having Jurisdiction.
- International Plumbing Code
- International Mechanical Code
- National Electrical Code
- Architectural Barriers Act (ABA)
In the event of a conflict, the most stringent laws, codes, regulations, standards, and provisions shall apply.
2.0. WORK LOCATION AND PERIOD OF PERFORMANCE.
2.1 Work Location: Moapa Valley National Wildlife Refuge (MVNWR), 4225 West Warm
Springs Road, Moapa, Nevada 89025.
New Gage Coordinates: 36.71050112, -114.71467166
The new stream channel will be immediately downstream from the coordinate values noted above. The USFWS does not know the exact coordinates for the new stream channel because this will depend on the design/engineering performed.
2.2 Period of Performance:
Start Date: October 1, 2020 – Estimated (Depends on NTP Date).
End Date: September 30, 2021 – Estimated (Depends on NTP Date).
Site Conditions of the area of interest consists of a thermal spring system, riparian areas, and desert uplands. The soil in the area is sandy loam. Although dace can spawn year-round, peak spawning occurs during spring and early summer. Therefore, work within the stream itself will be restricted to fall and late summer.
In-Water Construction Work Window:
(October 1 – March 1 and July 1 – September 30).
In the event of damage to government property resulting from construction, the contractor shall return the damaged area to its original condition. The contractor will also be instructed where to access the Construction Site to minimize potential damage to the existing resources.
The Period of Performance for this Contract is 1-year from the actual date of Notice to Proceed (NTP) Letter. Anticipated Delivery Date for NTP Letter is 30 Days Following Initial Contract Award Date. Above dates shown are tentative and subject to change.
Contractor shall coordinate with the Refuge Manager and/or Project Leader for a Proposed Construction Work Window. The Final Accepted Construction Work Window will be mutually agreed to between the Contractor and USFWS Moapa Valley NWR prior to Construction.
2.3 Normal Business Hours for the Refuge, Monday thru Friday 7:00 a.m. - 5:00 p.m. Work Activities shall be performed during Normal Business Hours. Limited accommodation to an alternate schedule may possible with coordination with on-site FWS staff. In the event of emergencies, Contractor shall provide contact information.
2.4 Non-duty hours include week nights, weekends, and Government holidays (New Year’s Day, Martin Luther King JR.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day).
3.0. DEFINITIONS.
Not Used.
4.0. BACKGROUND.
The Moapa Valley National Wildlife Refuge (MVNWR) is operated by the U.S. Fish and Wildlife Service (USFWS). It is located approximately 10.3 miles northwest of Glendale, Nevada. The nearest major City/town is Las Vegas, Nevada located approximately 58.7 miles southwest of MVNWR.
The Future Awarded Contract is to result in the Design-Build of approximately 500 feet of
Naturalized Stream Channel in Pedersen Stream at Moapa Valley National Wildlife Refuge (MVNWR) in Clark County, Nevada. The Muddy River Ecosystem in Clark County, Nevada begins in the Warm Springs Area where thermal springs from the regional carbonate aquifer coalesce over a short distance to create the main stem Muddy River. Many endemic, thermophilic species occur in the Warm Springs Areas including the monotypic Moapa dace (Moapa coriacea), which was originally listed as an Endangered Species in 1967 and subsequently designated with a recovery priority of 1 (highest priority) in the Endangered Species Act of 1973. There are currently three barriers to fish passage (culvert, stream gauge, and waterfall) on the Pedersen Stream and a newly-constructed channel and culvert are required to allow Moapa dace to move freely upstream to the springhead.
Purpose.
The purpose of this project is to restore connectivity between breeding habitat located in the Pederson stream springhead on the Moapa Valley National Wildlife Refuge and downstream habitat on the privately-owned Warm Springs Natural Area (Southern Nevada Water Authority) for the federally-endangered Moapa Dace (Moapa coriacea). Restoring connectivity will enable dace to access breeding habitat through installation of a reinforced concrete box culvert, relocation of an existing US Geological Survey stream gauge, and excavation of new stream channel to re-route a portion of the stream.
5.0. SCOPE OF WORK.
Pre-Demolition and Pre-Construction Permitting. Development, Preparation, and Submittal of Permit Applications and Supporting Documents to the Permit Agencies / Permit Authorities for Review and Approval / Disapproval. Contractor shall be responsible for Identification of Permits through a Permit Registry. After identifying permits, the Contractor shall apply for, Pay, and Secure Permits to result in successful project delivery.
The Scope of Work for this contract shall include the Design, Construction, and Installation of the Following Project Design Elements:
Demolition, Removal, Recycling, and Disposal of Existing Under-Road Culvert.
Construction and Installation of:
New Stream Channels.
New Stream Banks / Embankments.
New Reinforced Concrete Box Culvert.
Road Embankments.
Road Courses to include the surface course, base course, and subbase course.
Restoration of Stream Channel, Surrounding Site, Re-Seeding, and Re-Vegetation.
The Contractor shall accomplish the following Tasks if awarded this contract:
5.1 TASK 1. 35% Draft Design Development Documents (Drawings and Specifications).
(Base Task).
