Atch_2_-_Statement_of_Work_Prefab_Metal_Bldg.pdf

PDF 19 KB Posted

Attached to
Install Government Metal Building and Slab Work
Solicitation number
1232SC18R0017
Issued by

About this file

Statement of Work

View the file

Other files

File Type Posted
R12.pdf PDF
ss_E3.pdf PDF
R8.pdf PDF
ss_E4.pdf PDF
R10.pdf PDF
ss_E6.pdf PDF
1232SC18R0017_Amendment_0001.pdf PDF
R1.pdf PDF
ss_E9.pdf PDF
R5.pdf PDF
R4.pdf PDF
R11.pdf PDF
R2.pdf PDF
ss_E1.pdf PDF
R13.pdf PDF
ss_E10.pdf PDF
ss_E7.pdf PDF
R3.pdf PDF
ss_E8.pdf PDF
ss_E5.pdf PDF
ss_E2.pdf PDF
R7.pdf PDF
R9.pdf PDF
ss_F1.pdf PDF
R6.pdf PDF
Stamped_DuroBeam_217-38_Calcs_2018-03-16.pdf PDF
Solicitation_1232SC18R0017.pdf PDF
Stamped_DuroBeam_217-38_60x80_fndt_2018-3-16.pdf PDF
Atch_1_-_DOL_Wage_Determination,_OH82,_Mod_8,_dated_6-15-2018.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATRU Farm Storage Facility

2625 Selby Rd.

Wooster, OH 44691

08 May 2018

Statement of Work:

1. The Project generally consists of the site work; concrete; and installation of a Government Furnished pre-fabricated metal facility. The Government (Owner) will evaluate the proposals based on lowest price technically acceptable (LPTA).

2. Project Location: 2625 Selby Rd. Wooster, OH 44691.

3. Point of Contact at Location: Jim Hampton (330-263-3774).

4. The Contractor shall furnish all labor, materials, equipment, supplies, transportation, utilities, supervision, bonds, insurance, permits, and incidentals for all elements of the Work.

5. Contractor shall coordinate all work activities with the Location Point of Contact prior to beginning any work. All work shall be scheduled in a manner such that on-going research is not impacted negatively.

6. Period of performance: 90 business days. All submittals must be received and returned as approved to the Contractor prior to the commencement of work.

7. Existing Conditions/Demolition:

a. Conduct geotechnical investigation to affirm the minimum bearing capacity is 1500psf.

b. Survey existing site contours. Contractor shall submit a site plan identifying new contours to facilitate site drainage away from the foundation.

8. New Work:

a. Provide and install foundation per DuroBeam Steel Building drawings.

b. Install Government Furnished Steel Building per DuroBeam drawings.

c. Grade site per approved site plan. Seed and water.

d. Contract an independent consultant to perform Quality Assurance/Quality Control. QA/AC consultant shall inspect the following. Reference Sheet 1, Section E inspection:

i. Foundation excavation

ii. Reinforcement placement, prior to closing the forms and deliver of concrete

iii. Concrete placement

iv. Bolts installed in concrete, prior to and during placement of concrete around bolts

v. Epoxy filled anchor bolts

vi. Structural steel

vii. Field welding

viii. Bolts installed in concrete, prior to and during the placement of concrete and around bolts

ix. High-strength bolting

x. During preparation and taking of test specimens

e. Contractor shall purchase and use Pocket Forms (RD3 or equal).

Contractor shall complete and submit the Daily Report to the Engineering Project Manager daily.

9. All work must conform to ARS Standards as well as local and state requirements.

In the event of a conflict, the stricter standard or code shall prevail.

http://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf

10. Provide product data submittals for approval for all products that will be used on

Project, including, but not limited to, the following:

Site Grading Plan Concrete mix design Test results

11. All bidders are strongly encouraged to visit the site of the proposed work and fully acquaint themselves with the existing conditions. However, failure to visit the site will not disqualify offeror.

http://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf