STATEMENT OF WORK
FY20 DRY DOCK REPAIRS
NOAA Ship REUBEN LASKER
REVISION 2
Vessel Particulars
Year Built: 2013 Builder: Marinette Marine, Corp.
Marinette, Wisconsin
ABS ID: 13225985
IMO Number: 9664988 Construction: Welded Steel Hull/ Aluminum superstructure Propulsion: Diesel-Electric
Single Propeller/fixed pitch/1603 HP Bow Thruster: Elliot 40T3S/940 HP Length Overall: 208.6 Feet Beam: 49.2 Feet Draft: 19.4 ft Full load Centerboard retracted Draft: 29.7 ft Full load Centerboard extended Frame spacing: 600 mm (23.62”) Displacement: 1,840 metric Tons Light Ship
2,479 metric Tons Full Load
NOAA Ship REUBEN LASKER FY20 DRYDOCK REPAIRS
TABLE OF CONTENTS
Appendix A
Detailed Statement of Work
Item Title ............................................................................................................................... Page
Basic – Class 10000 Items
10101 - Routine Dry Docking 10102 - Underwater Inspections 10103 - ABS/USCG Inspections Assistance 10104 - Centerboard Maintenance 10105 - Preservation of Underwater Body 10106 - Hull Anode Replacement 10107 - Propeller Clean & Polish 10108 - Service Sea Valves 10109 - Service/Inspect Cathelco Anti-Fouling and Impress Current System .. ………………… 31 10110 - Ground Tackle Maintenance & Preservation 10111 - Bow Thruster Inspections, Grooming & Servicing 10112 - Inspect/Service Thrust, Line Shaft & Propulsion Motor Carrier Bearings 10113 - Freeboard Preservation 10114 - Inspect/Service MSD Tank 10115 - Tank Preservation 10116 - Clean & Test SSDG Heat Exchangers 10117 - Maintenance Aft Deck Crane 10118 - Replace Laundry Room Ducting 10119 - Dock & Sea Trials 10120 - Protective Coverings 10121 - Weight Control 10122 - Utilities and Services, Daily Rates Mooring/Drydock
Basic – Class 20000 Items
20201 - Install Searchlights 20202 - Replace Mess Deck Flooring
Growth – Class 30000 Items
30000 - Additional Government Requirements
Optional – Class 50000 Items
50501 - Deck Coating Maintenance 50502 - Deckhouse & Stack Coating Maintenance 50503 - Mast Coating Maintenance 50504 - Prep & Paint Anti Roll Tank 50505 - Main Generator Room and Trawl Winch Room Bilge Cleaning 50506 - Miscellaneous Piping Repairs 50507 - Miscellaneous Welding and Fabrication 50508 - Provide Drydock Lay Days
Appendix B
Specific Contract Work Definitions and Requirements
Appendix C
NOAA Standard Specifications
S0100 Implementation and Conduct of Checkpoints S2906 Arc Welding on Waterborne Vessels S4800-2 Piping Systems, General Requirements S6900 General Requirements for Electrical/Electronic Items S1205 Zinc Protectors S1905-1 Inspection & Routing Maintenance of Impressed Current Cathodic Protection Systems S8200 Weight Testing of Cranes and Davits
S2603 Inspection, Repair and Preservation of Ground Tackle
S4824-1 Refurbishment of Regulating/Reducing Valves
S4824-2 Repair & Test of Swing Check Valves
S4824-3 Shop Repair & Testing of Gate Valves
S4824-4 Shop Repair & Testing of Globe Valves AMC-240-1 Propulsion Shafts and Propellers AMC-505-1B Valve Overhaul & Test
Appendix D
Technical Publications
RL-165-01-00003-010 Centbrd Lifting Device Vol. 1 RL-165-01-00003-020 Centbrd Lifting Device Vol. 2 RL- 202-01-01-050B Rev B- CMCS RL- 202-0001-080 CMCS RL- 226 - 006-01: Stern Tube Bearing/ Shaft Sea RL-235-01-0001-10-1360 Generator RL-235-01-0002-10 -910 Generator RL-320-01-00002-010- Motor Controllers RL-422-01-00021-010 Search Light RL-500-00-01 Rev A Shipboard Valves RL-562-01: Rudder RL-568-01-01: Bow Thruster RL-593-01-01 Marine Sanitation System RL-591-01-02- Rev A, Aft Deck Crane RL-562 High Performance Flap Rudder RL-633-01-Cathelco Anti-Fouling System RL-633-01- Impress Current Protection System
Appendix E
Industry Standards and Public Documents
No Industry Standards or Public Documents are provided with the solicitation. Referenced Industry Standards and Public Documents are:
IEEE Standard 45-1983; Recommended Practice for Electric Installations on Shipboard Code of Federal Regulations Title 46, Subchapter J; Electrical Engineering Steel Structures Painting Council, (SSPC), Surface Preparation Specifications American Bureau of Shipping, Rules for Building and Classing Steel Vessels
Appendix F
Drawings
FSV6 -100-01 Centerboard Hoisting Gear FSV6 - 163-01: Sea Chest Diagram FSV6 -170-01 - Mast Details/Arrangements FSV6 - 243-01: Shaft Layout and Details FSV6 - 256-01 Main Seawater Cooling Sys FSV6 - 437-05 Center Board Wiring Diagram FSV6 - 461-03 Transducer Arrangement and Installation FSV6 - 512-01 HVAC Diagram FSV6 - 562-01: Rudder Arrangement FSV6 - 528-01 Grey and Black Water Sys FSV6 - 524-01: Aux SW Cooling System FSV6 - 568-01: Bow Thruster Layout & Detail FSV6 - 573-01 (C) Crane Deck Aft FSV6 - 601-01: General Arrangement FSV6 - 601-02: Booklet of General Drawings FSV6 - 602-01: Hull Markings FSV6 - 631-01 Paint Schedule FSV6 - 633-02: Cathodic Protection FSV6 - 633-01: Impressed Current Cathodic Protection FSV6 - 997-01: Docking Plan
Appendix G
Government Furnished Material
Item 10109 Cathoidco Anodes as follows:
2 Anodes Ref : UZX27 (copper) 2 Anodes Ref : UZX29 (cast iron) 8 Anodes Ref : SUV27 (copper) 8 Anodes Ref : SUV29 (cast iron)
Item 10111 One (1) Ethernet Module Four (4) Electronic Dimmer One (1) Unmanaged Switch Four (4) Bridge HMI’s Four (4) Control Plates Four (4) Signal Converters
Item 10114 One (1) Set of Medium for MSDS tank
Item 10117 five (5) electric/hydraulic solenoids
Item 20201 Two (2) 500-watt xenon searchlight, Carlisle & Finch model # XY5EDE-24ARF Two (2) 6PS115 Power Supply, 115/1/60 Volt Input Two (2) C4E1-1-1 Master Control Station (Console Mount)
APPENDIX A
Detailed Statement of Work
Basic – Class 10000 Items
Item No. 10101 Title: Routine Drydocking
1 SCOPE
1.1 Background: The ship is an American Bureau of Shipping (ABS) classed and United States Coast Guard (USCG) inspected vessel. The contractor must notify ABS/USCG of the schedule for all events and inspections that they want to observe.