The 35% Draft Design Development Drawings and Specifications shall fully define and describe All Base and Option Tasks / Elements selected for Contract Award and required for constructing this Project. The Level of Detail for the Design and Engineering Sections of Work shall be as follows:
• The 35% Submittal Documents shall describe All of the Architectural and Engineering Design Elements to be included in the Final Document Package, including, but not limited to the following:
Renderings, Existing Conditions Plans, De-watering and Diversion Plans, Demolition Plans, Site Plans, Topographic Survey Background Base Maps, Stream Channel Maps, Sections, Elevations, Details, Engineering Design Drawings, Design Criteria, Design Parameters, Design Calculations, Code Analyses, Project Constraints, Environmental Constraints, Engineering Design Schedules, Project Design Narrative Description, and Technical Specifications.
The 35% Technical Specifications shall be Developed, Prepared, and Submitted in PDF and DOCX File Extensions. The 35% Technical Specifications shall be incorporated into the 65% Technical Specifications.
• The Contractor shall incorporate the findings of any Cultural Resource Evaluations
(provided by the USFWS Project Leader) to determine necessary Cultural Coordination, Report / Application Preparation (including supporting documents), or documents for processing through the State/Tribe regulatory entity. (For example, TERO agreements if Applicable).
• The Drawings shall indicate work, which has Added any Scope (beyond the Scope of the
Contract) using Revision Clouds and Annotations. A separate Accounting by the Contractor shall be provided in XLSX File Extension for Changes to Scope (considered beyond the Scope of the Contract) Any Changes to Scope beyond the Scope of the Contract shall be Approved by the Government (USFWS) prior to the Contractor continuing with the next Phase. The 35% Submittal shall also identify “Work by Others” required for the Project to be successfully Constructed / Installed as Designed.
• The Contractor’s Professional Engineer under Subcontract shall conduct a Safety
Analysis - Perform Code Reviews, and Ensure the Design and Construction complies with (but is not limited to) the USFWS Manuals, Current Edition of the Federal and State OSHA safety Requirements, Applicable Bridge and Dam Safety Regulations, National Fire Protection Association 101 Life Safety Code, National Electrical Code, International Plumbing Code, International Building Code, International Mechanical Code, National Gas Code, and Similar Model Codes.
• The Contractor shall be required to Apply For, Pay, and Secure Permit Applications, Inspections, and Develop, Prepare, and Submit Supporting Documents (to include but not be limited to: Environmental, Cultural Resource Clearance, Utility Company, Local Building Department, and Local Department of Transportation Permits and Inspections).
• Unless explicitly agreed to otherwise by the USFWS, Identify, Annotate, Develop, Prepare and Submit Permit Applications for USFWS Signature with Supporting Documents (To Include But Not be Limited To: Permit Drawings, Narratives, Biological Assessments, and Similar).
• In summary, this 35% Draft Submittal shall include All of the Above Items to result in
35% Detail Drawings, 35% Technical Specifications, and a 35% Design and Construction Schedule.
Deliverables:
(1) Electronic Copy of 35% Drawings and Specifications (plans, elevations, sections, and construction details).
(1) 35% Design Summary / Project Narrative.
(1) 35% Design and Construction Project Schedule.
(1) Completed USFWS Safety Checklist.
(1) Copy of All Permit Applications and Supporting Documents.
(1) Electronic Copy of the 35% Permit and Submittal Registry
Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available.
5.2 TASK 2. 65% Draft Construction Documents (Drawings and Specifications).
(Base Task).
After Responding to 35% USFWS Review Notes, the Contractor’s Architect-Engineer Company shall develop, prepare, and submit 65% Draft Construction Documents consisting of drawings, specifications, and an Engineer’s Opinion of Probable Construction Cost and the Contractor’s Opinion of Probable Construction Schedule. The Contractor shall provide Review Copies of the 65% Construction Documents to the USFWS within 45 Calendar Days after Receipt of Review Notes concerning the 35% Draft Design Development Submittal.
(1) Electronic Copy of the 65% Drawings and Specifications (to include plans, elevations, sections, and construction details).
(1) Electronic Copy of the 65% Design Summary / Project Narrative.
(1) Electronic Copy of the Engineer’s Opinion of Probable Construction Cost.
(1) Electronic Copy of the Contractor’s Opinion of Probable Construction Schedule.
(1) Electronic Copy of the 65% Permit and Submittal Registry.
Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available. Registries (Registers) for Permits and Submittals shall be submitted in XLSX File Extensions.
5.3 TASK 3. 100% Draft and Final Construction Documents (Drawings and Specifications).
(Base Task).
After Finalizing the Response to the 65% USFWS Review Notes, the Contractor’s Architect- Engineer Company shall develop, prepare, and submit 100% Draft and Final Construction Documents consisting of Final Drawings, Specifications, and a Contractor’s Opinion of Probable Construction Schedule.
(1) Electronic Copy of 100% Draft Drawings and Specifications (to include plans, elevations, sections, and construction details) for Review and Approval.
(1) Electronic Copy of 100% Final Drawings and Specifications (to include plans, elevations, sections, and construction details).
(1) Printed 22 x 34 Inch Size Drawings and (1) Printed 8.5 x 11 Inch General and Technical Specifications Manual mailed to Moapa Valley National Wildlife Refuge.
