This document is a comprehensive Standard General Conditions of Construction Contract issued by the Bergen County Utilities Authority (BCUA) for public works projects. The contract document, dated September 26, 2025, provides a detailed framework for construction contracts, covering 21 articles that outline the rights, responsibilities, and procedures for contractors, owners, and engineers. The document establishes standard protocols for project execution, including definitions, contract document management, site conditions, bonds and insurance requirements, contractor responsibilities, payment procedures, work completion, dispute resolution, and various administrative and regulatory compliance matters specific to New Jersey public contracting regulations.

The contract includes critical provisions such as prevailing wage requirements, performance and payment bonds, insurance specifications, and detailed guidelines for project modifications, claims processing, and potential value engineering proposals. Financial terms include retainage of up to 2% for contracts exceeding $100,000, with provisions for progressive payments and final settlement. The document emphasizes compliance with New Jersey state laws, including the Local Public Contracts Law, Prevailing Wage Act, and specific regulations related to public works contracts. Additional requirements cover anti-discrimination policies, investment disclosure, American-made product preferences, and specific health and safety plan details. The contract is designed to provide a comprehensive, legally robust framework for construction projects undertaken by the Bergen County Utilities Authority.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e BCUA General Conditions Friday, September 26, 2025

SECTION 00 80 10

STANDARD GENERAL CONDITONS OF CONSTRUCTION

CONTRACTS ISSUED BY THE BERGEN COUNTY UTILITIES

AUTHORITY

The enclosed “Standard Conditions of the Construction Contract” as prepared by the Bergen County Utilities Authority, Division of Purchasing for all Public Works projects undertaken by the Authority. The “General Conditions” are incorporated into the contract and specifications by reference.

Table of Contents Article 1 – Definitions and Terminology Article 2 – Preliminary Matters Article 3 – Contract Documents: Intent, Amending, Reuse Article 4 – Availability of Lands: Subsurface and Physical Conditions; Hazardous Environmental Conditions” Reference Points Article 5 – Bonds and Insurance Article 6 – Contractors Responsibilities Article 7 – Other Work at Site Article 8 – Owners Responsibilities Article 9 – Engineers Status During Construction Article 10 – Changes in Work; Claims Article 11 – Cost of the Work; Allowances; Unit Price Work Article 12 – Changes in Contract Price; Changes in Contract Time Article 13 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work Article 14 – Payments to Contractor and Completion Article 15 – Suspension of Work and Termination Article 16 – Dispute Resolution Article 17 – Miscellaneous Article 18 - Value Engineering for Projects Valued Over $5,000,000 Article 19 - General Conditions Included in the Specific Sections Related to N.J.A.C. 7:14 Article 20 – Additional NJ Public Contracting Requirements Article 21 – Minimum Health and Safety Plan Detail

2 | P a g e BCUA General Conditions Friday, September 26, 2025

ARTICLE 1 – DEFINITIONS AND TERMINOLOGY

1.01 Defined Terms

A. Wherever used in the Bidding Requirements or Contract Documents and printed with initial capital letters, the terms listed below will have the meanings indicated which are applicable to both the singular and plural thereof. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms.

1. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Contract Documents.

2. Agreement—The written instrument which is evidence of the agreement between Owner and Contractor covering the Work.

3. Application for Payment—The form acceptable to Engineer which is to be used by Contractor during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents.

4. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration.

5. Bid—The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed.

6. Bidder—The individual or entity who submits a Bid directly to Owner.

7. Bidding Documents—The Bidding Requirements and the proposed Contract Documents (including all Addenda).

8. Bidding Requirements—The advertisement or invitation to bid, Instructions to Bidders, Bid security of acceptable form, if any, and the Bid Form with any supplements.

9. Change Order—A document recommended by Engineer which is signed by Contractor and Owner and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Times, issued on or after the Effective Date of the Agreement.

10. Claim—A demand or assertion by Owner or Contractor seeking an adjustment of Contract

Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.

11. Contract—The entire and integrated written agreement between the Owner and Contractor concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral.

3 | P a g e BCUA General Conditions Friday, September 26, 2025

12. Contract Documents—Those items so designated in the Agreement including all documents, drawings, forms, questionnaires and other issued documents listed on the e-procurement platform. Approved Shop Drawings, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents.

13. Contract Price—The moneys payable by Owner to Contractor for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of Paragraph 11.03 in the case of Unit Price Work).