1.2 Objective: To drydock the ship in a drydock or a marine railway and to provide for it in this abnormal condition in a way that allows other work items to be accomplished. To return the vessel to the water.
2 REFERENCE DOCUMENTS
2.1 Appendix B Specific Contract Work Definitions and Requirements
2.2 Ship’s Drawing FSV6-997-01; Docking Plan
2.3 NOAA Std Form S0700, Docking Report
2.4 NOAA Standard Specification S0700-3; Drydock Standards for NOAA Ship Availabilities
2.5 American Bureau of Shipping, Rules for Building and Classing Steel Vessels
2.6 NOAA Standard Specification 0100; Conduct of Checkpoints
2.7 Drydocking Worksheet (Attached)
3 GOVERNMENT FURNISHED MATERIAL (GFM)
3.1 None
4 REQUIREMENTS
4.1 The contractor shall furnish all plans, labor, and materials required to dock and undock the ship in a safe and satisfactory manner and perform the work and associated services, including inspections and reports, outlined herein and/or required in other specification items. The dry dock must be certified in accordance with reference 2.3, S0700-3. Before drydocking and undocking, the contractor's dockmaster shall hold a drydocking/undocking conference to advise the ship's personnel what will be expected of them.
4.1.1 As documentation of the drydock’s certification status submit the Drydocking Worksheet attached to reference 2.3 with the solicitation. If the contractor may put the ship into more than one drydock, submit Drydocking Worksheet for all drydocks the contractor may use.
4.1.2 The ship may be dry docked with another vessel. The contractor shall ensure that the Reuben Lasker will not be delayed when exiting the drydock or the contractor will be assessed liquidated damages. If the contractor plans to dual dock they shall provide information in their production plan or schedule.
4.2 Within the first 10% of the period of performance, the ship shall be lifted in a suitable drydock or marine railway, in accordance with reference 2.1. Blocks and shoring shall be placed clear of obstruction so as to support the ship without strain or distortion. The ship shall be hauled without list.
The ship shall be docked in docking position 1 as shown on reference 2.1.
***** CHECKPOINT *****
4.2.1 Immediately before drydocking, inspect blocking system with the COR. Present the COR with a list of blocks left out. Demonstrate the marking of the Stern Reference Point and the centering devices.
Prove the distance from the Stern Reference Point to the first keel block. Demonstrate the position and height of blocks randomly selected by the COR. Demonstrate that all blocks in the list of blocks to be left out are, indeed, not present.
4.3 After the ship is hauled, service lines shall be provided and hooked up. Staging shall be erected, as required, to accomplish the underbody work and inspection. Two suitable gangways shall be furnished and maintained to provide access to the ship at all times.
4.3.1 Some discharges, such as cooling water and ballast pump overboard, discharge directly over the side. If it is not acceptable for this discharge to go into the drydock basin, provide a means to capture them and dispose of them in an appropriate manner.
4.4 Water wash - Within 4 hours after drydocking begin washing the entire underwater body including the propeller, centerboard and trunk, sea chest intakes and intake piping up to and including the strainer baskets, and boot-top are to be water washed with fresh water to remove all dirt, slime and marine growth. Sonic projectors (transducers) shall be cleaned of all marine growth with plastic scrapers and scrubbing pads. Upon cleaning they shall be rinsed with low pressure water and protected from the full hose blast. The water wash shall meet the following minimum requirements:
The most heavily slimed areas shall be washed within the first hour.
Hose pressure shall be 100 PSI minimum Hose size shall be 1-1/2" minimum
Use of a high-pressure wash is not required but is acceptable to the Government.
4.5 After docking, the contractor and Contracting Officer's Representative (COR) shall jointly inspect the hull. Particular attention shall be given to docking damage. The contractor shall submit a report within 24 hours detailing damage found and recommending required repairs. No remedial work, except that specified in other items of this contract, shall commence until authorized in writing by the Contacting Officer.
4.6 The ship will remain out of the water until all work required under the contract, which requires drydocking, has been completed. All required painting of the interior shell plating surfaces that would be below the waterline after undocking must be completed while in drydock. Upon completion of the underwater work and approval by the COR, the ship will be undocked. During the entire docking and undocking procedure and while the ship is out of the water, special care shall be taken to protect the ship from damage or fire.
4.7 In undocking the ship, the dock shall be flooded or the railway lowered, as the case may be, until as many underwater openings as possible are covered without lifting the ship off the blocks. An adequate watch shall be posted to check for leaks. If no leaks are found, and upon permission of the COR, the undocking may continue. Reference sighting marks for longitudinal and transverse positioning shall be provided so that the ship may be re-landed if necessary.
4.8 After the ship is undocked, the contractor must submit a docking report in accordance with reference
2.2. The contractor is advised that, although the report is not required until after undocking, the information necessary to complete the report must be gathered while the ship is in drydock.