(1) Electronic Copy of the 100% Draft Design Summary / Project Narrative for Review and Approval.
(1) Electronic Copy of the 100% Final Design Summary / Project Narrative.
(1) Electronic Copy of the 100% Draft and Final Engineering Design Calculations for Landscape Architecture, Civil, Water Resources, Environmental, and Structural Engineering Design Elements.
(1) Electronic Copy of the 100% Permit and Submittal Registry, which includes a Minimum Listing of Required Submittals to be submitted Prior to, During, and After Construction. The Submittal Registry shall incorporate the Permit Registry Prepared and Submitted in TASK 1.
As-Built Record Drawings. The Contractor shall work with the Site Superintendent during Construction to Document any Field Changes and provide CAD As-Built Record Drawings at the Closeout of the Project.
Deliverables:
(1) Electronic Copy of As-Built Record Drawings.
(1) Printed Mark-Up 22 x 34 Inch Size Drawings and (1) Printed Mark-Up 8.5 x 11 Inch General and Technical Specifications Manual mailed to Moapa Valley National Wildlife Refuge.
Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available. Registries (Registers) for Permits and Submittals shall be submitted in XLSX File Extensions.
5.4 TASK 4. Mobilization and De-Mobilization from Project Site.
(Base TASK).
Mobilize All Labor, Materials, Equipment, and Tools onto the Project Site.
De-Mobilize All Labor, Materials, Equipment, and Tools from the Project Site.
5.5 TASK 5. Site, Sediment, and Erosion Control Measures.
(Base TASK).
Provide and Install Site, Sediment, and Erosion Control Measures in accordance with the Design-Build Contractor’s 100% Final Construction Documents (Drawings and Technical Specifications) (TASK 3).
Remove Site, Sediment, and Erosion Control Measures after Construction if considered Temporary Measures. Permanent Site, Sediment, and Erosion Control Measures shall remain In-Place.
5.6 TASK 6. Construct Approximately 500 Feet of Stream Channel.
(Base TASK).
Contractor shall Design (TASKS 1, 2, 3, and 5) and Construct (under TASK 6) approximately 500 feet of Stream Channel. The Contractor shall advance to Construction under TASK 4 and Remaining TASKs Only if the Contractor has previously received Architect-Engineer Company Approval and USFWS Approval for the Design Elements shown in the Construction Documents.
The Contractor shall construct the Stream Channel Section to create optimal hydraulic conditions based on known Moapa Dace habitat requirements. Contractor shall excavate New Stream Channel and use rocks, cobble, gravel and logs to create hydraulic conditions preferred by Moapa Dace. Contractor shall create Meanders in the Stream to increase hydraulic diversity within the stream and better negotiate the gradient. Additionally, the Contractor will Line the Stream Channel with a suitable liner to reduce water loss to soil absorption. When the channel is finished (i.e. All Substrate in Place, Liner Installed) Contractor shall introduce Flows into the Channel. When All Flows have been diverted into the New Channel, the previous Existing Channel shall be backfilled by the Contractor.
5.5 TASK A. Design, Fabricate and Construct / Install Reinforced Concrete Box Culvert with Wing Wall Assemblies.
(Option TASK).
Contractor shall Design, Fabricate, and Construct / Install a New Reinforced Concrete Box Culvert with Wing Wall Assemblies. The Reinforced Concrete Box Culvert is to be located and installed under West Warm Springs Road and includes All Associated Re-Construction of Road Soil Embankments, Filling, Backfilling, Re-Compaction, Re-Vegetation, Re-Seeding, Stabilization, Road Re-Paving, and Road Stripping. Design, Fabrication, and Construction / Installation to result in a 100% Contractor Turnkey Installation.
The Reinforced Concrete Box Culvert could consist of Pre-Cast Reinforced Concrete Units or Cast-In-Place Reinforced Concrete Units. Type of Reinforced Concrete Installation is at the Discretion of the Contractor.
Contractor shall coordinate with Nevada Department of Transportation (NDOT) and obtain All Necessary Signage and Permits. Culvert shall be designed to pass Maximum Anticipated Storm Flows plus an Additional to 3.3 Cubic Feet / Second (CFS) Base Flow. The Reinforced Concrete Box Culvert shall also be designed and Highway Traffic Load Rated to HS 20-44 (Semi-Truck with Tractor Trailer). If at any time during the Contract and prior to construction, the Design- Build Contractor or Design-Build Contractor’s Structural Engineer determines a heavier Highway Load Rating is required for the Box Culvert, the Design-Build Contractor shall notify the Contracting Officer and Contracting Officer’s Representative.
Lastly, the New Reinforced Concrete Box Culvert installed shall be designed to Incorporate Fish Passage Requirements for Anticipated Fish Species in the Pedersen Stream.
5.6 TASK B. Restore Construction Site and Re-Vegetate.
(Option TASK).