14. Contract Times—The number of days or the dates stated in the Agreement to: (i) achieve

Milestones, if any; (ii) achieve Substantial Completion; and (iii) complete the Work so that it is ready for final payment as evidenced by Engineer’s written recommendation of final payment.

15. Contractor—The individual or entity with whom Owner has entered into the Agreement.

16. Cost of the Work—See Paragraph 11.01 for definition.

17. Drawings—That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Shop Drawings and other Contractor submittals are not Drawings as so defined.

18. Effective Date of the Agreement—The date indicated in the Agreement on which it becomes effective, but if no such date is indicated, it means the date on which the Agreement is signed and delivered by owner.

19. Engineer—The individual or entity named as such in the Agreement.

20. Field Order—A written order issued by Engineer which requires minor changes in the Work but which does not involve a change in the Contract Price or the Contract Times.

21. General Requirements—Sections of Division 1 of the Specifications.

22. Hazardous Environmental Condition—The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous Waste, or Radioactive Material in such quantities or circumstances that may present a substantial danger to persons or property exposed thereto.

23. Hazardous Waste—The term Hazardous Waste shall have the meaning provided in Section

1004 of the Solid Waste Disposal Act (42 USC Section 6903) as amended from time to time.

24. Laws and Regulations; Laws or Regulations—Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction.

25. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or personal property.

4 | P a g e BCUA General Conditions Friday, September 26, 2025

26. Milestone—A principal event specified in the Contract Documents relating to an intermediate completion date or time prior to Substantial Completion of all the Work.

27. Notice of Award—The written notice by Owner to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the condition’s precedent listed therein, Owner will sign and deliver the Agreement.

28. Notice to Proceed—A written notice given by Owner to Contractor fixing the date on which the Contract Times will commence to run and on which Contractor shall start to perform the Work under the Contract Documents.

29. Owner—The individual or entity with whom Contractor has entered into the Agreement and for whom the Work is to be performed.

30. PCBs—Polychlorinated biphenyls.

31. Petroleum—Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Waste and crude oils.

32. Progress Schedule—A schedule, prepared and maintained by Contractor, describing the sequence and duration of the activities comprising the Contractor’s plan to accomplish the Work within the Contract Times.

33. Project—The total construction of which the Work to be performed under the Contract

Documents may be the whole, or a part.

34. Project Manual—The bound documentary information prepared for bidding and constructing the Work. A listing of the contents of the Project Manual, which may be bound in one or more volumes, is contained in the table(s) of contents.

35. Radioactive Material—Source, special nuclear, or byproduct material as defined by the

Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time.

36. Resident Project Representative—The authorized representative of Engineer who may be assigned to the Site or any part thereof.

37. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged.

38. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities.

39. Schedule of Values—A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing

5 | P a g e BCUA General Conditions Friday, September 26, 2025

Contractor’s Applications for Payment.

40. Shop Drawings—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work.

41. Site—Lands or areas indicated in the Contract Documents as being furnished by Owner upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by Owner which are designated for the use of Contractor.

42. Specifications—That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto.

43. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site.

44. Substantial Completion—The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of Engineer, the Work (or a specified part thereof) is sufficiently complete, in accordance with the Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intended.

The terms “substantially complete” and “substantially completed” as applied to all or part of the Work refer to Substantial Completion thereof.

45. Successful Bidder—The Bidder submitting the lowest responsive and responsible Bid to whom Owner makes an award.

46. Supplementary Conditions—That part of the Contract Documents which amends or supplements these General Conditions.

47. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor.

48. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.

49. Unit Price Work—Work to be paid for on the basis of unit prices.

50. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents.

6 | P a g e BCUA General Conditions Friday, September 26, 2025

51. Work Change Directive—A written statement to Contractor issued on or after the Effective

52. Date of the Agreement and signed by Owner and recommended by Engineer ordering an addition, deletion, or revision in the Work, or responding to differing or unforeseen subsurface or physical conditions under which the Work is to be performed or to emergencies. A Work Change Directive will not change the Contract Price or the Contract Times but is evidence that the parties expect that the change ordered or documented by a Work Change Directive will be incorporated in a subsequently issued Change Order following negotiations by the parties as to its effect, if any, on the Contract Price or Contract Times.

53. Contract Documents - Those items so designated in the Agreement including all documents, drawings, forms, questionnaires and other issued documents listed on the e-procurement platform. Approved Shop Drawings, other CONTRACTOR submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents.

