1.5b_SOV_BidForm-NWBPhase2.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
Norway Beach Sewer System Replacement Federal contract opportunity
Solicitation number
12639220R0004
Issued by
Department of Agriculture Forest Service R9-Eastern Region

About this file

This document contains a bid form and schedule of values for the Norway Beach Sewer System Replacement project. The project consists of constructing individual sanitary sewer systems to replace an existing combined sewer treatment plant at the Norway Beach Recreation Area campground loops and Visitor Information Center. Work includes installing septic tanks, pump stations, gravity sewer lines, force mains, electrical controls, drain fields, site restoration and staff training at the Visitor Center, Norway Beach West and East loops, Chippewa West and East loops, and optionally at the Wanaki campground loops. Bidders are required to provide unit pricing for each line item covering general requirements, work at each site, and optional primary electrical improvements. The related federal contract opportunity posted by the USDA Forest Service, Eastern Region solicits bids for this Norway Beach Sewer System Replacement Project.

View the file

Other files for this federal contract opportunity

Other files attached to Norway Beach Sewer System Replacement, newest first.
File Type Posted
ConstructionRFP_FAC2020_04_01152020.docx DOCX document
1.5a_Section B-ScheduleofItems.doc DOC document
2.2a_SpecificationAddendum-NorwayPhase2.pdf PDF
1.4_STATEMENT OF WORK.docx DOCX document
2.2_Specivications-Coversheet.pdf PDF
2.1_Drawings-SignedCoversheet.pdf PDF
2.2_Specifications-NorwayPhase2.pdf PDF
2.1_Drawings-NorwayPhase2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Norway Beach Recreation Area Reconstruction - Phase 2: Sanitary Sewer System Replacement
Bid Form - Schedule of Values (SOV)

Instructions: - Enter all fields highlighted in YELLOW.

- Form computation is thought to be accurate, but Offerors shall perform their own check for accuracy.

- Enter any notes in the fields at the bottom of the form

Offeror:
Tax ID:
Item NumberWork Item DescriptionQTYUnit of MeasureItem
Unit PriceItem

