About this file
This document contains Technical Specifications for a public works contract (Contract No. C220) issued by the Bergen County Utilities Authority for Cleaver-Brooks Boiler Upgrades. The project involves replacing control and entrance panels on two existing Cleaver-Brooks CB-200X-500 boilers located at the Bergen County Utilities Authority facility in Little Ferry, New Jersey. The solicitation (BCUA-25-C220) is scheduled for bid opening on October 16, 2025, with a strongly recommended pre-bid conference on September 30, 2025. The scope of work requires the contractor to supply labor and materials for a complete and operational installation, with specific upgrades including a new control cabinet, burner management system, air compressor controls, blower motor controls, fuel selection system, and temperature controls.
The project requires contractors to have experience with industrial boiler control upgrades, with technicians factory-trained on Cleaver-Brooks equipment. Contractors must possess New Jersey licensing, be registered under the Public Works Contractor Registration Act, and be classified to perform public works projects. The contract includes provisions for prevailing wage requirements, certified payroll documentation, and apprenticeship program compliance. Deliverables include full installation, functional testing, commissioning, updated wiring diagrams, operation manuals, facility personnel training, and a one-year parts and labor warranty. The contract will be awarded to the lowest responsible and responsive bidder meeting all specification requirements, with the Bergen County Utilities Authority reserving the right to reject any or all bids.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specifications Contract No. C220 Page 1 of 4
TECHNICAL SPECIFICATIONS
Bergen County Utilities Authority
PROJECT INFORMATION
• Solicitation Number: BCUA-25-C220
• Project Title: Cleaver-Brooks Boiler Upgrades
• Bid Opening Date: October 16, 2025 at 10:00 AM (Prevailing Time)
• Pre-Bid Conference: September 30, 2025 at 10:00 AM (STRONGLY
RECOMMENDED)
• Location: Bergen County Utilities Authority, Foot of Mehrhof Road, Little Ferry, NJ
07643
• Submission Method: Electronic submission via www.BergenBids.com
SCOPE OF WORK
The Contractor shall supply labor and material to replace the control and entrance panels on both existing Cleaver-Brooks boilers at the Bergen County Utilities Authority facility. The scope includes all work necessary for complete and operational installation.
EQUIPMENT SPECIFICATIONS
Existing Equipment to be Upgraded:
• Quantity: Two (2) Cleaver-Brooks Boilers
• Model: CB-200X-500
• Serial Numbers:
o Boiler No. 1: L-63990 o Boiler No. 2: L-63989
• Horsepower: 500 HP each
• Max Pressure: 250 PSI
• Design Pressure: 150 PSI (operating)
• Fuel Type: Fuel Oil or Methane Gas (dual fuel capability)
• Input Capacity: 20,922,000 BTU/hr
• Steam Capacity: Approximately 17,250 lbs/hr
• Blower Motor: 5 HP
• Air Compressor Motor: 5 KW
• Oil Pump Motor: 1 HP
• Year Manufactured: December 1978 (12/78) http://www.bergenbids.com/
Technical Specifications Contract No. C220 Page 2 of 4
Electrical Requirements:
• Main Power Supply: 460V / 3Ø / 60Hz
• Minimum Circuit Ampacity: 34 Amps
• Max Circuit Protection: 50 Amps
• Control Circuit: 1Ø / 60Hz / 7 Amps
• Oil Heat Circuit: 7 Amps
REQUIRED UPGRADES AND MATERIALS
The Contractor shall provide and install the following items for EACH boiler (2 units total):
1. Control Cabinet o NEMA 1 rated enclosure o Properly sized for all control components o Wall-mounted configuration
2. Burner Management System o RM-7800L programmer with integrated UV scanner o Compatible with existing Cleaver-Brooks systems o Include all necessary programming and commissioning
3. Air Compressor Controls o New contractor rated for motor load o Properly rated fuses for circuit protection
4. Blower Motor Controls o Motor starter sized for 5 HP motor o Appropriate fuses for overcurrent protection
5. Fuel Selection System o Manual fuel selector switch o Capable of selecting between fuel oil and methane gas o Integrated with burner management system
6. Temperature Controls o Limiting potentiometer o Compatible with existing control scheme
7. Wiring and Documentation o Complete rewiring per updated manufacturer's wiring diagrams o Provide updated as-built wiring prints o All wiring to meet current NEC standards
TECHNICAL REQUIREMENTS
1. All equipment shall be new and of current manufacture
2. Components must be compatible with existing Cleaver-Brooks CB-200X-500 boilers
3. Installation shall maintain boiler's dual-fuel capability
4. System shall meet or exceed original equipment specifications
5. All work shall comply with applicable codes and standards
Technical Specifications Contract No. C220 Page 3 of 4
CONTRACTOR QUALIFICATIONS
1. Must have experience with industrial boiler control upgrades
2. Technicians must be factory-trained on Cleaver-Brooks equipment
3. Provide references for similar projects completed within last 5 years
4. Must possess all required licenses for work in New Jersey
5. Must be registered pursuant to the provisions of "The Public Works Contractor
Registration Act," P.L.1999, c.238 (N.J.S.A. 34:11-56.48 et seq.)
