4. Forest Service Supplemental Specifications - VERSION 2.pdf
PDF 396 KB Posted
- Solicitation number
- 127EAW25R0010
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Forest Service Supplemental Specifications (FSSS) version 2 for the Antelope Fire Roadway Reconditioning project, dated April 17, 2025. The technical specifications provide detailed guidance for roadway reconstruction work, covering multiple aspects of road construction including aggregate courses, road reconditioning, clearing and grubbing, and material requirements. Key technical specifications include requirements for aggregate gradation, compaction methods, surface course composition, and disposal of construction materials, with specific technical standards referenced from AASHTO and other engineering testing methodologies.
The document systematically modifies and updates previous specification sections, deleting or replacing subsections related to bid processes, contract execution, work scope, and measurement standards. Notably, it provides granular technical instructions for aggregate types, including subbase, base, and surface course materials, with precise requirements for particle size, plasticity index, abrasion resistance, and other physical characteristics. The specifications are designed to ensure high-quality road reconstruction work in forest service areas, with a focus on material quality, proper compaction, and environmental considerations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Official Responses - 1.pdf | ||
| A00001 - RFI Official Responses - 1.pdf | ||
| 3. Project Map.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 4. Forest Service Supplemental Specifications.pdf | ||
| 5. Fire Plan.pdf | ||
| 1. Statement of Work.pdf | ||
| 6. Davis-Bacon Act WD # CA20250007.pdf | ||
| 127EAW25R0010 - Antelope Fire Road Reconditioning.pdf | ||
| 2. Schedule.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Antelope Fire Roadway Reconditioning FSSS - Forest Service Supplemental Specifications
April 17, 2025 Version 2
Table of Contents Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04
104.06 Use of Roads by Contractor
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.02 Visual Inspection
107 - Legal Relations and Responsibility to the Public
Delete Subsection 107.05
108 - Prosecution and Progress
Delete Section 108
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09
109.02 Measurement Terms and Definitions
155 - Schedules for Construction Contracts
Delete Section 155
201 - Clearing and Grubbing
201.04(d) Clearing
201.04 Clearing
201.06 Disposal
203 - Removal of Structures and Obstructions
203.04 (b) General
203.05 Disposing of Material
301 - Untreated Aggregate Courses
301.03 General
301.05 Compacting
303 - Road Reconditioning
303.07 Roadway Reconditioning
703 - Aggregate
703.05 (c) Surface course aggregate. (3) Plastic Index
703.05 Subbase, Base, Surface Course, and Screened Aggregate
703.09 Chip Seal Aggregate
Preface Preface_wo_04_17_2025
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest
System Roads.
101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016
Add the following paragraph to Subsection 101.01:
101.01 Meaning of Terms.
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_National_11_9_2016
Add the following to Subsection 101.03:
101.03 Abbreviations.
(a) Acronyms.
AGAR — Agriculture Acquisition Regulations
AFPA — American Forest and Paper Association
FSAR — Forest Service Acquisition Regulations
MSHA — Mine Safety and Health Administration
NESC — National Electrical Safety Code
WCLIB — West Coast Lumber Inspection Bureau
(f) Miscellaneous unit abbreviations.
MP — milepost location ppm — parts per million volume
STA station location
101.04_National_11_9_2016
Make the following changes to Subsection 101.04:
101.04 Definitions.
Delete these definitions and replace the following:
Bid Schedule — The Schedule of Items.
Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.
Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.
Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.
Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.
Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.
Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or
(2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.
Add the following definitions:
Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line — A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road — Temporary construction access built along the route of the project.
Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction.
Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.
Utilization Standards — The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016
Delete Section 102 in its entirety.
Delete Section 102.
103 - Scope of Work 103.00_National_11_9_2016
Delete all of Section 103 except Subsection 103.01 Intent of Contract.
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work 104.00_National_11_9_2016
Delete Subsections 104.01, 104.02, and 104.04.
Delete Subsections 104.01, 104.02, 104.04.
