About this file
This is a Bid form for the Jordan Basin Improvement District's 13400 South Mountain View Corridor Sewer Project located in Utah. The project encompasses installation of gravity sanitary sewer infrastructure, including 15-inch and 8-inch PVC gravity sanitary sewer pipe, trenchless installation of 36-inch steel casing pipe with carrier pipe beneath Mountain View Corridor (State Route 85) and 13400 South, excavation and construction of launch, retrieval, and intermediate shafts, installation of new 60-inch diameter sanitary sewer manholes, connections to existing sanitary sewer systems, abandonment and removal of existing infrastructure, and surface restoration including pavement, curb and gutter, sidewalk, and striping. Bidders must have been prequalified for the Multiple Mountain View Corridor Sewer Projects to be eligible. The contract includes work within UDOT Region 2 right-of-way, traffic control, and sanitary sewer bypass pumping as required. Work must commence within ten days after the Notice to Proceed is issued, with Substantial Completion and Final Completion required within the Contract Time specified in the Agreement. Bidders must acknowledge receipt of any addenda and certify that bids were prepared independently without consultation with competitors.
The bid submission requires bidders to execute a Bid Schedule, provide a Bid Bond, submit the Information Required of Bidder, and include all other documents mandated by the Bidding Documents. The bid is valid and binding for sixty days after the opening of bids, or a longer period as specified in the Invitation to Bid, unless mutually extended by bidder and owner. Bidders agree to pay liquidated damages as specified in Article 4 of the Agreement for failure to achieve Substantial Completion within the Contract Time. The Jordan Basin Improvement District reserves the right to reject any and all bids for any reason. Specific pricing information, funding sources, and award dates are not included in this bid form document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JORDAN BASIN IMPROVEMENT DISTRICT BID (STD)
13400 S MVC SEWER PROJECT PAGE 00300-1
SECTION 00300
BID
Proposal of
_____________________________________________________________________ (Bidder), organized and existing under the laws of the State of ______________ doing business as
*(Insert “a corporation”, “a partnership”, “a limited liability company” or “an individual” as applicable).
To the JORDAN BASIN IMPROVEMENT DISTRICT (OWNER):
Bidder hereby proposes to complete all of the Work in accordance with the Contract Documents for the 13400 S MVC SEWER PROJECT and to accept as full payment therefor the total Bid Price indicated in the Bid Schedule which is incorporated herein by this reference.
Bidder acknowledges that Bidder has received and reviewed the following Addenda:
Addendum No. Addendum Date
By submission of this Bid, Bidder certifies, and in the case of a joint Bid each party thereto certifies as to its own organization, that this Bid has been arrived at independently, without consultation, communication, or agreement as to any matter relating to this Bid with any other Bidders or with any competitor.
If awarded the contract, Bidder hereby agrees to enter into the Agreement with Owner included in the Bidding Documents, to commence the Work within ten (10) days after the Commencement Date to be specified in the Notice to Proceed, and to achieve Substantial Completion of the entire Work and Final Completion of the entire Work within the Contract Time specified in Article 4 of the Agreement. Bidder further agrees to pay liquidated damages to the Owner in the amount specified in Article 4 of the Agreement for failure to achieve Substantial Completion of the entire Work within the Contract Time, as provided in Article 4 of the Agreement.
By its submission of this Bid, Bidder agrees that the Bid is valid and binding for a period of sixty
(60) days after the date of the opening of Bids or such longer period of time as may be specified in the Invitation to Bid for Bidder’s guarantee of the Bid provided, however, Bidder and Owner may by mutual agreement extend these times. Subject to very limited exceptions stated in the Bidding Documents, this Bid may not by modified or withdrawn by Bidder during that sixty (60) day period, or such longer period of time as is specified in the Invitation to Bid or in an agreement of the Bidder and the Owner.
JORDAN BASIN IMPROVEMENT DISTRICT BID (STD)
13400 S MVC SEWER PROJECT PAGE 00300-2
By its submission of this Bid, Bidder agrees that the right is reserved by Owner to reject any and all Bids for any reason.
Dated:
Bidder:
Signature
Title:
Important: Bidder must submit with this Bid, the Bid Schedule, Information Required of Bidder, Bid Bond and all other documents and information which may be required by the Bidding Documents to be submitted with the Bidder’s Bid.
File details come from the government source that posted it. Updated .