Total Price

ITEM 1: DIVISION 1 - GENERAL REQUIREMENTS
1.01GEN - Mobilization1LS$0.00
1.02GEN -Construction Surveying and Staking1LS$0.00
1.03GEN -Contractor Sampling and Testing1LS$0.00
1.04GEN -Temporary Erosion Control (silt barrier)1LS$0.00
1.05GEN -Temporary Facilities and Traffic Control1LS$0.00
1.06GEN - Closeout Procedures - Includes Record Drawings Submittal, O&M Manuals, Materials Submittals, and Final Cleaning.1LS$0.00
1TOTALS FOR ITEM NUMBER 11LS$0.00
ITEM 2: VISITOR INFORMATION CENTER (VIC) PROJECT AREA
2.01VIC - Salvage and re-install log rail barrier.1LS$0.00
2.02VIC - Removals including front entry wood stoop, concrete sidewalk, sanitary manhole #5 and CIP sewer pipe.1LS$0.00
2.03VIC - Furnish and Install 3,000 gallon concrete septic holding tank.1LS$0.00
2.04VIC - Construct 4" Dia. Schedule 40 PVC sanitary gravity sewer.1LS$0.00
2.05VIC - Construct 4" PVC sanitary clean-out incl. marker post.1LS$0.00
2.06VIC - Construct septic alarm system including new electrical power circuit w/breaker from VIC building and UG power in conduit to alarm panel.1LS$0.00
2.07VIC - Construct VIC basement sump pump drain system including new interior piping, 4" Schedule 40 PVC storm sewer gravity drain and 4' dia. concrete filtration catch basin.1LS$0.00
2.08VIC - Construct front entry wood deck/stoop including hand railings (in kind).1LS$0.00
2.09VIC - Construct 4" concrete sidewalk on 6" aggregate base.1LS$0.00
2.10VIC - Site Restoration.1LS$0.00
2.11VIC - Systems Commissioning and Staff Training.1LS$0.00
2TOTALS FOR ITEM NUMBER 21LS$0.00
ITEM 3: NORWAY BEACH CG - WEST LOOP PROJECT AREA
3.01NWB-West - Salvage light pole and fixture.1LS$0.00
3.02NWB West - Removals including sanitary manhole #8, CIP sewer pipe, abandoned septic tank and concrete light base.1LS$0.00
3.03NWB West - Remove asphalt paving1LS$0.00
3.04NWB West - Drain field area vegetation clearing and surface preparation.1LS$0.00
3.05NWB West - Clearing and Grubbing general construction limits.1LS$0.00
3.06NWB West - Furnish and Install concrete 3,600 gallon/1,200 gallon septic/pump combination tank.1LS$0.00
3.07NWB West - Construct 4" PVC gravity sewer to tank.1LS$0.00
3.08NWB West - Construct 4" PVC sanitary clean-out incl. marker post.1LS$0.00
3.09NWB West - Connect to existing sanitary manhole.1LS$0.00
3.10NWB West - Furnish and Install lift station pumps and piping systems.1LS$0.00
3.11NWB West - Furnish and install septic system control and float system and wiring including new electrical power circuit w/breaker from existing distribution panel and UG wiring in conduit to control panel.1LS$0.00
3.12NWB West - Construct 2" Dia. HDPE forcemain sewer.1LS$0.00
3.13NWB West - Construct mound system drain field with 2,000 SF absorbtion area.1LS$0.00
3.14NWB West Loop - Construct 3" asphalt patch on 8" aggregate base.1LS$0.00
3.15NWB West - Site Restoration.1LS$0.00
3.16NWB West - Systems Commissioning and Staff Training.1LS$0.00
3TOTAL FOR ITEM 3 - NORWAY BEACH WEST1LS$0.00
ITEM 4: NORWAY BEACH CG - EAST LOOP PROJECT AREA
4.01NWB East - Reconstruct siphon manhole #21LS$0.00
4.02NWB East - Drain field area vegetation clearing and surface preparation.1LS$0.00
4.03NWB East - Clearing and Grubbing general construction limits.1LS$0.00
4.04NWB East Loop - Furnish and Install concrete 6,000 gallon/2,000 gallon septic/pump combination tank.1LS$0.00
4.05NWB East - Construct 4" PVC gravity sewer to tank.1LS$0.00
4.06NWB East - Connect to existing sanitary manhole.1LS$0.00
4.07NWB East - Furnish and Install lift station pumps and piping systems.1LS$0.00
4.08NWB East - Furnish and install septic system control and float system and wiring including new 100 amp distribution panel, electrical power circuit w/breaker and UG wiring in conduit to control panel.1LS$0.00
4.09NWB - Construct 2" Dia. HDPE forcemain sewer.1LS$0.00
4.10NWB East Loop - Construct double mound system drain field with 3,200 SF absorbtion area.1LS$0.00
4.11NWB East - Site Restoration.1LS$0.00
4.12NWB East - Systems Commissioning and Staff Training.1LS$0.00
4TOTAL FOR ITEM 4 - NORWAY BEACH EAST1LS$0.00
ITEM 5: CHIPPEWA CG - WEST LOOP PROJECT AREA
5.01CHIP WEST - Removals including sanitary manhole #2, CIP sewer pipe1LS$0.00
5.02CHIP WEST - Drain field area vegetation clearing and surface preparation.1LS$0.00
5.03CHIP WEST - Clearing and Grubbing general construction limits.1LS$0.00
5.04CHIP WEST - Furnish and Install concrete 3,600 gallon/1,200 gallon septic/pump combination tank.1LS$0.00
5.05CHIP WEST - Construct sanitary inside drop section manhole.1LS$0.00
5.06CHIP WEST - Construct 4" Dia. Schedule 40 PVC sanitary gravity sewer.1LS$0.00
5.07CHIP WEST - Connect to existing CIP sanitary sewer pipe.1LS$0.00
5.08CHIP WEST - Furnish and Install lift station pumps and piping systems.1LS$0.00