5 QUALITY ASSURANCE
5.1 Submit a written report of the results of the all testing and inspections required by this item. The report must contain the date, time, results, and names of the witnesses.
6 NOTES
6.1 All hull openings shall be secured outside of normal working hours.
6.2 While the ship is in drydock, all hull openings shall be secured outside of normal working hours.
6.3 Drydock Worksheet
Item No. 10102 Title: Underwater Body Inspections & Repairs
1 SCOPE
1.1 Background -This item contains some inspections required by Item #10103 ABS/USCG Surveys; however, the work in this item either goes beyond the required inspections or specifies which of ABS/USCG allowed options is required by the Government.
1.2 Objective - To inspect various structures and equipment that are accessible only when the ship is in drydock.
2 REFERENCE DOCUMENTS
2.1 Appendix B Specific Contract Work Definitions and Requirements
2.2 NOAA Standard Specification S0100; Implementation and Conduct of Check Points
2.3 American Bureau of Shipping, Rules for Building and Classing Steel Vessels
2.4 Drawing FSV6 -163-01: Sea Chest Diagram
2.5 Drawing FSV6 -243-01: Shaft Layout and Details
2.6 Drawing FSV6- 562-01: Rudder Arrangement
2.7 Drawing FSV6 - 568-01: Bow Thruster Layout & Detail
2.8 Technical Manual FSV6-562-01 Rudder
2.9 Technical Manual RL-226-006-010 Stern Tube Bearing and Shaft Seal
2.10 Technical Manual RL-568-01-00001-010 Bow Thruster
3 GOVERNMENT FURNISHED MATERIAL (GFM)
3.1 None
4 REQUIREMENTS
4.1 General Requirements
4.1.1 The contractor shall perform all work in accordance with the requirements of the documents cited in paragraph 2 above.
4.1.2 Whenever an inspection is called for the contractor must submit a written report to the COR detailing findings and /or recommended repairs.
4.1.3 The vessel is ABS Classed and USCG inspected. ABS/USCG may attend some of the inspections required in this specification. The contractor is responsible for advising ABS/USCG when the inspections will occur.
4.1.4 All inspections of the stern tube bearing, line shaft bearing, thrust bearings, seal, shaft, and rudder shall be accomplished under the guidance of a technical representative familiar with all system components. A possible source for a technical representative with extensive experience on NOAA FSV’s and these components is:
Sound Propeller Systems LLC 9130 15th Place South – Suite A Seattle, WA, 98108
(206) 392-0021\
4.2 Sea Chest Inspections
4.2.1 Remove all sea chest gratings. Inspect interior of sea chest for damage. Inspect all zincs and antifouling system anodes for wastage. Provide a report to the COR of the inspections and any repairs if needed.
4.2.2 Upon completion of all underwater work, reinstall sea chest gratings with new 316 CRESS hardware.
4.3 Rope Guard & Line Cutter Inspections
4.3.1 Remove the rope guard. Remove any debris/line found. Upon completion of all underwater work, reinstall with new 316 CRESS hardware.
4.3.2 Inspect the line cutter for signs of damage and/or corrosion. DO NOT remove the line cutter unless serious damage is discovered that requires replacement of the unit. Provide a report to the COR of the inspections and any repairs if needed.
4.4 Hull Inspections
4.4.1 Hull: Inspect the condition as to structural damage, corrosion, welds, rivets, fastenings, caulking or evidence of grounding, collision or extensive strain.
4.5 Bow Thruster Inspections
4.5.1 Remove the gratings from the bow thruster intakes to facilitate access to the bow thruster sea chest for inspections and painting. Upon completion of all underwater work, replace the gratings using new 316 CRESS fasteners with locking nuts.
4.5.2 Inspect bow thruster for signs of damage and/or corrosion. Complete the items listed in reference 2.10, check list 2 and checklist 3, to all components that are submerged. Provide a report to the COR of the inspections and any repairs if needed.
4.6 Centerboard Inspections
4.6.1 Inspect the Centerboard and trunk for signs of damage and corrosion. Open all centerboard access covers and clean/inspect the interior. Provide a report to the COR on the condition and any recommended repairs.
4.6.2 Inspect and clean all transducer faces using plastic scrapers and scrubbing pads. After cleaning/inspections, transducers shall be protected from sand blasting and painting.
****** CHECKPOINT ******
4.7 Rudder Inspections. Provide the services of an American Bureau of Shipping (ABS)/USCG representatives to witness the inspections required by this work item.
4.7.1 Under the guidance of the rudder tech rep, verify the mechanical integrity of the rudder stock taper joint, rudder flap and associated linkage. Inspect rudder sections to the extent possible without removing rudder welded access plates. Remove bolted covers or obstructions, measure Neck Bearing, Rudder Hinge, Link System slide bolt to slide bushing clearance.
4.7.2 In addition to feeler gage measurements of bearing/shaft/pin clearances taken above, perform a test of the rudder and the rudder flap clearances by jacking the rudder forward, aft, port and starboard to determine amount of travel at a convenient location to attach dial indicator measuring travel of the rudder with respect to the hull. Measure and record travel and dial indicator location(s) on a condition report.
4.7.3 Drain the rudder in the presence of the COR and the ABS/USCG representative. If water is present, conduct an air test of the rudder to a pressure of 3 PSIG. The test shall show absolutely no pressure drop in 10 minutes. If the test shows a pressure drop, conduct a soap test to isolate all leaks and submit a report to the COR detailing the leaks and recommended repairs.
*****CHECK POINT*****
4.8 Propeller shaft, stern tube, line shaft and thrust bearings, and shaft seal inspections. NOTE - Inspections shall be accomplished leaving the tailshafts and propeller in place.
4.8.1 Provide the services of an ABS/USCG representative to witness the inspections required by this work item.
4.8.2 Under the guidance of the bearing/rear seal tech rep, perform the following:
4.8.2.1 Stern Tube Bearing - Perform a borescope analysis of the stern tube bearing inspecting each water lubrication groove Provide a digital video of the bore scoping to the COR In accordance with reference 2.9, measure and record stern tube bearing wear down readings, specifically the shaft-to Thordon stern tube bearing clearance. Submit a report detailing the bearing clearances to the COR and ABS/USCG Inspector.