54. Department - As defined by N.J.S.A. 7:22-3.4 to the definitions—i.e. Department – The New Jersey Department of Environmental Protection and its successors and assigns.

55. Inspector - The representative of the Engineer designated to observe the Work for which these specifications are intended.

56. Manufacturer Shall be the manufacturer of the equipment specified.

57. Modification Request – Is a request submitted by CONTRACTOR seeking the consent of

OWNER to a change in equipment, materials or methods of Work provided for within the Contract Documents that does not compromise the useful life, operation costs, safety, code compliance, project schedule or design integrity and is in accordance with N.J.A.C. 5:30-

11.7 to -11.8. Authorization of these changes would result in a change order. Change Orders for these types of changes are subject to the rules governing construction contracts, which are set forth in NJAC 5:30-11.8, and are limited to the following types:

a. Unforeseeable problems, which are defined as conditions or circumstances that could not be foreseen at the time the specifications were written and the contract awarded; provided that a substantial amount of the construction would be delayed, which would result in substantial increases in costs above the original contract amount or substantial inconvenience to the public if bidding were to be required; and

b. Minor modifications to effect economies, improve service or resolve minor problems with affected property owners.

58. OWNER - Shall be the Bergen County Utilities Authority and the term OWNER means the

OWNER and/or the OWNER’s authorized representatives. While not deemed to be OWNER for purposes of this Contract, and any and all authorities, agencies, boards, bureaus, commissions, divisions, districts, departments and offices of the State of New Jersey, including but not limited to the Department, as may be identified by the Bergen County Utilities Authority during the term of this Contract shall have the right to enforce the relevant terms of this Contract by reason of a contractual relationship with the OWNER.

59. Soil Erosion Standards The "Standards for Soil Erosion and Sediment Control in New Jersey" adopted September 9, 1974 by the New Jersey State Soil Conservation Committee, as amended and supplemented to date.

60. Successful Bidder — The Bidder submitting the lowest responsive and responsible Bid to whom Owner makes an award

7 | P a g e BCUA General Conditions Friday, September 26, 2025

61. Surety The corporate body which is bound with and for the CONTRACTOR and which engages to be responsible for the faithful performance of the Contract, and to indemnify the Owner against all claims for damages.

62. Testing Laboratory - A laboratory selected by the Owner for the inspection and testing of materials.

63. Limited Notice to Proceed (LNP), shall mean a document authorizing the contractor to initiate and complete certain project task milestones which must be met to receive a final Notice to Proceed.

1.02 Terminology

A. The words and terms discussed in Paragraph 1.02.B through F are not defined but, when used in the Bidding Requirements or Contract Documents, have the indicated meaning.

B. Intent of Certain Terms or Adjectives:

1. The Contract Documents include the terms “as allowed,” “as approved,” “as ordered,” “as directed” or terms of like effect or import to authorize an exercise of professional judgment by Engineer. In addition, the adjectives “reasonable,” “suitable,” “acceptable,” “proper,” “satisfactory,” or adjectives of like effect or import are used to describe an action or determination of Engineer as to the Work. It is intended that such exercise of professional judgment, action, or determination will be solely to evaluate, in general, the Work for compliance with the information in the Contract Documents and with the design concept of the Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective is not intended to and shall not be effective to assign to Engineer any duty or authority to supervise or direct the performance of the Work, or any duty or authority to undertake responsibility contrary to the provisions of Paragraph 9.09 or any other provision of the Contract Documents.

C. Day:

1. The word “day” means a calendar day of 24 hours measured from midnight to the next midnight.

D. Defective:

1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it:

a. does not conform to the Contract Documents; or

b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or

c. has been damaged prior to Engineer’s recommendation of final payment (unless responsibility for the protection thereof has been assumed by Owner at Substantial

8 | P a g e BCUA General Conditions Friday, September 26, 2025

Completion in accordance with Paragraph 14.04 or 14.05).

E. Furnish, Install, Perform, Provide:

1. The word “furnish,” when used in connection with services, materials, or equipment, shall mean to supply and deliver said services, materials, or equipment to the Site (or some other specified location) ready for use or installation and in usable or operable condition.

2. The word “install,” when used in connection with services, materials, or equipment, shall mean to put into use or place in final position said services, materials, or equipment complete and ready for intended use.

3. The words “perform” or “provide,” when used in connection with services, materials, or equipment, shall mean to furnish and install said services, materials, or equipment complete and ready for intended use.

