RFI Official Responses - 2.pdf

PDF 149 KB Posted

Attached to
127EAW22R0028 - Caldor Fire Gates
Solicitation number
127EAW22R0028
Issued by

View the file

Other files

File Type Posted
RFI Official Responses - 3 .pdf PDF
RFI Official Responses - 4.pdf PDF
A00002 - RFIs 3 and 4.pdf PDF
A00001 - RFIs Round 1 and 2.pdf PDF
RFI Official Responses - 1.pdf PDF
Gate Pictures.pdf PDF
7. RFI.docx DOCX document
127EAW22R0028 - Caldor Fire Gates.pdf PDF
5. Gate Locations and Type.pdf PDF
1. Statement of Work.pdf PDF
2. Fire Plan.pdf PDF
4. Drawings and Maps.pdf PDF
6. Davis-Bacon Act WD # CA20210007.pdf PDF
3. Schedule.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

REQUEST FOR INFORMATION (RFI) OFFICIAL RESPONSES

127EAW22R0028 - Caldor Fire Gates

RFI responses will be responded to as necessary in amendment format which will be posted to the solicitation via beta.SAM.gov

Telephone requests for information will not be accepted or returned.

RFI #1 – Are all the gate locations accessible now-no downed trees in the way?

USFS Response – Yes

RFI #2 – Are any locations behind a locked gate and if so can we have a key to look at the sites?

USFS Response – No location is behind a locked gate

RFI #3 – Are the exact gate locations flagged or do we need to use GPS coordinates-which can be off by 100’ or more?

USFS Response – Intent is to field fit final location with COR prior to installation. Coordinates and map markers provide general locations. Gates will be placed in the best location for intent and installation

RFI #4 – Clarifying-the contract goes for one year from NTP?

USFS Response – Work should not take more than 6 months. One year includes work stoppage time due to weather.