Revegetate the Construction Site. After Stream Channel Excavation is performed, the Contractor shall Grade the Stream Bank to prepare for planting. Seeds and cuttings for revegetation shall be locally sourced (Clark County) and grown out by a local nursery. All Plant Materials shall be grown according to USFWS Standards. The Above Ground Bio-Mass at time of planting should be 6-8 inches with a well-established root structure. Contractor shall plant Native Grass, Forbs, Shrubs, and Tree Seedlings. Refer to Appendix A for List of Approved Species. Tree Seedlings shall be protected by tubes to prevent small mammals from foraging on trees. Re-Vegetation shall include installation of temporary irrigation system, which will withstand a harsh desert environment for the duration of vegetation establishment.
Baseline Submittals to be submitted Prior To, During, and After Construction.
The Contractor shall develop, prepare, and submit the following Baseline Submittals for Pre- De-watering, Pre-Demolition, Pre-Construction, Dewatering, Demolition, and Construction to include but not be limited to the following:
• Prepare and Submit a Schedule of Values. Refer to General Specification Section 01 20
00 – Payment Procedures.
• Prepare and Submit a Master Submittal List. Refer to General Specification Section 01
33 00 Submittal Procedures for Master Submittal List Requirements.
• Prepare and Submit Subcontractor List and Key Personnel Names. Refer to General Specification Section 01 34 00 – Baseline Submittal List.
• Prepare and Submit Site Specific Safety Plan, Job Hazards Analysis (JHA), and Health and Safety Plan (HSP). Provide Detailed Project Data in the Site Specific Safety Plan, Job Hazards Analysis (JHA), and Health and Safety Plan (HSP). Refer to General Specification Section 01 34 00 – Baseline Submittal List.
• Prepare and Submit Testing Agency Qualifications, Permits, Licenses, and Certificates.
Refer to General Specification Section 01 34 00 – Baseline Submittal List.
• Prepare and Submit Contractor’s Dewatering Plan.
• Prepare and Submit Contractor’s Demolition and Construction Schedule, Demolition/Construction Schedule Updating Reports, Daily Construction Reports, Site Condition Reports, and Qualification Data.
• Prepare and Submit Quality Control Plan (QCP). Provide delineation of Laboratory and Insitu (Onsite) Tests and Inspections to be performed by the Contractor’s Independent Testing Agency under subcontract. Refer to Technical Specifications for Scope and Quantity of Tests and Inspections required for the Project.
• Prepare and Submit Site Utilization Plan and Project Identification and Temporary Signs. Refer to General Specification Section 01 51 00 – Temporary Facilities.
• Prepare and Submit Product Substitution Requests (if applicable). Refer to General Specification Section 01 63 00 – Product Substitution Procedures.
• Prepare and Submit Certificates, Landfill Receipts, Certified Surveys, and Final Property Survey (where required).
• Prepare and Submit Proposed Protection Measures and Schedule of Selective Demolition Activities.
• Prepare and Submit Demolition, Recycling, and Disposal Plan, Recycling and Processing Facility Records, Landfill and Incinerator Disposal Records. Refer to General Specification Section 01 74 00 – Cleaning and related Specification Sections.
• Prepare, Submit, and Maintain an On-site a Written Spill Prevention and Response Procedure.
• Prepare, Submit, and Maintain a Toxic and Hazardous Materials Storage, Application, and Disposal Procedures.
• Prepare and Submit Construction Plan. The Construction Plan shall describe how the Contractor plans to perform the Work of the Contract.
• Prepare and submit Product Literature, Product Data, Material Safety Data Sheets (MSDS), and Product / Material Certifications for proposed new materials and products to be provided and installed.
• Prepare and Submit Contractor’s List of Incomplete Items, Certified List of Incomplete Items, Certificates of Release, Certificate of Insurance for continuing coverage, and Schedule of Maintenance Material Items.
• Prepare and Submit Operation and Maintenance Manuals and Final Manual Submittal.
• Prepare and Submit Initial and Final Submittal Record Drawings, Record Specifications, Record Product Data. Refer to General Specification 01 78 00 – Closeout Submittals.
• Prepare and Submit System Operation and Maintenance Instruction Manual and Course Materials to review the Operation and Maintenance of the new system(s) and provide USFWS Refuge Employees with sufficient understanding of the system(s).
Submittals Number of Copies and Format
• Schedule of Values
• Master Submittal List (Submittal Registry)
• Subcontractor List and Key Personnel
Multiple Electronic Copies (.pdf file extensions)
Names
• Site Specific Safety Plan
• Job Hazard Analysis (JHA)
• Health and Safety Plan (HSP)
• Qualification Data
• Testing Agency Qualifications
• Permits
• Licenses
• Certificates
• Contractor’s Dewatering Plan
• Contractor’s Demolition and Construction
Schedule
• Demolition/Construction Schedule
Updating Reports
• Daily Construction Reports
• Site Condition Reports
• Quality Control Plan (QCP)
• Site Utilization Plan
• Project Identification and Temporary Sign
• Product Substitution Requests (if applicable)
• Certificates
• Landfill Receipts
• Certified Surveys (where required)
• Final Property Survey (where required)
• Proposed Protection Measures
• Schedule of Selective Demolition
Activities
• Demolition, Recycling, and Disposal Plan
• Recycling and Processing Facility Records
• Landfill and Incinerator Disposal Records
• Written Spill Prevention and Response
Procedure
• Written Toxic and Hazardous Materials
Storage, Application, and Disposal Procedures
• Construction Plan
• Product Literature
• Product Data
• Material Safety Data Sheets (MSDS)
• Product and Material Certifications
• Contractor’s List of Incomplete Items
• Certified List of Incomplete Items
• Certificates of Release
• Certificate of Insurance for continuing coverage
• Schedule of Maintenance Material Items
• Operation and Maintenance Manuals
• Final Operation and Maintenance Manuals
• Initial and Final Submittal Record
Drawings
• Record Specifications
• Record Product Data
• System Operation and Maintenance
Instruction Manual and Course Materials
Design and Construction Deliverable Notes
Contractor shall develop, prepare, and submit the following Design and Construction Deliverables.