4. When “furnish,” “install,” “perform,” or “provide” is not used in connection with services, materials, or equipment in a context clearly requiring an obligation of Contractor, “provide” is implied.

F. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning.

ARTICLE 2 – PRELIMINARY MATTERS

2.01 Delivery of Bonds and Evidence of Insurance

A. When Contractor delivers the executed counterparts of the Agreement to Owner, Contractor shall also deliver to Owner such bonds as Contractor may be required to furnish.

B. Evidence of Insurance: Before any Work at the Site is started, Contractor and Owner shall each deliver to the other, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance which either of them or any additional insured may reasonably request) which Contractor and Owner respectively are required to purchase and maintain in accordance with Article 5.

2.02 Copies of Documents

A. Owner shall furnish to Contractor up to ten printed or hard copies of the Drawings and Project

Manual. Additional copies will be furnished upon request at the cost of reproduction.

2.03 Commencement of Contract Times; Notice to Proceed and Limited Notice to Proceed

A. The Contract Times to run on the thirtieth day after the Effective Date of the Agreement or, if a

Notice to Proceed is given, on the day indicated in the Notice to Proceed.

B. The CONTRACTOR shall start the Work on or before the date specified herein or as

9 | P a g e BCUA General Conditions Friday, September 26, 2025 documented in the Notice to Proceed, or if no date is so specified, within ten (10) days of the mailing of the Notice to Proceed issued by the Engineer to the CONTRACTOR directing him to proceed with Work. The Contract Time shall commence in accordance with the effective date of the Notice to Proceed.

C. The Owner may determine it is in in the best interest of the authority to issue a “Limited Notice to Proceed” or LNP. The LNP, shall authorize the contractor to proceed on Owner directed work including but not limited developing progress schedules, project milestones as may exist and be stipulated in the contract/bid documents, providing a safety plan as specified, shop drawing review and/or other activities as directed by the Owner. In order for a formal Notice to Proceed to be issued the activities and required tasks of the LNP must be satisfied. It is incumbent on the CONTRACTOR to complete the tasks in the LNP in a timely manner not to exceed 20 calendar days.

1. Failure of the CONTRACTOR to satisfy the requests of the LNP may constitute default on part of the CONTRACTOR.

2. Deliverables required to satisfy the LNP shall be stipulated in the LNP.

2.04 Starting the Work

A. Contractor shall start to perform the Work on the date when the Contract Times commence to run. No Work shall be done at the Site prior to the date on which the Contract Times commence to run.

2.05 Before Starting Construction

A. Preliminary Schedules: Within 10 days after the Effective Date of the Agreement, or the date stipulated on the LNP (whichever is sooner), Contractor shall submit to Engineer for timely review:

1. a preliminary Progress Schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents;

2. a preliminary Schedule of Submittals; and

3. a preliminary Schedule of Values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdivides the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work.

4. Before the preparation of the first estimate, the CONTRACTOR shall submit for the

Engineer's approval a schedule of breakdown costs of all lump sum bid items into a series of minor subdivisions in the manner to be directed by the Engineer and for the sole purpose of determining the estimates of Work done for partial payments. Revisions to the schedule, if required, shall be furnished acceptable to the Engineer prior to consideration for partial

10 | P a g e BCUA General Conditions Friday, September 26, 2025 payment.

2.06 Preconstruction Conference; Designation of Authorized Representatives

A. Pursuant to NJAC 7:22-3.17(a) (26), After contract award and prior to the start of work, BCUA will schedule a preconstruction meeting. BCUA, the responsible engineer, the environmental and construction inspectors, the contractor and one or more representatives of the Department of Environmental Protection will be present at the preconstruction meeting. The primary purpose of the meeting will be to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in Paragraph 2.05.A, procedures for handling Shop Drawings and other submittals, processing Applications for Payment, and maintaining required records.

B. At this conference Owner and Contractor each shall designate, in writing, a specific individual to act as its authorized representative with respect to the services and responsibilities under the Contract. Such individuals shall have the authority to transmit instructions, receive information, render decisions relative to the Contract, and otherwise act on behalf of each respective party.

2.07 Initial Acceptance of Schedules

A. At least 10 days before submission of the first Application for Payment a conference attended by

Contractor, Engineer, and others as appropriate will be held to review for acceptability to Engineer as provided below the schedules submitted in accordance with Paragraph 2.05.A.

Contractor shall have an additional 10 days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to Contractor until acceptable schedules are submitted to Engineer.