4.8.2.2 Inspect the rear shaft seal. If inspection indicates replacement, replace the seal.
4.8.2.3 Open /inspect the thrust bearings
4.8.2.4 Open/Inspect the line shaft bearings.
4.9 Locate and inspect fuel Tank drain plugs for signs of leakage.
4.10 Remove void drain plugs listed below and inspect for water intrusion. Record results on a condition report. Fill and drain or float coat voids and rudder with rust preventive compound complying with MIL-C- 16173, Grade 5, or Eureka Fluid Film Liquid A or equal. Reinstall void drain plugs using ABS/USCG approved thread anti-seize sealant on all plugs:
Skeg drain plug frame 87-88 starboard
Aft stern tube structure Port & starboard bilge keels Rudder and rudder blade/flap
5 QUALITY ASSURANCE
5.1 Submit a written report of the results of the tests and inspections required by this item. The report must contain the date, time, results, and names of the witnesses.
6.1 Work in this item must be accomplished while the ship is in drydock.
Item No. 10103 Title: ABS/USCG Inspections Assistance
1 SCOPE:
1.1 Background - The NOAA Ship REUBEN LASKER is an ABS Classed vessel and USCG inspected. The ABS ID is 13225985. Each inspection in this item is considered a CHECKPOINT and the COR must be notified in accordance with reference 2.1.
1.2 Objective - To coordinate the services of and assistance to the American Bureau of Shipping (ABS) and USCG representatives to conduct of the following surveys:
Annual Automation Survey 2 Annual Load Line Survey 2 Annual Machinery Survey 2 Annual Hull Survey 2 Drydocking Survey Intermediate Safety Construction Survey
2 REFERENCE DOCUMENTS:
2.1 NOAA Standard Specification S0100; Implementation and Conduct of Checkpoints
2.2 American Bureau of Shipping, Rules for Building and Classing Steel Vessels
2.3 Appendix B Specific Contract Work Definitions and Requirements
2.4 NOAA Standard Specification AMC-533-1, Potable Water Tank Disinfection
3 GOVERNMENT FURNISHED MATERIAL (GFM):
3.1 None.
4 REQUIREMENTS:
4.1 The contractor shall perform all work in accordance with the requirements of the documents cited in paragraph 2 above.
4.2 Coordinate the services of ABS and USCG representatives to conduct the surveys listed in 1.2. ABS inspections shall be coordinated by the Contractor to avoid interferences and duplications. The Contractor shall conduct a joint meeting with the COR, ABS and USCG to discuss inspections and requirements for attendance by the ABS and/or USCG within 3 working days of the ship’s arrival at the contractor’s facility.
Each item requiring inspection shall be reviewed to ensure there will be adequate coverage and that all necessary documentation has been provided to ABS/USCG.
4.2.1 The ABS/USCG representative shall witness the inspections required by the surveys of 4.1 and as specified by the individual work items. All inspections shall be accomplished with COR, or other designated government representative present.
4.2.2 The majority of USCG inspection requirements are identical to those required by ABS. The USCG may attend each inspection point or defer this to ABS. The contractor shall instruct ABS to coordinate all inspection items and checkpoints with the USCG to ensure that COI requirements met.
4.2.3 The Contractor shall provide the COR a schedule of ABS/USCG inspections and shall update the schedule as required to show those inspections which have been completed and those which are outstanding with an anticipated completion date.
4.2.4 The Government will compensate ABS for survey costs under a separate purchase order.
Neither Government nor Contractor shall be compensated by the other for delay of a scheduled survey if delay is caused by ABS for which neither Contractor nor Government is at fault.
4.3 Provide all assistance to the ABS Surveyor/USCG Inspector as required to conduct the surveys listed in 1.2.
4.3.1 Various items in this Statement of Work may overlap with the requirements of this item. In general, when there is overlap it is because the item specifies which of the optional ABS/USCG survey methods will be used or because the Government requires more than the minimum ABS/USCG required inspection. The fact that an item may or may not be called out separately in this Statement of Work does not relieve the contractor from the responsibility to provide the ABS/USCG surveys listed in 1.2.
4.3.2 Items identified by the ABS Surveyor/USCG Inspector that require correction before certificates can be issued shall be reported to the government in a CFR and repairs shall be accomplished under a change order.
4.4 Tail shaft and rudder will be inspected in place per item 10102. Propellers shall be inspected in place per item 10107.
4.5 Tank Inspections and Cleaning
4.5.1 Open, clean and ventilate the tanks, voids, lockers and coffer dams as shown on table 6.5. Expect the ship to arrive at the contractor’s facility with not more than 50% of its fuel capacity on board. Transfer fuel as required to accomplish the inspections. Fuel transfers will be performed by the ship’s crew. Provide the services of a Marine Chemist to certify the tanks gas free, safe for entry, safe for hot work.
4.5.2 Cleaning requirements. - The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths. Disinfecting tank and internal components (specifically tank 4-34-0) as needed to make tank safe for entry and inspection.
4.5.3 Any remaining fluids in a tank to be tested which would prevent it from being certified gas free, safe for men and hot work shall be removed and disposed of by the Contractor in compliance with all applicable Federal, state, and local laws, ordinances and regulations.
4.5.4 The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, TLI condition, suction/discharge piping condition, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a report to the COR for each tank that is inspected.
4.5.5 ABS/USCG inspection will involve “hydros” of tanks. The contractor is responsible for developing a plan with ABS/USCG to accomplish these tests and for submitting the plan to the COR as part of the ABS/USCG inspection plan.
4.5.6 Potable Water Tank refilling/testing - Fill each tank until water runs out the vents. Only potable water, suitable for human consumption, shall be used. Disinfect both potable water tanks in accordance with reference 2.4.
