RFIs and Responses 2.docx

DOCX document 26 KB Posted

Attached to
Building 62 Renovation, Coral Gables Federal contract opportunity
Solicitation number
12639524R0020
Issued by
Department of Agriculture Animal and Plant Health Inspection Service Marketing and Regulatory Programs Business Services

About this file

This document contains Requests for Information (RFIs) and responses related to Solicitation 12639524R0020 for the renovation of Building 62 in Coral Gables. The key details are:

The contractor is responsible for furnishing and installing the Uninterruptible Power Supply (UPS). The CO2 line is part of the project and must be installed as shown. The government will be responsible for finalizing the contract with a monitoring service for the fire alarm system, which requires a Digital Alarm Communication Transmitter (DACT). The contractor does not need to furnish and install the compressed gas cylinders, but the compressed gas piping must be run overhead above the ceiling. The contractor is responsible for installing junction boxes and conduit for the access control system, but the cabling and equipment will be done by others.

View the file

Other files for this federal contract opportunity

Other files attached to Building 62 Renovation, Coral Gables, newest first.
File Type Posted
12639524R0020-0004.pdf PDF
12639524R0020-0003.pdf PDF
12639524R0020-0002.pdf PDF
Building 62 Asbestos Final Report 07302017.pdf PDF
12639524R0020-0001.pdf PDF
RFIs and responses.docx DOCX document
20240422_184353638_iOS.jpg JPG image
20240422_184332471_iOS.jpg JPG image
20240422_184140685_iOS.jpg JPG image
20240422_183955449_iOS.jpg JPG image
20240422_184244122_iOS.jpg JPG image
20240422_184002492_iOS.jpg JPG image
20240422_184000455_iOS.jpg JPG image
20240422_184119221_iOS.jpg JPG image
20240422_184050336_iOS.jpg JPG image
Atch 4_Federal Construction Wage Rates_Miami-Dade.pdf PDF
Atch 3_bldg 62 drawings.pdf PDF
Atch 2_Bldg 62 specifications.pdf PDF
Atch 1_SOW Coral Gable Bldg 62 construction 5-8-24.docx DOCX document
12639524R0020.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFIs, 12639524R0020

1. Is the contractor responsible for furnishing and installation of the UPS?

Yes

1. Page PP102 (29/54), does the CO2 line have to be deleted from the design?

CO2 is a part of this project. Must be installed as shown on contract documents.

1. What are the requirements for fire alarm monitoring post-installation of the alarm panel? Can the subcontractor who installs the fire panel provide a quote for alarm monitoring?

No. Riser diagram indicates system connection to a (wireless) Digital Alarm Communication Transmitter (DACT). Government will be responsible for finalizing contract with a monitoring service and providing contractor with appropriate information to allow final coordination and testing.

1. Does the contract need to furnish and install the compressed gas cylinders as part of the SOW?

No. Generally, the Government has a separate contract for the gas cylinders.

1. Should the compressed gas piping be ran overhead above the ACT or below finished floor?

All compressed gas must be run overhead above ceiling with access provided to all valves in the system. Refer to riser diagram D4 on sheet P-701 per riser designation #1 on sheet PP102 (see Lab Gas Riser Designation symbol on sheet P-001).

1. Can USDA confirm that the wiring, equipment, and commissioning of access control systems and low voltage systems (Cameras, telephone, CAT 5/6) will be done by others?

Contractor is to install junction boxes and conduit for access control system as per drawing ET 501. Cabling and equipment is by others. Telecommunications details are shown on drawings. USDA to determine if this is in bidder's scope.

File details come from the government source that posted it. Updated .