1. The Progress Schedule will be acceptable to Engineer if it provides an orderly progression of the Work to completion within the Contract Times. Such acceptance will not impose on Engineer responsibility for the Progress Schedule, for sequencing, scheduling, or progress of the Work, nor interfere with or relieve Contractor from Contractor’s full responsibility therefor.

2. Contractor’s Schedule of Submittals will be acceptable to Engineer if it provides a workable arrangement for reviewing and processing the required submittals.

3. Contractor’s Schedule of Values will be acceptable to Engineer as to form and substance if it provides a reasonable allocation of the Contract Price to component parts of the Work.

ARTICLE 3 – CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE

3.01 Intent

A. The Contract Documents are complementary; what is required by one is as binding as if required by all.

B. It is the intent of the Contract Documents to describe a functionally complete project (or part thereof) to be constructed in accordance with the Contract Documents. Any labor, 11 | P a g e BCUA General Conditions Friday, September 26, 2025 documentation, services, materials, or equipment that reasonably may be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the indicated result will be provided whether or not specifically called for, at no additional cost to Owner.

C. Clarifications and interpretations of the Contract Documents shall be issued by Engineer as provided in Article 9.

D. Figured dimensions on the Drawings shall be given preference over scaled dimensions, but shall be checked by the CONTRACTOR before starting construction. Any errors, omissions or discrepancies shall be brought immediately to the attention of the Engineer, and his decisions thereon shall be final.

E. The Contract Documents require the furnishing of all labor, superintendence, materials, plant, power, light, heat, fuel, water, tools, appliances, equipment, supplies and other means of construction necessary or proper for performing and completing the Work. In general, the completed Work shall consist of the improvements and appurtenances completely installed, successfully tested and in "ready to operate" condition.

The CONTRACTOR shall perform and complete the Work in the manner best calculated to promote rapid construction consistent with safety of life and property, and to the satisfaction of the Engineer, and in strict accordance with the Contract Documents. The CONTRACTOR shall clean up all areas where Work has been and/or is being performed and shall maintain all areas where Work has been and/or is being performed during and after the completion of any Work, until accepted, and shall do all Work and pay all costs incidental thereto. He shall repair or restore all structures and property that may be damaged or disturbed during performance of the Work.

Detailed specifications for materials, equipment, workmanship and all items pertaining to a particular part of the Work may be found under those parts of the Contract describing the Work to be done and the methods of measurement and payment for the various Bid Items.

All Work called for in the Specifications applicable to this Contract, but not shown on the plans in their present form, or vice versa, shall be of the like effect as if shown or mentioned in both.

Work not specified in either the Drawings or in the Specifications, but involved in carrying out their intent or in the complete and proper execution of the Work, is required and shall be performed by the CONTRACTOR as though it were specifically delineated or described.

The apparent silence of the Specifications as to any detail, or the apparent omission from them of a detailed description concerning any Work to be done and materials to be furnished, shall be regarded as meaning that only the best general practice is to prevail and that only material and workmanship of the best quality is to be used, and interpretation of these Specifications shall be made upon that basis.

3.02 Reference Standards

A. Standards, Specifications, Codes, Laws, and Regulations

12 | P a g e BCUA General Conditions Friday, September 26, 2025

1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents.

2. No provision of any such standard, specification, manual, or code, or any instruction of a

Supplier, shall be effective to change the duties or responsibilities of Owner, Contractor, or Engineer, or any of their subcontractors, consultants, agents, or employees, from those set forth in the Contract Documents. No such provision or instruction shall be effective to assign to Owner, Engineer, or any of their officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents.

3.03 Reporting and Resolving Discrepancies

A. Reporting Discrepancies:

1. Contractor’s Review of Contract Documents Before Starting Work: Before undertaking each part of the Work, Contractor shall carefully study and compare the Contract Documents and check and verify pertinent figures therein and all applicable field measurements. Contractor shall promptly report in writing to Engineer any conflict, error, ambiguity, or discrepancy which Contractor discovers, or has actual knowledge of, and shall obtain a written interpretation or clarification from Engineer before proceeding with any Work affected thereby.

2. Contractor’s Review of Contract Documents During Performance of Work: If, during the performance of the Work, Contractor discovers any conflict, error, ambiguity, or discrepancy within the Contract Documents, or between the Contract Documents and (a) any applicable Law or Regulation, (b) any standard, specification, manual, or code, or (c) any instruction of any Supplier, then Contractor shall promptly report it to Engineer in writing. Contractor shall not proceed with the Work affected thereby (except in an emergency as required by Paragraph 6.16.A) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in Paragraph 3.04.