4.5.7 When closing tanks and voids upon completion of all test and inspections, install new gaskets, chase threads, clean threaded sockets and replace damaged fasteners.
4.5.8 The COR will be notified before final closures of all tanks or voids to perform a final inspection.
***** CHECK POINT *****
4.6 Touch=up Painting – Clean all damaged paint to sound paint or bare metal. Clean all exposed metal free of foreign matter and corrosion. Spot prime all damaged paint or exposed metal. Coat all new and damaged areas with 2 coats of finish paint to match the surrounding area. Epoxy paint must be used over galvanized metal.
5 QUALITY ASSURANCE:
5.1 Submit a written report(s) of the results of the testing required by this item. The report(s) must contain the date, time, results, and names of the witnesses.
6 NOTES:
6.1 Some inspections in this item must be done while the ship is in dry dock. Some require the ship to be in the water. The contractor is responsible for scheduling the inspections around the dry docking.
6.2 All inspections in this item are in support of the ABS/USCG classification process and must be carried out to the satisfaction of the ABS surveyor/USCG Inspector. Required repairs identified will be the subject of a Change Request.
6.3 The crew will assist in making documentation and/or equipage available for inspection. The crew must be told what is required and given 24 hour notice to meet those requirements.
6.4 The contractor is advised that this is a substantial item. The Government recommends that the contractor contact the local ABS/USCG office to determine what is involved in each inspection and what assistance ABS/USCG will require.
6.5 Tank/Void Table
Tank # Ballast Tank List Capacity (Liters) Location
4-1-0 Forepeak Ballast (C) 43,678 Fr. 1-7 CL
4-13-2 Ballast Deep Tank #1A (P) 21,456 Fr. 13-19 Port
4-13-1 Ballast Deep Tank #1A (S) 21,456 Fr. 13-19 Stbd
4-29-2 Ballast Double Bottom #3 (P) 36,012 Fr. 29-39 Port
4-29-1 Ballast Double Bottom #3 (S) 36,012 Fr. 29-39 Stbd
Tank # Fresh Water Tank List Capacity (Liters) Location
3-19-2 Fresh Water (P) 17,508 Fr. 19-27 Port
3-19-1 Fresh Water (S) 17,508 Fr. 19-27 Stbd
Tank # Misc Tanks Capacity (Liters) Location
4-34-0 Waste Water (C) 36,163 Fr. 34-39 Center
4-47-2 Oily Water (P) 5,352 Fr. 47-49 Port
02-22-0 Roll Stabilization Tank (C) 72,441 Fr. 22-29 Center
Void # Compartment Name Location
4-49-01 Void Fr 49 Center, Inter-bottom
LASKER TANK DIAGRAM
Item No 10104 Centerboard Maintenance
1. SCOPE
1.1. Objective - To remove the centerboard from the vessel, conduct maintenance and services needed to perform a complete overhaul of the centerboard, and reinstall.
2. REFERENCE DOCUMENTS
2.1. Appendix B Specific Contract Work Definitions and Requirements
2.2. NOAA Standard Specification S0100; Implementation and Conduct of Check Points
2.3. Technical Manual RL-320-01-00003-010 Rev 3 Motor Control Centers
2.4. Technical Manual RL-165-01-00003-010 Rev C, Centerboard Lifting Device Vol. One
2.5. Technical Manual RL-165-01-00003-010 Rev C, Centerboard Lifting Device Vol. Two
2.6. Drawing FSV6-461-03 Transducer Arrangement and Installation”
2.7. Drawing FSV6-461-01 Mission Scientific Block Wiring Diagram”
2.8. Drawing FSV6-437-05 Center Board Block and Elem Wiring Diagram
2.9. Drawing FSV6-100-01 Centerboard Hoisting Gear Layout and Details
2.10. Drawing FSV6- 801-09 Centerboard Bottom Void Scantlings
2.11. Steel Structures Painting Council, Surface Preparation Specification No. 6 - SSPC-SP6 / NACE 3 Commercial Blast Cleaning
2.12. American Bureau of Shipping, Rules for Building and Classing Steel Vessels
2.13. Contract Item 10105 – Preservation of Underwater Body
2.14. Contract Item 10105 – Freeboard Preservation
3. GOVERNMENT FURNISHED MATERIAL (GFM)
3.1. None
4. REQUIREMENTS
4.1. The contractor shall perform all work in accordance with the requirements of the documents cited in paragraph 2 above.
4.1.1. Contractor shall provide all services, technical expertise, materials, supervision, rigging, crane lifts and parts to accomplish all work called out in this item. Inspection of all components and installation /operation shall be completed under the direction of the OEM representative who are:
National Oilwell Varco, L.P.
Mr.David Drake 10353 Richmond Avenue Houston, Texas 77042 Tel: (346) 223-3753 Fax: (346) 223-3021
Or
Global Technical Services (GTS) Field Service Engineer: Mark Connor 414 232 0412 mark.connor@gts-mc.com
The OEM Centerboard Technical Representative shall inspect the following items, as a minimum, before removal and after testing, and provide a condition report/documentation of results:
a) Trunk guide rails for damage; distortion; cracks; corrosion; loose or missing parts.
b) Eight wear pads and shim as needed to meet specification.
c) Centerboard drive equip for damage; distortion; cracks; corrosion; loose/missing parts.
d) Structural members/welds for damage; distortion; cracks; corrosion; loose/ missing parts.
e) Foundations and supports for continued ability to support the imposed loads.
f) Handrails, stairs, ladders, walkways, and safety guards for damage, distortion, cracks, corrosion, and loose or missing parts.
g) Fasteners for tightness, corrosion, etc.
h) Verify that interior centerboard drain lines are free and unplugged.
i) Pins, bearings, shafts, gears, couplings, rollers, locking and clamping devices (spud, wear pads) for wear, cracks, and distortion, and for excessive noise and vibration.
j) Clean Safety labels for good legibility. Replace all damaged or missing safety labels.
k) Hydraulic power plant for proper performance and compliance with applicable safety requirements.
l) Electrical equipment (control contactors, encoder, limit switches, control panels, etc.) for contact pitting or any deterioration.