104.06_National_11_9_2016
Add the following to Subsection 104.06:
104.06 Use of Roads by Contractor.
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
106 - Acceptance of Work 106.01_National_7_18_2017
Delete Subsection 106.01 and replace with the following:
106.01 Conformity with Contract Requirements.
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to
106.05 inclusive. The primary method of acceptance is specified in each Section of work.
However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work; providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
Sampling method;
Number of samples;
Sample transport;
Test procedures;
Testing laboratories;
Reporting;
Estimated time and costs; and Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
Have the work accepted at a reduced price; or Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.02_National_11_9_2016
Delete Subsection 106.02 and replace with the following:
106.02 Visual Inspection.
Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.
107 - Legal Relations and Responsibility to the
Public 107.05_National_7_18_2017
Delete Subsection 107.05.
Delete Subsection 107.05.
108 - Prosecution and Progress 108.00_National_11_9_2016
Delete Section 108 in its entirety.
Delete Section 108.
109 - Measurement and Payment 109.00_National_11_9_2016
Delete Subsections 109.06, 109.07, 109.08, and 109.09:
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.02_National_11_9_2016
Add the following sentence to Subsection 109.02(b):
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
155 - Schedules for Construction Contracts 155.00_National_11_9_2016
Delete Section 155 in its entirety.
Delete Section 155.
201 - Clearing and Grubbing 201.04_National_11_8_2016
Delete and replace Subsection 201.04(d) with the following:
201.04(d) Clearing.
(d) Trim tree branches that extend over the road surface and shoulders to attain a clear height of <number> feet. Trim tree limbs as near flush with the trunk as practicable.
201.04_National_11_2_2016
Add the following paragraph to Subsection 201.04:
201.04 Clearing.
(e) Do not cut vegetation less than 3 feet in height and less than 3 inches in diameter that is within the clearing limits but beyond the roadway and not in a decking area and that does not interfere with sight distance along the road unless otherwise designated.
201.06_National_11_2_2016
Delete the first sentence of this Subsection 201.06 and replace the following:
201.06 Disposal.
Dispose of merchantable timber designated for removal according to the provisions of the timber sale contract.
203 - Removal of Structures and Obstructions 203.04_National_11_2_2016
Make the following changes to Subsection 203.04(b):
203.04 (b) General.
Delete the fifth paragraph of Subsection 203.04(b) and replace with the following:
Remove structures and obstructions in the roadbed to 12 inches (300 millimeters) below subgrade elevation. Remove structures and obstructions outside the roadbed to 12 inches (300 millimeters) below finished ground or to the natural stream bottom.
Delete the seventh paragraph of Subsection 203.04(b) and replace with the following:
When abandoning an existing culvert pipe, remove the upstream and downstream portion of the culvert to within 12 inches (300 millimeters) of the subgrade or embankment slope. Ensure the abandoned pipe is at least 48 inches (1200 millimeters) from a new culvert or structure. Seal the abandoned culvert ends with a tight-fitting plug of concrete at least 6 inches (150 millimeters) thick. Ensure the structure does not entrap water.
203.05_National_11_8_2016
Add the following to Subsection 203.05:
203.05 Disposing of Material.
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toe line of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees.
(f) Scattering. Scatter construction slash in designated areas without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations. When scattering for erosion control, place construction slash as flat as practicable on the completed slope.
(g) Chipping. Use an approved chipping machine to chip slash longer than 3 feet. Deposit chips on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking. Remove brush from designated log deck areas. Limb and top logs.
Logs not meeting the Utilization Standards described in Subsection 201.04(c) shall be cut to lengths less than <number> feet and decked in designated log deck location.
Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection 201.04(c).
Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps.
301 - Untreated Aggregate Courses 301.03_National_7_17_2017
Add the following to Subsection 301.03:
301.03 General.
Written approval of the roadbed is required before placing aggregate.
For pit run or grid-rolled material, furnish material smaller than the maximum size, no gradation will be required otherwise. After processing on the road, remove all oversize material from the road and dispose as directed by the CO.