3. Contractor shall not be liable to Owner or Engineer for failure to report any conflict, error, ambiguity, or discrepancy in the Contract Documents unless Contractor had actual knowledge thereof.

B. Resolving Discrepancies:

1. Except as may be otherwise specifically stated in the Contract Documents, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Contract Documents and:

a. the provisions of any standard, specification, manual, or code, or the instruction of any

Supplier (whether or not specifically incorporated by reference in the Contract

13 | P a g e BCUA General Conditions Friday, September 26, 2025

Documents); or

b. the provisions of any Laws or Regulations applicable to the performance of the Work (unless such an interpretation of the provisions of the Contract Documents would result in violation of such Law or Regulation).

3.04 Amending and Supplementing Contract Documents

A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by either a Change Order or a Work Change Directive.

B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized, by one or more of the following ways:

1. A Field Order;

2. Engineer’s approval of a Shop Drawing or Sample (subject to the provisions of Paragraph

6.17.D.3); or

3. Engineer’s written interpretation or clarification.

C. CONTRACTOR may submit to the Engineer for his consideration a Modification Request to the

Contract Documents for a change in equipment, materials or methods of Work. A Modification Request will only be considered if it will not compromise the useful life, operation costs, safety, code compliance, project schedule, or design integrity of the system and is in accordance with N.J.A.C. 5:30-11.7 to -11.8. Any Modification Request submitted by CONTRACTOR shall be at the sole cost and expense of CONTRACTOR, including the obligation of CONTRACTOR to reimburse OWNER and Engineer for any costs and expenses incurred in connection with the submission of any Modification Request.

D. Requests by the CONTRACTOR shall only be considered if accompanied by a detailed report, calculations, and drawings signed and sealed by a licensed Professional Engineer in the State of New Jersey defining the impacts related to the Modification Report and the net cost savings to the OWNER over the useful life of the Modification.

E. CONTRACTOR shall submit all Modification Requests to the Engineer within sixty (60) calendar days after Notice to Proceed. The Engineer shall respond to the Request within thirty (30) calendar days of submission either denying the Request, deeming the Request incomplete, or conditionally approving the Request. In cases where Requests are conditionally approved, the Engineer shall define the conditions of approval including the applicable redesign costs and any other impacts which must be borne at the CONTRACTOR’S sole cost and expense. In cases where a Request is deemed incomplete, the CONTRACTOR shall resubmit the required information within ten

(10) calendar days or the Request will be deemed denied. No denied Requests will be reconsidered.

3.05 Reuse of Documents

A. Contractor and any Subcontractor or Supplier shall not:

14 | P a g e BCUA General Conditions Friday, September 26, 2025

1. have or acquire any title to or ownership rights in any of the Drawings, Specifications, or other documents (or copies of any thereof) prepared by or bearing the seal of Engineer or its consultants, including electronic media editions; or

2. reuse any such Drawings, Specifications, other documents, or copies thereof on extensions of the Project or any other project without written consent of Owner and Engineer and specific written verification or adaptation by Engineer.

B. The prohibitions of this Paragraph 3.05 will survive final payment, or termination of the

Contract. Nothing herein shall preclude Contractor from retaining copies of the Contract Documents for record purposes.

3.06 Electronic Data

A. Unless otherwise stated in the Supplementary Conditions, the data furnished by Owner or

Engineer to Contractor, or by Contractor to Owner or Engineer, that may be relied upon are limited to the printed copies (also known as hard copies). Files in electronic media format of text, data, graphics, or other types are furnished only for the convenience of the receiving party. Any conclusion or information obtained or derived from such electronic files will be at the user’s sole risk. If there is a discrepancy between the electronic files and the hard copies, the hard copies govern.

B. Because data stored in electronic media format can deteriorate or be modified inadvertently or otherwise without authorization of the data’s creator, the party receiving electronic files agrees that it will perform acceptance tests or procedures within 60 days, after which the receiving party shall be deemed to have accepted the data thus transferred. Any errors detected within the 60-day acceptance period will be corrected by the transferring party.

C. When transferring documents in electronic media format, the transferring party makes no representations as to long term compatibility, usability, or readability of documents resulting from the use of software application packages, operating systems, or computer hardware differing from those used by the data’s creator.