m) Hydraulic hoses, fittings, and tubing for: wear, rubbing, or chaffing, evidence of leakage at the surface of the flexible hose or its junction with the end fittings, blistering or abnormal deformation of the outer covering of the hydraulic hose, leakage at threaded or clamped joints that cannot be eliminated by normal tightening or recommended procedure, evidence of excessive abrasion or rubbing on the outer surface of a hose, rigid tube, or fitting.
n) Hydraulic pump and motor for: loose fasteners, leaks at joints between sections, shaft seal leaks, unusual noises or vibration, loss of operating speed, excessive heating of the fluid, loss of pressure
o) Hydraulic valves for: cracks in valve housing, improper return of spool to neutral position, leaks at spools or joints, sticking spools, failure of relief valves to attain correct pressure setting
p) Relief valve pressures as specified on hydraulic drawings
q) Hydraulic cylinders for: drifting caused by fluid leaking across the piston, rod seal(s) leakage, leaks at welded joints, scored, nicked, or dented cylinder rods, dented cylinder barrel, lose or deformed rod eyes or connecting joints
r) PLC program and operation for proper function. Inspect the encoder and all pressure switches for proper function and condition.
s) All electrical cabling and penetrations for wear, rubbing, chaffing and ensure all cable penetrations are properly sealed.
4.2. Transducer and Cabling Removals - Remove all transducers prior to Centerboard removal. Centerboard transducer removal shall consist of the following:
4.2.1. Coordinate lock-out and tag-out of all Transducers with Ship’s Force. Coordinate all work on transducers with the COR and Ships’ Electronics Technician (ET).
4.2.2. Inspect transducer mounting rings. Clean each transducer face using a normal, mild, synthetic soap, water and a soft bristle brush. Photograph each transducer and submit a report to the COR. Photos should provide sufficient detail to clearly see each transducer’s surface. Report shall include transducer name, location, and current condition.
****CHECK POINT****
4.2.3. After all transducers on the Centerboard have been tagged-out, disconnect, remove all Centerboard transducer cabling. Note - in most cases, transducers and cabling must be removed and reinstalled as a unit. Provide and install permanent self-laminating cable labels to both ends of each cable before removing the cables. Transducer cabling is terminated in the Scientific Equipment room located in the Dry laboratory and in the main deck passageway at frame 46. All cabling must be disconnected and pulled back to each Transducer. Ships ET will disconnect all transducers form equipment at this location.
****CHECK POINT****
4.2.4. Once disconnected from equipment in the Scientific Equipment room and frame 46, pull back all cabling through the multi-cable transit penetration in the Scientific Equipment Room, frame 46, Centerboard Roxtec Box, and cable penetrations within the Centerboard. Caution – it is imperative that labels do not detach. Place protective covering over ends of cable before pulling Transducers that must be removed from the Centerboard per reference 2.6 include:
Scientific Sonar (18 KHZ) Scientific Sonar (333 KHZ) Scientific Sonar (38 KHZ) Scientific Sonar (70 KHZ) Scientific Sonar (200 KHZ) Scientific Sonar (120 KHZ) Scientific Sonar (MS 70) Self Noise Hydrophone Acoustic Net Mensuration (2 units)
Acoustic Release
4.2.5. Carefully inspect each transducer and all cables for evidence of cracks, scrapes, blistering, corrosion or other abnormalities that would indicate an unsound unit. Notify COR immediately should any of these conditions be found.
****CHECK POINT****
4.2.6. Provide and install a protective cover for the face of each transducer.
4.2.7. Unbolt and remove all transducers, including their associated cabling. Clean each transducer bac/sides/and cabling completely using a normal, mild, synthetic soap, water and a soft bristle brush.
Carefully wrap and place the transducers on a pallet and transport to a secure climate-controlled storage facility approved by the COR.
****CHECK POINT****
4.3. Centerboard Removal
4.3.1. Temporarily remove all obstructions in the Pilot House and 04 Level required for Centerboard removal including the APC UPS, chart tables, etc. in the Pilot House, and bolted awning frames on the 04 Level.
4.3.2. Cover and protect bridge all equipment at the 03 Level as well as radars, antennas, and other equipment on the 04 Level from any damage throughout all work associated with this item.
4.3.3. Remove the Centerboard bolted equipment removal plates (BERPS) in the Pilot House and 04 Level Decks for equipment removal and installation. The 04 Level BERP shall be reinstalled immediately after Centerboard component removal/installation for protection from the weather. Ensure seal is watertight to protect bridge equipment from damage. The 04 Level BERP shall only be removed when there is no chance of rain as determined by the National Weather Service.
4.3.4. Provide and install temporary safety handrails/chains around the 03 and 04 level BERPs while the BERPs are removed and while being removed. There are six M24x3x36mm deck sockets around each BERP intended for temporary stanchions. Provide stanchions and lifelines. Stanchion bases shall screw into the existing sockets.
4.3.5. Uncouple all hydraulic hoses from fixed pipes and cap them to prevent contamination. Remove hoses from the centerboard. Label fixed pipes so that the new hoses may be reinstalled in the correct orientation. It is imperative that the new hoses are installed in the correct orientation or the Centerboard will not operate properly. Cap all hose, pipe, and equipment fittings to prevent contamination infiltration.
4.3.6. Cut the weld holding the Flexible Hose Tray to the Centerboard and unbolt the Flexible Hose Tray from the Centerboard and Centerboard Trunk. Remove the Flexible Hose Tray from the ship for inspection & servicing.
4.3.7. After approval from COR and a confirmed clear weather forecast (less than 10% chance of precipitation) as shown by the National Weather Service for a period of at least 12 hours, open the BERP in the top and deck of the Pilot House and lift the Centerboard up and out of the ship.
****CHECK POINT****
4.3.8. Support the Centerboard and lay down for maintenance, preservation, and repairs. Remove the Centerboard Gearbox from the Centerboard for inspection and preservation.