Provide additives or binder, if required, at the proportions specified.
Develop and use Government furnished sources according to Section 105.
If the aggregate is produced and stockpiled before placement, handle and stockpile according to Section 314.
301.05_National_7_17_2017
Delete Subsection 301.05 and replace with the following:
301.05 Compacting.
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
303 - Road Reconditioning 303.07_National_7_18_2017
Add the following to Subsection 303.07:
303.07 Roadway Reconditioning.
Remove cattleguard decks. Clean the deck and the area beneath the cattleguard of soil and other material to the bottom of the original foundation over the entire width of the installation. Dispose of waste at designated sites or according to Subsection 204.14. Reinstall the cattleguard deck.
703 - Aggregate 703.05_National_7_18_2017
Delete Subsection 703.05(c)(3) and Replace with the following:
703.05 (c) Surface course aggregate. (3) Plastic Index
(3) Plastic Index, AASHTO T 90
If the percent passing the No. 200 sieve is less than 12% 2 to 9 If the percent passing the No. 200 sieve is greater than 12% Less than 2
703.05_National_12_15_2016
Delete 703.05 and replace with the following:
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-2
(2) Liquid limit, AASHTO T 89 25 max.
(3) Plastic limit, AASHTO T 90 Nonplastic
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 50% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-3
(2) Liquid limit, AASHTO T 89 35 max.
(3) Plastic Index, AASHTO T 90
a) If the percent passing the No. 200 sieve is less than 12% 2 to 9
b) If the percent passing the No. 200 sieve is greater than 12% Less than 2
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 75% min.
(9) Free from organic matter and lumps or balls of clay
Do not furnish material that contains asbestos fibers.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:
(1) Gradation Table 703-16
(2) Plastic Index, AASHTO T 90 Less than 9
(3) Los Angeles abrasion, AASHTO T 96 55% max.
(4) Free from organic matter and lumps or balls of clay.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
Delete Table 703-2 and replace with the following:
T a b le
-2
T a rg et
V a lu e
R a n g es f o r
S u b b a se a n d B a se
G ra d a ti o n
P er ce n t b y M a ss
P a ss in g D es ig n a te d
S ie v e
(A A
S H
T O
T a n d
T
G ra d in g D es ig n a ti
E
B a se
.0
.0
T h e v al u e in t h e p ar en th es es i s th e al lo w ab le d ev ia ti o fr o m t h e ta rg et v al u es
D
B a
.0
.0
C
B a
.0
.0
B
S u b b a
.0
.0
A
S u b b a se
.0
.0
S ie v e
S iz e
½ i ch i
½ i i
/4 i
/2 i
/8 i
N
Delete Table 703-3 and replace with the following:
Delete Table 703-3 and replace with the following:
Table 703-3
Limits for Surface Course Gradation and Plasticity Index
Sieve Size
Percent by Mass
Passing
Designated Sieve
(AASHTO T 27 & T
11)
1 inch 100
3/4 inch 97 - 100
3/8 inch 68 - 85
No. 4 45 - 64
No. 16 25 - 42
No. 40 16 - 29
No. 200 8-12 12-18
Plasticity index (PI)* 5-9 2-5
If desired, off-site clay soil may be used to meet indicated limits or 2% bentonite* maybe added by weight when there at least 8% No 200 and low or no PI
Add Table 703-13:
Table 703-16
Gradation Requirements for Screened Aggregate
Sieve Size
Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation
L M N O P Q R
6 inch 100 100
4 inch 100 100
3 inch 100 100
2 inch 100
No. 4 15-45 15-45 15-45
703.09_National_7_18_2017
Make the following changes to Subsection 703.09:
703.09 Chip Seal Aggregate.
Delete Subsection 703.09(c) and replace with the following:
(c) Flakiness Index, FLH T 508 30% max.
Add the following to Subsection 703.09:
(g) Adherent coating on the aggregate, FLH T 512
0.5% max.