Item No. Deliverable Notes
1 Stream Channel Design
The stream channel design will include topographic survey and base map, boundary survey related to construction easements on W. Warm Springs Road, design calculations, construction pages, and drawings.
2 Stream Channel Construction
Approximately 150 meters of stream channel. Contractor shall stake-out construction area, excavate channel, and place rocks, cobbles, and gravel to create ideal habitat structure for Moapa Dace.
3 Riparian Area Re-Vegetation
Contractor will re-vegetate riparian area with locally-sourced plant material from Clark County, Nevada. Approved plant species are listed in Appendix A.
Contractor Responsibilities.
• Obtain all necessary permits including dust control, Clean Water Act Section 404, Army
Corps of Engineers (ACE), and NDOT.
• During all phases of construction, contractor will work to minimize turbidity in existing stream and erosion in work area by using best management practices (BMPs).
• Rock, cobble, gravel, and sand used in construction of aquatic habitat within the stream channel will be sourced locally and contractor is responsible for transportation of all materials and equipment.
• Excavation spoils will be transported to a location on the Refuge to be determined by FWS.
• All Costs Associated with installation and construction including equipment rental and travel costs.
• All Design Drafts and Design Final Drafts shall be presented as 22” x 34” and 11” x 17”
Physical Hard Copies
• Submit PDF File Extensions for Review, Mark-Up, and Approval by USFWS.
6.0. GENERAL REQUIREMENTS.
Contractor shall provide supervision, labor, materials, equipment, tools, construction equipment, machinery, inspection, testing, start-up, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work.
6.1 Quality Assurance:
a. Contractor shall implement a Quality Assurance/Quality Control (QA/QC) Plan to verify products and services are free of errors or omissions. Use of Contractor’s internal QA/QC plan and procedures is OK; however, they shall be adapted to the specifics of this contract.
6.2 Submittal Reviews:
a. Contractor shall provide electronic submittals indicating Professional Engineer of Record and
Contractor Approval. Distribute the response via email to the USFWS.
6.3 Communications:
a. Contractor shall direct contracting related inquiries in writing or electronically to the CO during the pre-solicitation, solicitation, and contract period of performance. Contractor shall direct technical-related inquiries in writing or electronically to the COR.
6.4 Initial Field Visit
a. After issuance of Contract Award, the USFWS shall arrange for an Initial Conference Call
Project Kick-Off Meeting.
Topics to be covered during the Initial Conference Call Project Kick-Off Meeting:
- Contracting Requirements
- Scope and Objectives
- Ambiguities and Discrepancies
- Existing Facility Drawings
- Construction Work Window
6.5 Subcontractors:
a. Contractor shall utilize general contractors and specialty subcontractors who are duly-licensed and well-qualified to perform the work, consistent with the contract documents.
Contracting officer may remove from the work any employee they deem incompetent, careless or otherwise objectionable. Refer to FAR Clause 52.236-5 for additional information.
b. Within fourteen (14) days after award of the contract, Contractor shall submit to the CO completed Standard Form (SF) 1413s for each subcontractor. Refer to FAR Clause 52.222-
11 for additional information.
c. Contractor shall obtain written approval from the SBA and USFWS Contracting Officer prior to any subcontracting. Refer to Paragraph (b)(3) of FAR Clause 52.219-12 for additional
6.6 Progress Schedules:
a. Prior to the pre-construction meeting, Contractor shall submit to the Refuge and COR for review and approval, a preliminary project schedule, in .pdf format. At a minimum, schedule shall consider the periods of performance of each task stated within the bid schedule.
b. Contractor shall update the schedule every two weeks. Progress schedules shall be submitted to the Refuge, CO, and COR. If at any time the contractor’s schedule shows any slippage in critical tasks or completion past the construction completion date, contractor shall narrate the reasoning for slippage and/or late completion.
6.7 Pre-construction Meeting:
a. After contract award and prior to commencement of work, the Refuge and COR will arrange for a pre-construction meeting at the Moapa Valley NWR Office. Contractor, along with their major subcontractors, shall attend the face-to-face meeting. Meeting is expected to take place within fourteen (14) days after issuance of the contract award and take no longer than two (2) hours.
c. Meeting will address the contract requirements and identify and resolve any ambiguities or discrepancies. In accordance with FAR 36.212 and FAR Clause 52.236-26, the conference shall discuss statutory matters such as labor standards (refer to FAR Subpart 22.4). Other topics include matters of significant interest, including who has authority to decide matters such as contractual, administrative (e.g. security, safety, and fire and environmental protection) and construction responsibilities.