4.4. Centerboard Maintenance
4.4.1. Open, gas-free, and certify the Centerboard for hot work.
4.4.2. Disassemble all components (guide/spud assemblies, hydraulic motor, cylinders, pinion gear box & brake, wear pads, etc.) for inspection/cleaning and paint preparation. Replace all hydraulic cylinder seals and gear box seals.
4.4.3. Sandblast the centerboard exterior, including the lower flooded void, all components and manhole covers per reference 2.11. to SSPC 6. Protect and cover all equipment and hardware that should not be blasted.
****CHECK POINT****
4.4.4. Provide visual inspection and nondestructive testing of the lifting links, pins, spud sliding assembly, gear box mounting plate, and pad eyes on the centerboard and the centerboard drive assembly.
Provide pull testing for each pad eye on the centerboard and the drive assembly. Each pad eye shall be tested to 11 tons.
4.4.5. Remove the existing ROXTEX boxes on the centerboard and replace with new CRSS 316 units of the same size.
4.4.6. Recoat the centerboard exterior and flooded void following the paint schedule per reference 2.13 Preservation of Underwater Body. Recoat the Centerboard Drive Assembly in accordance with reference 2.14 Freeboard Preservation. Protect and cover all equipment and hardware that should not be painted
****CHECK POINT****
4.4.7. Perform paint repairs and touch-ups to the internal of the Centerboard (“Dry void”). Machine power tool areas of corrosion to SSPC-15)and recoat in accordance with reference 3.14 Freeboard Preservation.
For estimating purposes, Contractor shall estimate 50 square feet in non-contiguous areas of surface preparation and paint repairs. Upon spot repairs apply a “maintenance coat” to the complete interior of the Centerboard.
****CHECK POINT****
4.4.8. Install centerboard man-hole covers upon completion of Centerboard repairs with new gaskets. Install a new chain to secure each man-hole cover to the Centerboard.
4.4.9. Replace all of the wear pads in the Centerboard trunk.
4.4.10. Inspect and replace all proximity sensor targets for each Centerboard position. Replace the sensors and sensor targets so that the Centerboard will be properly positioned upon demand. The proximity sensor targets are possibly bent and the sensors are not making contact within the position sensor range. Repair and paint targets and submit a condition report if sensors must be replaced.
4.5. Centerboard Trunk Maintenance
4.5.1. Remove the existing ROXTEX boxes on the centerboard trunk bulkheads that feed the Scientific Equipment room and passage way and replace with new CRSS 316 units of the same size.
4.5.2. Machine power tool areas of corrosion to SSPC-15 and recoat in accordance with reference 3.14 Freeboard Preservation. For estimating purposes, Contractor shall estimate 150 square feet in non-contiguous areas of surface preparation and paint repairs. Upon spot repairs apply a “maintenance coat” to the complete interior of the Centerboard.
****CHECK POINT****
4.5.3. Disassemble and inspect the centerboard trunk watertight doors on the 2nd deck. Provide and install new door gasket, inspect knife edge, and disassemble and inspect all dogs. Reassemble door and properly adjust dogs. Hose test for COR and ABS
****CHECK POINT****
4.6. Flexible Hose Tray Repairs - Clean and inspect the Flexible Hose Tray and provide a condition report.
Replace all C-clips on the Flexible Hose Tray with new 316 stainless steel clips. Replace all corroded fasteners with new material that is CRSS 316.
4.6.1. Purchase or fabricate an extension section attachable to the trays side to allow for the placement of 8 hydraulic hoses. Materials shall be the same as the existing tray and materials placement shall be approved by the COR.
4.6.2. After the flexible hose tray has been removed from the ship, replace the hose tray end links that connect the hose tray to the Centerboard and to the aft bulkhead. Existing hose tray end links are Gleason Part Number GR04777801LH. Modify and strengthen the link connecting the flexible hose tray to the centerboard by adding a stringer between the link fingers or other suitable means to strengthen the link as approved by the COR.
4.6.3. Install a 5/8” steel doubler plate welded to the centerboard to stiffen the foundation for the hose tray end link at Centerboard connection or provide alternate means to strengthen the hose tray foundation as approved by the COR.
4.7. Centerboard Installation:
4.7.1. Complete all painting of the centerboard trunk and centerboard.
****CHECK POINT****
4.7.2. Clean, preserve, and lubricate the spud pockets and rack on the STBD bulkhead of the Centerboard trunk for each Centerboard position. Provide and install EAL grease on centerboard rack and pinion gears
4.7.3. Reassemble all components (guide/spud assemblies, hydraulic motor, cylinders, pinion gear box & brake, wear pads, etc.) for that were removed for painting and inspections.
4.7.4. After approval from COR and a confirmed clear weather forecast (less than 10% chance of precipitation) as shown by the National Weather Service for a period of at least 12 hours, open the BERP in the overhead and deck of the Pilot House and reinstall the Centerboard. Secure the Centerboard within the trunk and lock into place. Verify proper gearbox installation with the guidance of the Centerboard Technical Representative.
****CHECK POINT****
4.7.5. Close the Pilot House overhead BERP directly after Centerboard installation. Install new gaskets and seal BERPs for watertight integrity. Protect bridge equipment as necessary and test the overhead BERP in the Pilot House using 50 PSI water to verify water-tightness. Certify BERP watertight integrity for a minimum of 12 months after installation.
4.7.6. Reinstall all removed obstructions in the Pilot House.
4.8. Flexible Hose Tray Installation - After the centerboard has been re-installed within the centerboard trunk, connect the flexible hose tray to the doubler plate foundation using 5/8” 316L stainless steel bolts. Install isolation sleeves between dissimilar metals.
4.8.1. Connect the Flexible Hose Tray link to the Aft Centerboard Trunk using new hardware.
4.8.2. Install hydraulic hoses. Contractor shall replenish all discarded oil with compatible EAL oil to match existing.
4.9. Transducer Installation - Coordinate with the COR, Ships’ ET to reinstall all Centerboard transducers.
4.9.1. Ensure transducers and cabling is clean and shows no signs of external damage. Reinstall the transducers and original cables with new gaskets and route the cables through the existing Roxtec openings and flexible hose tray to their appropriate deck units or terminations. Maintain the minimum bend radius of not less than 135 degrees between the cable retraction system and the top of the centerboard to avoid unnecessary stress on heavy gauge cable. Pack all Roxtec transits on the Centerboard, and in the Centerboard trunk with new blocks and CRSS 316 components.