ARTICLE 4 – AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS;

HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS

4.01 Availability of Lands

A. Owner shall furnish the Site. Owner shall notify Contractor of any encumbrances or restrictions not of general application but specifically related to use of the Site with which Contractor must comply in performing the Work. Owner will obtain in a timely manner and pay for easements for permanent structures or permanent changes in existing facilities. If Contractor and Owner are unable to agree on entitlement to or on the amount or extent, if any, of any adjustment in the Contract Price or Contract Times, or both, as a result of any delay in Owner’s furnishing the Site or a part thereof, Contractor may make a Claim therefor as provided in Paragraph 10.05.

B. Upon reasonable written request, Owner shall furnish Contractor with a current statement of

15 | P a g e BCUA General Conditions Friday, September 26, 2025 record legal title and legal description of the lands upon which the Work is to be performed and Owner’s interest therein as necessary for giving notice of or filing a mechanic’s or construction lien against such lands in accordance with applicable Laws and Regulations.

C. Contractor shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment.

4.02 Subsurface and Physical Conditions

A. Reports and Drawings:

1. those reports known to Owner of explorations and tests of subsurface conditions at or contiguous to the Site; and

2. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the accuracy of the “technical data” contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such “technical data” is identified in the Supplementary Conditions. Except for such reliance on such “technical data,” Contractor may not rely upon or make any claim against Owner or Engineer, or any of their officers, directors, members, partners, employees, agents, consultants, or subcontractors with respect to:

1. the completeness of such reports and drawings for Contractor’s purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto; or

2. other data, interpretations, opinions, and information contained in such reports or shown or indicated in such drawings; or

3. any Contractor interpretation of or conclusion drawn from any “technical data” or any such other data, interpretations, opinions, or information.

4.03 Differing Subsurface or Physical Conditions

A. Notice: If Contractor believes that any subsurface or physical condition that is uncovered or revealed either:

1. is of such a nature as to establish that any “technical data” on which Contractor is entitled to rely as provided in Paragraph 4.02 is materially inaccurate; or

2. is of such a nature as to require a change in the Contract Documents; or

3. differs materially from that shown or indicated in the Contract Documents; or

4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents;

16 | P a g e BCUA General Conditions Friday, September 26, 2025 then Contractor shall, promptly after becoming aware thereof and before further disturbing the subsurface or physical conditions or performing any Work in connection therewith (except in an emergency as required by Paragraph 6.16.A), notify Owner and Engineer in writing about such condition. Contractor shall not further disturb such condition or perform any Work in connection therewith (except as aforesaid) until receipt of written order to do so.

B. Engineer’s Review: After receipt of written notice as required by Paragraph 4.03.A, Engineer will promptly review the pertinent condition, determine the necessity of Owner’s obtaining additional exploration or tests with respect thereto, and advise Owner in writing (with a copy to Contractor) of Engineer’s findings and conclusions.

C. Possible Price and Times Adjustments:

1. The Contract Price or the Contract Times, or both, will be equitably adjusted to the extent that the existence of such differing subsurface or physical condition causes an increase or decrease in Contractor’s cost of, or time required for, performance of the Work; subject, however, to the following:

a. such condition must meet any one or more of the categories described in Paragraph 4.03.A; and

b. with respect to Work that is paid for on a unit price basis, any adjustment in Contract Price will be subject to the provisions of Paragraphs 9.07 and 11.03.

2. Contractor shall not be entitled to any adjustment in the Contract Price or Contract Times if:

a. Contractor knew of the existence of such conditions at the time Contractor made a final commitment to Owner with respect to Contract Price and Contract Times by the submission of a Bid or becoming bound under a negotiated contract; or

b. the existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation, exploration, test, or study of the Site and contiguous areas required by the Bidding Requirements or Contract Documents to be conducted by or for Contractor prior to Contractor’s making such final commitment; or

c. Contractor failed to give the written notice as required by Paragraph 4.03.A.

3. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any adjustment in the Contract Price or Contract Times, or both, a Claim may be made therefor as provided in Paragraph 10.05 within the cost limitations as stated in the BCUA LPCL Supplementary Terms and Conditions Q-27BJ section 1.0.33. However, neither Owner or Engineer, or any of their officers, directors, members, partners, employees, agents, consultants, or subcontractors shall be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project.