6.8 Temporary Facilities and Utilities:
a. Contractor shall furnish all temporary utilities needed, except as noted otherwise. Facilities and utilities include but are not limited to: Heating, lighting, non-potable water, telephone, material handling equipment, temporary construction aids and storage enclosures. Refer to
FAR Clause 52.236-10 for additional information.
b. No electrical power is available to the Contractor.
6.9 Diligence: Contractor shall perform all construction activities efficiently and with the requisite expertise, skill and competence to satisfy the requirements of the contract documents. Contractor shall at all times exercise complete and exclusive control over the means, methods, sequences and techniques of construction. Refer to FAR Clause 52.236-5 for additional information.
6.10 Supervision: Contractor shall provide a Project Manager or Project Superintendent on-site at all times while work is underway. Manager or Superintendent shall have a good working knowledge of the project work. Refer to FAR Clause 52.236-6 for additional information.
6.11 USFWS Operations: USFWS operations have precedence over construction activities.
Contractor shall schedule and coordinate all construction and demolition activities so as not to unduly impact ongoing facility operations. Refer to FAR Clause 52.236-8 for additional
6.12 Security: Contractor shall effectively secure the worksite, staging areas and materials storage areas. The Government shall be held harmless from any liability resulting from the contractor’s negligence to provide effective security.
6.13 Construction Safety:
a. Contractor shall be ultimately responsible for health and safety on the worksite at all times.
Refer to FAR Clause 52.236-13 for additional information.
b. Contractor shall ensure that all onsite activities, equipment and facilities constructed by the contractor, subcontractor or supplier conform fully to the safety standards in Section 8.2 of the SOW.
c. Contractor shall provide barricades and warning devices as necessary to safeguard the public, workers and Government personnel. Where project work affects public roads, Contractor shall provide signage in accordance with the current edition of the Manual on Uniform Traffic Control Devices (MUTCD), as published by the U.S. Department of Transportation (USDOT) Federal Highway Administration (FHWA).
http://mutcd.fhwa.dot.gov/ http://mutcd.fhwa.dot.gov/
d. Contractor shall initiate and maintain, throughout the performance of this contract, an effective health and safety program that provides adequate policies, procedures, and practices to protect workers from (and allow them to recognize) job-related health and safety hazards.
e. The program shall include provisions for the identification, evaluation, prevention and control of general work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods and conditions, as well as providing a competent person to conduct frequent and regular inspections.
f. Each employee (Contractor or subcontractor) must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the work environment.
g. The contractor shall adopt the USACE Safety and Occupational Health (SOH) Program as a starting point for Safety Program requirements. In the event a more stringent Safety Program exists, the more stringent Safety Program shall be applied to the Contract / Project by the Contractor.
6.14 Site Cleanup: Contractor shall remove construction debris from the worksite daily, including debris within temporary facilities and storage areas. Before completing the work, Contractor shall remove from the worksite any rubbish, tools, scaffolding, equipment and materials that are not the property of the Government. Upon completion of work, Contractor shall leave the work area in a clean, neat and orderly condition. Refer to FAR Clause 52.236-12 for additional information.
6.15 Material, Equipment, Transportation, Handling and Storage:
a. Government-owned equipment will not be made available to the Contractor for use within this contract. Government buildings and other facilities are not available for storage of the Contractor’s materials, equipment and tools.
b. Contractor shall have a representative onsite to receive material deliveries. Contractor shall be responsible for all material deliveries, whether or not their representative is on-site at the time of delivery or not.
c. Contractor shall transport, handle and store materials and equipment in a secure manner and in accordance with the manufacturer’s written instructions.
d. Contractor shall promptly remove from the worksite any material(s) and equipment which are damaged or are otherwise unsuitable. Refer to FAR Clause 52.236-5 for additional
6.16 Construction Waste:
a. Minimize creation of construction, deconstruction, and demolition waste.
b. Minimize factors that contribute to waste such as over-packaging, improper storage, ordering error, poor planning, breakage, mishandling, and contamination.
c. Develop a Waste Management Plan to ensure any existing or new materials/equipment/substances are properly characterized, reused, salvaged, recycled, and/or disposed of properly.
d. Any regulated quantities of hazardous materials shall be disposed of at disposal facilities specifically licensed to accept hazardous waste.
e. Dispose of any materials (not salvaged, reused, or recycled) in a legal manner off-site, in licensed disposal facilities.
f. Contractor shall actively protect the natural environment and human health by using environmentally preferable products in their activities.
g. The Contractor wherever possible shall divert solid waste from disposal in landfills through recycling and reuse of materials to lower greenhouse gas emissions.
7.0. GOVERNMENT FURNISHED ITEMS.
No Government Furnished Material or Government Furnished Equipment will be provided.
7.1. General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract.
7.2. Materials: The Contractor shall furnish all materials, supplies, and equipment necessary to meet the requirements of this contract.
7.3. Equipment: The Contractor shall furnish all required equipment to meet the requirements to perform work under this contract.
Government Furnished Information:
7.4 Construction Drawings NOT provided as part of this solicitation.
7.5 Construction General Specifications provided as part of the Solicitation to be used in close coordination with Construction Drawings and Technical Specifications.