4.9.2. Secure the cables and hoses in the flexible hose tray and at the transition from the flexible hose tray to the top of the Centerboard. Bundle and secure cables at the top of the Centerboard and inside the transducer compartment.
4.9.3. Ensure cables will not be damaged or stressed when the centerboard is raised and lowered.
Demonstrate that transducer cable length and routing are adequate by cycling the centerboard through all positions. Ships’ ET and COR shall inspect transducer installation. Contractor shall work with ET to verify transducer operation, proper installation and cable routing, and that no damage has occurred
****CHECKPONT****
4.9.4. Follow ship’s lock-out/tag-out procedures to re-energize all electrical power serving the Centerboard.
Do not re-energize any equipment serving any transducers as damage will occur if transducers are active and not in the water.
4.10. Testing - Centerboard testing shall consist of the following and be done under the guidance of the Centerboard Technical Representative. Full testing shall be accomplished when the ship is in the water.
4.10.1. Demonstrate operate the centerboard from the local control stations in the automatic and manual mode. Verify correct calibration and operations at all positions. All Centerboard position indicator lamps shall indicate same centerboard positions
4.10.2. Demonstrate operation of the Centerboard in “Auto” mode from the Bridge control station. All Centerboard position indicator lamps shall indicate same centerboard positions.
4.10.3. Once the ship has been placed back in the water, notify COR that the transducers are ready for testing. Ship’s Force ET and Survey Tech will calibrate all transducers and verify operation. Assist Ships’ Force ET and Survey Tech during the calibration as needed
4.10.4. Verify that all centerboard repairs are leak free.
4.10.5. Upon completion of testing, rectify all failures, damages, or broken equipment that is found to be attributed to the Centerboard overhaul.
5 QUALITY ASSURANCE:
5.1 Submit a written report(s) of the results of the inspections and testing required by this item. The report(s) must contain the date, time, results, and names of the witnesses.
None
Item No. 10105 Title: Preservation of Underwater Body
1.1 Objective: To remove the existing coating system and re-coat the underwater body of the ship from the keel to the boot-top.
2.3 Steel Structures Painting Council, Surface Preparation Specification No. 6 - SSPC-SP6 / NACE 3
Commercial Blast Cleaning
2.4 Steel Structures Painting Council, Surface Preparation Specification No. 7 - SSPC-SP7 / NACE 4
Brush-Off Blast Cleaning
2.5 Steel Structures Painting Council, Surface Preparation Specification No. 12 - SSPC-S12 / NACE 5 High and Ultra High-Pressure Water Jetting UHP - WJ2
4.1.1 The contractor shall perform all work in accordance with the requirements of the documents cited in
4.1.2 During abrasive blast cleaning, all openings to the interior of the ship must be sealed to prevent contamination.
4.1.3 Rudders, rope guards, shaft tubes, sea chest, centerboard, dunce cap, and trunk shall receive the same preparation and coating as the rest of the underwater body. Sea chest gratings shall be removed and both they and the sea chest shall be prepared and coated the same as the rest of the underwater body.
4.1.4 Bow thruster gratings shall be removed and both they and the bow thruster sea chest and discharge shall be prepared and coated the same as the rest of the underwater body.
4.1.5 Remove all zinc anodes. Anodes not removed shall be protected from abrasive blast cleaning and from paint.
4.1.6 All transducers shall be protected from abrasive blast/UHP cleaning and from paint.
4.1.7 Cathodes located in each sea chest and bow thruster trunk, shall be protected from abrasive blast cleaning and from paint.
4.1.8 All welding on the hull must be completed prior to application of any paint.
4.1.9 All surface preparation and paint application must be performed and inspected under the supervision of an authorized PPG manufacturer's representative following recommended procedures.
4.2 Verify marks
4.2.1 Verify the punch marks or weld beads of the plymsoll marks and the draft marks. If marks cannot be found, install new marks. If new marks are required, they must be welded bead.
4.2.2 Verify the punch marks or welded beads that define the boot-top, frame, and bow thruster.
markings. If marks cannot be found, install new marks. If new marks are required, they must be welded bead.
4.3 Surface Preparation
4.3.1 Perform a high pressure fresh water wash of the entire underwater body including the centerboard and trunk, sea chest intakes and intake piping to the strainer baskets, and boot-top to remove and slime, fouling, and contaminants from the anti fouling (AF) paint remaining on the hull.
4.3.2 Perform Brush-Off Blast Cleaning (SSPC-7) to remove all AF paint from the boot stripe and to areas where anti corrosion (AC) paint is exposed. of the complete underwater body from 2ft above the boot-top to the keel in accordance with reference 2.4.
4.3.3 Perform Commercial Blast Cleaning per references 2.3 and/or 2.5 of areas of the hull where the AC paint has failed in accordance with reference 2.3. The coating system can be expected to have failed and/or need touch-up at prior blocking positions on approximately 10% of the underwater body.
4.3.4 After AF paint removal, measure and record the DFT of the remaining paint in 50 locations. Map these locations so that final DFT readings are in the same locations. Submit a written report to the COR of all DFT readings.
***** CHECKPOINT *****
4.3.5 Test the surface for chloride contamination in accordance with standard NV-2 using Chloride Chemical Test Strips in at least 20 random locations. If chloride level is above 7μg/cm², wash prepared areas with low pressure, 1200 PSI water. HoldTight102 Flash Rust Inhibitor/Salt Remover (or equal) shall be used at the manufacturer’s recommended level. Retest the prepared areas in accordance with
NV-2.
4.4 Painting Anti Corrosive (AC) - Apply AC coatings to the hull areas prepared in 4.3 as follows:
4.4.1 Apply two coats of…