amendment_001_.pdf
PDF 248 KB Posted
- Attached to
- Raven’s Roost Cabin Construction Federal contract opportunity
- Solicitation number
- 12010920R0004
About this file
This amendment modifies a solicitation for the Raven's Roost Cabin Reconstruction project. The base bid work includes providing stamped drawings for a single-story 16'x20' cabin from provided drawings, construction of the cabin and associated covered deck and porch, and related site work including new trail construction with aggregate surfacing, concrete steps, and a metal staircase. Optional items include demolition of an existing cabin and outhouse with site rehabilitation, and supplying and installing furnishings, a site identification sign, and a propane heating system at the new cabin site. The project locations are provided, and work must be completed by November 1, 2020. The amendment extends the due date for responses to September 14, 2020 and adds existing drawings, questions and answers from a pre-proposal conference, additional clauses and certifications, revised specifications and drawings, and an updated design narrative.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Question Post FBO.docx | DOCX document | |
| amendment_002_.pdf | ||
| Revised 17 sideElevs.pdf | ||
| 00_AllDwgs_RRCabin_L T_09022020.pdf | ||
| Preproposal Meeting Notes 8.27.2020 Q A.pdf | ||
| Representations and Certifications.docx | DOCX document | |
| Revised Section B C and Special Project Specifications.pdf | ||
| Ravens Roost Cabin_trail log_09012020updated.pdf | ||
| Existing 1980 Ravens Roost Cabin Constr Dwgs.pdf | ||
| Updated Design Narrative_RRCabin_L T_09012020.pdf | ||
| Design Narrative.docx | DOCX document | |
| Wage Determination AK20200001 June 2020.pdf | ||
| RRCabinAllDwgs95percent.pdf | ||
| 12010920R0004 Ravens Roost Cabin final.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/ MODIFICATION OF
CONTRACT
1 1
2. AMENDMENT/MODIFICATION
NO.
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
01 Sept 2, 2020
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
Contracting Officer USDA, Forest Service P.O. Box 21628 Juneau, AK 99802-1628
Contracting Officer USDA, Forest Service P.O. Box 21628 Juneau, AK 99802-1628
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
X 12010920R0004
9B. DATED (SEE ITEM 11)
Jan 31, 2020
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour & date specified for receipt of Offers X is extended, is not ex-tended
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, & returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH ARE MADE IN ACCORDANCE WITH THE
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT:
Contractor is not, X is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
Raven’s Roost Cabin Reconstruction 12010920R0004 The purpose of amendment 01 is to add:
1. Existing drawings for the 1980 cabin 2. Questions and answers from the pre-proposal conference Aug 27, 2020
3. Add FAR 52.204-24 to Section K Resprentation and Certifications 4. Revised Section B, C & Special Project Specifications
5. Revised Drawings 6. Updated Design Narrative
7. Trail Log Extended due date Sept 14, 2020 12:00 pm AST
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) DELLA KOELLING, Contracting Officer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE FAR (48 CFR) 53.243 Prescribed by GSA
File details come from the government source that posted it. Updated .