6. Must be classified by the New Jersey Division of Property Management and Construction to perform public works projects
DELIVERABLES
1. Complete installation of control panels on both boilers
2. Functional testing and commissioning of all systems
3. Updated manufacturer's wiring diagrams (as-built)
4. Operation and maintenance manuals
5. Training for facility personnel (minimum 4 hours)
6. One-year warranty on parts and labor
PROJECT REQUIREMENTS
1. Work Schedule: Coordinate with facility to minimize operational disruption
2. Safety: Comply with all OSHA and facility safety requirements
3. Insurance: Maintain appropriate liability and workers' compensation coverage
4. Performance Bond: 100% performance and payment bond required
5. Prevailing Wage: This is a public works project subject to prevailing wage rates as determined by the Commissioner of Labor and Workforce Development pursuant to the "New Jersey Prevailing Wage Act," P.L.1963, c.150 (N.J.S.A. 34:11-56.25 et seq.)
PREVAILING WAGE REQUIREMENTS
NOTICE TO CONTRACTORS: This project is subject to the New Jersey Prevailing Wage Act. All contractors and subcontractors performing work on this project must pay prevailing wages as determined by the New Jersey Department of Labor and Workforce Development.
Prevailing wage rates are available at www.nj.gov/labor/wageandhour/prevailing-wage-rate/.
CERTIFIED PAYROLL REQUIREMENTS: Contractors and all subcontractors must provide certified payroll records for each employee performing work on this project using DOLWD Form MW-562. Certified payroll records must be submitted within ten (10) days of each pay period to the contracting unit.
APPRENTICESHIP PROGRAM COMPLIANCE: All contractors directly employing craftworkers must complete apprenticeship certification pursuant to N.J.S.A. 34:11-56.52, as amended by P.L. 2023, c.138, documenting participation in registered apprenticeship programs for each craft employed.
Technical Specifications Contract No. C220 Page 4 of 4
LOW BIDDER CERTIFICATION: If the lowest responsible bid is 10 percent or lower than the next lowest responsive bid, the bidder must provide additional certification of prevailing wage compliance prior to contract award pursuant to N.J.S.A. 34:11-56.27.
SPECIAL NOTES
1. Customer responsible for removal of external wiring not being used
2. Contractor must verify all existing conditions prior to bidding
3. All equipment must be delivered to site FOB destination, freight prepaid
4. NJ Sales tax exempt - certificate will be provided upon contract execution
QUESTIONS AND CLARIFICATIONS
All questions regarding this specification must be submitted in writing through the Euna E- Procurement Platform no later than the date specified on the aforementioned platform. Questions submitted after this deadline will not be answered.
CONTRACT AWARD
Contract will be awarded by resolution of the Bergen County Utilities Authority governing body to the lowest responsible and responsive bidder meeting all specification requirements and mandatory contract documents.
Bergen County Utilities Authority reserves the right to reject any or all bids, waive technical defects, and award contract in the best interest of the Authority.
| TECHNICAL SPECIFICATIONS |
| Bergen County Utilities Authority |
| PROJECT INFORMATION |
| SCOPE OF WORK |
| EQUIPMENT SPECIFICATIONS |
| Existing Equipment to be Upgraded: |
| Electrical Requirements: |
| REQUIRED UPGRADES AND MATERIALS |
| TECHNICAL REQUIREMENTS |
| CONTRACTOR QUALIFICATIONS |
| DELIVERABLES |
| PROJECT REQUIREMENTS |
| PREVAILING WAGE REQUIREMENTS |
| SPECIAL NOTES |
| QUESTIONS AND CLARIFICATIONS |
| CONTRACT AWARD |
File details come from the government source that posted it. Updated .