7.6 Access to Facilities to be based on Pre-Determined Schedule.
7.7 USFWS Facility Managers and / or Maintenance, as required and as by Pre-Arrangement.
7.8 Obtain Pre-Approval from USFWS for Selected Staging Areas to conduct Project Work and
Temporary Storage of Materials.
7.9 There is no public internet and no wireless access at Moapa Valley NWR sites. Cell phone service may be limited.
7.10 Certain roads within Site are High Clearance Dirt Roads.
7.11 Contractors will be instructed by the government on entry points to the Work Site and
Equipment Staging Areas.
8.0. CODES AND STANDARDS.
8.1 Technical Standards: All work shall be done in accordance with all applicable International
Code Council (ICC) Codes (e.g. International Building Code (IBC), International Plumbing Code (IPC)), NFPA 70 (National Electrical Code®) and NFPA 101 (Life Safety Code®), as well as other applicable State or local regulations. In the event of a conflict, the most stringent laws, codes, and regulations shall apply.
8.2 Safety Standards: Contractor shall adhere to Occupational Safety and Health Administration
(OSHA) 29 CFR 1910 and 1926, as well as other applicable DOI, USFWS, State and local regulations. In the event of a conflict, the most stringent laws, codes, regulations, standards, and provisions shall apply. Refer to FAR Clause 52.236-13 for additional
9.0. INSPECTION AND ACCEPTANCE.
9.1 Inspection and acceptance will be determined by the USFWS. Refer to FAR Clause 52.246-
12 for additional information.
9.2 The Work is subject to observation and inspection by the USFWS and other authorities with jurisdiction.
9.3 Acceptance of the work is contingent on compliance with the requirements set forth in the specifications, drawings, and other documents awarded with (or referenced by) the contract for this project.
10.0. FINAL WALK THROUGH.
10.1 Submit a preliminary list of unfinished work and notify the USFWS at least ten (10) calendar days prior to the anticipated date of completion of unfinished work.
10.2 The USFWS will perform the final walk through as promptly as practicable.
10.3 The time required for such walk through and for making any corrections as a result thereof shall be included in the contract performance time.
10.4 The Contractor’s representative responsible for the work shall be present at the final walk through.
11.0 CLOSEOUT DOCUMENTS.
11.1 Submit any requested regulatory-agency clearance documents indicating the work complies with their requirements such as finalized plumbing/gas/electrical inspections.
11.2 After completion of the work and prior to final payment, submit a Release of Claims
(Form DI-137 provided by the Contracting Officer), properly executed by the Contractor, releasing claims against the United States arising out of this contract, other than claims specifically excepted from the operation of the release.
12.0. INVOICE AND PAYMENT.
12.1 General: Contractor shall not invoice between September 20th and October 20th, due to the seasonal financial system closure.
12.2 Progress Payments: Monthly progress payments shall be invoiced and submitted in accordance with Clause 52.232-70. Invoices shall reflect the actual work performed at the time of submission. Prior to submitting invoices, they shall be sent to the COR for review and approval / disapproval.
12.3 Final Payment: Final payment shall be invoiced and submitted in accordance with Clause
52.232-70. Prior to submitting the final invoice, Contractor shall have submitted all closeout submittals. In addition, Contractor shall have been provided an approval by the USFWS stating all deficiencies have been corrected.
13.0. GOVERNMENT AVAILABILITY.
13.1 Government is available Monday thru Friday from 7:30 AM to 4:00 PM (Pacific Daylight
Time), excluding Federal Holidays. Availability outside those dates / hours shall be coordinated with the Refuge at least two business days in advance.
13.2 Work shall be performed during work hours agreed to by the Refuge and Contractor.
14.0. WORK HOURS.
14.1 Work shall be performed between Monday thru Friday, 7:30 AM to 4:00 PM (Pacific
Time), excluding Federal Holidays. Work outside those dates / hours shall be coordinated with the Refuge Manager at least two business days in advance.