17 | P a g e BCUA General Conditions Friday, September 26, 2025

4. In all instances where differing site or changed conditions exist the provisions of NJSA 40A:11-16.7 sub sections a, b, c, & d as follows;

All construction contracts issued by a contracting unit for bids which were advertised on or after the effective date of P.L.2017, c. 317 (C.40A:11-16.7 et seq.) shall include the changed conditions contract provisions set forth in this section, which provisions shall be deemed to be a part of any such contract even if not expressly incorporated therein, and which provisions may not be modified in any manner by the contracting unit.

a. A contract subject to this section shall include the following differing site conditions provisions:

(1) If the contractor encounters differing site conditions during the progress of the work of the contract, the contractor shall promptly notify the contracting unit in writing of the specific differing site conditions encountered before the site is further disturbed and before any additional work is performed in the impacted area.

(2) Upon receipt of a differing site conditions notice in accordance with paragraph (1) of this subsection, or upon the contracting unit otherwise learning of differing site conditions, the contracting unit shall promptly undertake an investigation to determine whether differing site conditions are present.

(3) If the contracting unit determines different site conditions that may result in additional costs or delays exist, the contracting unit shall provide prompt written notice to the contractor containing directions on how to proceed.

(4)(a) The contracting unit shall make a fair and equitable adjustment to the contract price and contract completion date for increased costs and delays resulting from the agreed upon differing site conditions encountered by the contractor.

(b) If both parties agree that the contracting unit's investigation and directions decrease the contractor's costs or time of performance, the contracting unit shall be entitled to a fair and equitable downward adjustment of the contract price or time of performance.

(c) If the contracting unit determines that there are no differing site conditions present that would result in additional costs or delays, the contracting unit shall so advise the contractor, in writing, and the contractor shall resume performance of the contract, and shall be entitled to pursue a differing site conditions claim against the contracting unit for additional compensation or time attributable to the alleged differing site conditions.

(5) Execution of the contract by the contractor shall constitute a representation that the contractor has visited the site and has become generally familiar with the local conditions under which the work is to be performed.

(6) As used in this subsection, “differing site conditions” mean physical conditions at the contract work site that are subsurface or otherwise concealed and which differ materially from those indicated in the contract documents or are of such an unusual nature that the conditions differ materially from those ordinarily encountered and generally recognized as inherent in the work of the character provided for in the contract.

https://1-next-westlaw-com.proxy.libraries.rutgers.edu/Link/Document/FullText?findType=l&pubNum=1077005&cite=UUID(I80838C8006-CC11E8AACCD-94647BB9206)&originatingDoc=N8DEF6380169E11E88208B9A86E446D98&refType=SL&originationContext=document&transitionType=DocumentItem&ppcid=a4b74a3b353f4a6184423481d6fca907&contextData=(sc.UserEnteredCitation)

18 | P a g e BCUA General Conditions Friday, September 26, 2025

b. A contract subject to this section shall include the following suspension of work provisions:

(1) The contracting unit shall provide written notice to the contractor in advance of any suspension of work lasting more than 10 calendar days of the performance of all or any portion of the work of the contract.

(2) If the performance of all or any portion of the work of the contract is suspended by the contracting unit for more than 10 calendar days due to no fault of the contractor or as a consequence of an occurrence beyond the contracting unit's control, the contractor shall be entitled to compensation for any resultant delay to the project completion or additional contractor expenses, and to an extension of time, provided that, to the extent feasible, the contractor, within 10 calendar days following the conclusion of the suspension, notifies the contracting unit, in writing, of the nature and extent of the suspension of work. The notice shall include available supporting information, which information may thereafter be supplemented by the contractor as needed and as may be reasonably requested by the contracting unit. Whenever a work suspension exceeds 60 days, upon seven days' written notice, either party shall have the option to terminate the contract for cause and to be fairly and equitably compensated therefor.

(3) Upon receipt of the contractor's suspension of work notice in accordance with paragraph

(2) of this subsection, the contracting unit shall promptly evaluate the contractor's notice and promptly advise the contractor of its determination on how to proceed in writing.

(4)(a) If the contracting unit determines that the contractor is entitled to additional compensation or time, the contracting unit shall make a fair and equitable upward adjustment to the contract price and contract completion date.

(b) If the contracting unit determines that the contractor is not entitled to additional compensation or time, the contractor shall proceed with the performance of the contract work, and shall be entitled to pursue a suspension of work claim against the contracting unit for additional compensation or time attributable to the suspension.

(5) Failure of the contractor to provide timely notice of a suspension of work shall result in a waiver of a…