About this file
This document contains a federal contract opportunity for Caldor Suppression Repair and GAOA John Don't projects. The projects involve furnishing labor, materials, equipment and supplies to complete suppression repairs after the Caldor Fire and within the John Don't project area. Work on the Caldor project includes restoring drainage functions, cleaning ditches and culverts, spot surfacing, asphalt repairs, chip sealing, fog sealing, asphalt overlay and striping. Work on the John Don't project includes reconditioning roads, cleaning ditches and culverts, constructing water bars and rolling dips, spot surfacing, and asphalt repairs. The location is provided for both projects. Contractors must furnish all requirements in compliance with the contract by June 2023. The solicitation number is 12363N23R4006. The opportunity type is pre-solicitation. NAICS code is 237310 with a $45 million size standard. This project is 100% set aside for small business. The agency is the Department of Agriculture Forest Service.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
813 SPOT SURFACING 1
813 SPOT SURFACING (5/97)
1. DESCRIPTION
This work consists of placing surface aggregate as staked on the ground, or designated by the Government. It includes preparing the area, furnishing, hauling, and placing all necessary materials and other work necessary to blend with the adjacent road cross section.
2. MATERIALS
a. Materials will be Government furnished when stated in Special Project Specifications.
b. Materials furnished by the Contractor shall conform to the gradation requirements shown in the Special Project Specifications and the quality requirements of Section 893.
3. MAINTENANCE REQUIREMENTS
a. The area to be spot surfaced shall be thoroughly loosened to a minimum depth of one inch (1") prior to placement of aggregate.
4. MIXING AND PLACING
a. When scheduled coincident with work under Section 811, spot surfacing and existing aggregate, when ordered, shall be mixed with water until a uniform mixture is obtained prior to final shaping and compaction.
b. The material shall otherwise be spread on the prepared area in layers no more than four (4) inches in depth. When more than one (1) layer is required, each layer shall be shaped and compacted before the succeeding layer is placed. Upon completion, the spot surfacing shall reasonably conform to the adjacent cross section and provide smooth transitions in the road profile.
c. Compaction shall be accomplished by breaking track while operating equipment on the traveled way
5. MEASUREMENT
a. The quantity will be the number of cubic yards measured in the vehicles, or square yards of aggregate placed, whichever is shown in the Schedule of Items.
813 SPOT SURFACING 2
b. Hauling is considered incidental.
6. PAYMENT
a. The accepted quantities will be paid for at the contract unit prices shown in the Schedule of Items
b. Payment will be made under:
Pay Item Description Pay Unit
813 (1) Spot Surfacing, Grading Cubic Yard
813 (2) Spot Surfacing, Grading Square Yard
File details come from the government source that posted it. Updated .