14.2 Weekend work shall be approved by the Refuge Manager.
14.3 USFWS escort required unless previously arranged with the Service.
Points of Contact
Administrative:
Cindy Salazar Contracting Officer 911 NE 11th Avenue Portland, OR 97232 Email: cindy_salazar@fws.gov 503-872-2832
Refuge Technical Coordinators:
Primary Contact:
David Stone, Wildlife Refuge Specialist, Moapa Valley NWR HWY 93 Mile Post 32, Alamo, NV 89001 Cell: 702-379-1220 Office: 775-725-3417 ext. 103 david_stone@fws.gov
Secondary Contact:
Rob Vinson, Refuge Manager, Pahranagat NWR HWY 93 Mile Post 32, Alamo, NV 89001 775-725-3417 ext. 102 james_vinson@fws.gov mailto:cindy_salazar@fws.gov mailto:david_stone@fws.gov mailto:james_vinson@fws.gov
Appendix A: Approved Plant Species for Revegetation
Overstory Trees
Velvet ash Fraxinus velutina Goodings willow Salix gooddingii Coyote willow Salix exigua Fremont cottonwood Populus fremontii Honey mesquite Prosopis glandulosa
Shrubs
Emory’s seepwillow Baccharis emoryi Wolfberry Lycium torreyi Arrowweed Pluchea sericea Quailbush Atriplex lentiformis
Understory
Yerba mansa Anemopsis californica Bushy bluestem Andropogon glomeratus Alkali sacaton Sporobolus airoides Saltgrass Distichlis stricta Arizona grape Vitis arizonica Warm springs fimbry Fimbristylis thermalis
| 1.0. GENERAL INFORMATION. |
| Design and Construction Deliverable Notes |
| a. Contractor shall utilize general contractors and specialty subcontractors who are duly-licensed and well-qualified to perform the work, consistent with the contract documents. Contracting officer may remove from the work any employee they deem inc... |
| b. Within fourteen (14) days after award of the contract, Contractor shall submit to the CO completed Standard Form (SF) 1413s for each subcontractor. Refer to FAR Clause 52.222-11 for additional information. |
| c. Contractor shall obtain written approval from the SBA and USFWS Contracting Officer prior to any subcontracting. Refer to Paragraph (b)(3) of FAR Clause 52.219-12 for additional information. |
| 6.6 Progress Schedules: |
| a. Prior to the pre-construction meeting, Contractor shall submit to the Refuge and COR for review and approval, a preliminary project schedule, in .pdf format. At a minimum, schedule shall consider the periods of performance of each task stated with... |
| b. Contractor shall update the schedule every two weeks. Progress schedules shall be submitted to the Refuge, CO, and COR. If at any time the contractor’s schedule shows any slippage in critical tasks or completion past the construction completion d... |
| 6.7 Pre-construction Meeting: |
| a. After contract award and prior to commencement of work, the Refuge and COR will arrange for a pre-construction meeting at the Moapa Valley NWR Office. Contractor, along with their major subcontractors, shall attend the face-to-face meeting. Meeti... |
| c. Meeting will address the contract requirements and identify and resolve any ambiguities or discrepancies. In accordance with FAR 36.212 and FAR Clause 52.236-26, the conference shall discuss statutory matters such as labor standards (refer to FAR ... |
| 6.8 Temporary Facilities and Utilities: |
| a. Contractor shall furnish all temporary utilities needed, except as noted otherwise. Facilities and utilities include but are not limited to: Heating, lighting, non-potable water, telephone, material handling equipment, temporary construction aids... |
| b. No electrical power is available to the Contractor. |
| 6.9 Diligence: Contractor shall perform all construction activities efficiently and with the requisite expertise, skill and competence to satisfy the requirements of the contract documents. Contractor shall at all times exercise complete and exclusi... |
| 6.10 Supervision: Contractor shall provide a Project Manager or Project Superintendent on-site at all times while work is underway. Manager or Superintendent shall have a good working knowledge of the project work. Refer to FAR Clause 52.236-6 for ... |
| 6.11 USFWS Operations: USFWS operations have precedence over construction activities. Contractor shall schedule and coordinate all construction and demolition activities so as not to unduly impact ongoing facility operations. Refer to FAR Clause 52... |
| 6.12 Security: Contractor shall effectively secure the worksite, staging areas and materials storage areas. The Government shall be held harmless from any liability resulting from the contractor’s negligence to provide effective security. |
| 6.13 Construction Safety: |
| a. Contractor shall be ultimately responsible for health and safety on the worksite at all times. Refer to FAR Clause 52.236-13 for additional information. |
| b. Contractor shall ensure that all onsite activities, equipment and facilities constructed by the contractor, subcontractor or supplier conform fully to the safety standards in Section 8.2 of the SOW. |
| c. Contractor shall provide barricades and warning devices as necessary to safeguard the public, workers and Government personnel. Where project work affects public roads, Contractor shall provide signage in accordance with the current edition of the... |
| d. Contractor shall initiate and maintain, throughout the performance of this contract, an effective health and safety program that provides adequate policies, procedures, and practices to protect workers from (and allow them to recognize) job-related... |
| e. The program shall include provisions for the identification, evaluation, prevention and control of general work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods and conditions, as well a... |
| f. Each employee (Contractor or subcontractor) must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the work environment. |
| g. The contractor shall adopt the USACE Safety and Occupational Health (SOH) Program as a starting point for Safety Program requirements. In the event a more stringent Safety Program exists, the more stringent Safety Program shall be applied to the C... |
| 6.14 Site Cleanup: Contractor shall remove construction debris from the worksite daily, including debris within temporary facilities and storage areas. Before completing the work, Contractor shall remove from the worksite any rubbish, tools, scaffol... |
| 6.15 Material, Equipment, Transportation, Handling and Storage: |
| a. Government-owned equipment will not be made available to the Contractor for use within this contract. Government buildings and other facilities are not available for storage of the Contractor’s materials, equipment and tools. |
| b. Contractor shall have a representative onsite to receive material deliveries. Contractor shall be responsible for all material deliveries, whether or not their representative is on-site at the time of delivery or not. |
| c. Contractor shall transport, handle and store materials and equipment in a secure manner and in accordance with the manufacturer’s written instructions. |
| 13.0. GOVERNMENT AVAILABILITY. |
| 14.0. WORK HOURS. |