5.09CHIP WEST - Furnish and install septic system control and float system and wiring including new electrical UG power in conduit from existing junction box and disconnect at the control panel.1LS$0.00
5.10CHIP WEST - Construct 2" Dia. HDPE forcemain sewer.1LS$0.00
5.11CHIP WEST - Construct mound system drain field with 2,000 SF absorbtion area.1LS$0.00
5.12CHIP WEST - Site Restoration.1LS$0.00
5.13CHIP WEST - Systems Commissioning and Staff Training.1LS$0.00
5TOTALS FOR ITEM 5 - CHIPPEWA CG - WEST LOOP1LS$0.00
ITEM 6: CHIPPEWA CG - EAST LOOP PROJECT AREA
6.01CHIP EAST - Salvage light pole and fixture.1LS$0.00
6.02CHIP EAST - Removals including CIP sewer pipe and concrete light base.1LS$0.00
6.03CHIP EAST - Drain field area vegetation clearing and surface preparation.1LS$0.00
6.04CHIP EAST - Clearing and Grubbing general construction limits.1LS$0.00
6.05CHIP EAST - Furnish and Install concrete 3,600 gallon septic tank.1LS$0.00
6.06CHIP EAST - Furnish and Install concrete 1,200 gallon pump tank.1LS$0.00
6.07CHIP EAST- Construct 4" Dia. Schedule 40 PVC sanitary gravity sewer.1LS$0.00
6.08CHIP EAST - Construct 4" PVC sanitary clean-out incl. marker post.1LS$0.00
6.09CHIP EAST- Connect to existing CIP sanitary sewer pipe.1LS$0.00
6.10CHIP EAST - Furnish and Install lift station pumps and piping systems.1LS$0.00
6.11CHIP EAST - Furnish and install septic system control and float system and wiring including new 100 amp distribution panel, electrical power circuit w/breaker and UG wiring in conduit to control panel.1LS$0.00
6.12CHIP EAST - Construct 2" Dia. HDPE forcemain sewer (directional drilling).1LS$0.00
6.13CHIP EAST - Construct mound system drain field with 2,000 SF absorbtion area.1LS$0.00
6.14CHIP EAST- Site Restoration.1LS$0.00
6.15CHIP EAST- Systems Commissioning and Staff Training.1LS$0.00
6TOTALS FOR ITEM 6 - CHIPPEWA CG - EAST LOOP1LS$0.00
ITEM - GOV. OPTION A: WANAKI CAMPGROUND LOOPS - PRIMARY ELECTRICAL IMPROVEMENTS
A.01WAN-OPT A - Primary Electrical Improvements including associated mobilization, vegetation clearing, terminations at existing transformer, UG primary conductors, road crossing, pad mount 1-phase transformer, concrete pad, meter base, meter and associated site restoration.1LS$0.00
OPT ATOTAL FOR ITEM - GOV. OPTION A1LS$0.00
ITEM - GOV. OPTION B: WANAKI CAMPGROUND LOOPS PROJECT AREA
B.01WAN-OPT B - Mobilization (all B110:B133work except primary electric).1LS$0.00
B.02WAN-OPT B - Construction Surveying and Staking1LS$0.00
B.03WAN-OPT B - Contractor Sampling and Testing1LS$0.00
B.04WAN-OPT B - Temporary Erosion Control (silt barrier)1LS$0.00
B.05WAN-OPT B - Temporary Facilities and Traffic Control1LS$0.00
B.06WAN-OPT B - Closeout Procedures - Includes Record Drawings Submittal, Operation & Maintenance Manuals and Materials Submittal and Final Cleaning.1LS$0.00
B.07WAN-OPT B - Removals including sanitary manholes #1, #2 and #3, CIP sewer pipe and concrete sidewalk.1LS$0.00
B.08WAN-OPT B East Loop - Drain field area vegetation clearing and surface preparation.1LS$0.00
B.09WAN-OPT B - Clearing and Grubbing general construction limits.1LS$0.00
B.10WAN-OPT B East Loop - Furnish and Install concrete 3,600 gallon/1,200 gallon septic/pump combination tank.1LS$0.00
B.11WAN-OPT B West Loop - Furnish and Install concrete 600 gallon grinder pump tank.1LS$0.00
B.12WAN-OPT B West Loop - Construct sanitary manhole.1LS$0.00
B.13WAN-OPT B - Construct 4" Dia. Schedule 40 PVC sanitary gravity sewer.1LS$0.00
B.14WAN-OPT B West Loop - Construct 4" PVC sanitary clean-out incl. marker post.1EACH$0.00
B.15WAN-OPT B - Connect to existing CIP sanitary sewer pipe.2EACH$0.00
B.16WAN-OPT B West Loop - Furnish and Install lift station grinder pumps and piping systems.1LS$0.00
B.17WAN-OPT B East Loop - Furnish and Install lift station pumps and piping systems.1LS$0.00
B.18WAN-OPT B Electrical - Furnish and Install post mounted distribution panel at the location of the proposed 1-phase transformer/meter.1LS$0.00
B.19WAN-OPT B Electrical - Furnish and Install empty 2" HDPE conduit/innerduct.1LS$0.00
B.20WAN-OPT B West Loop Electrical - Furnish and install septic system control and float system and wiring including new electrical UG power in conduit/innerduct from proposed junction box and disconnect at the control panel.1LS$0.00
B.21WAN-OPT B East Loop Electrical - Furnish and install septic system control and float system and wiring including new electrical UG power in conduit/innerduct from proposed junction box and disconnect at the control panel.1LS$0.00
B.22WAN-OPT B - Construct 1.5" Dia. HDPE forcemain sewer.1LS$0.00
B.23WAN-OPT B - Construct 2" Dia. HDPE forcemain sewer.1LS$0.00
B.24WAN-OPT B West Loop - Construct mound system drain field with 2,000 SF absorbtion area.1LS$0.00
B.25WAN-OPT B - Site Restoration.1LS$0.00
B.26WAN-OPT B - Systems Commissioning and Staff Training.1LS$0.00
OPT BTOTAL FOR ITEM - GOV. OPTION B1LS$0.00
SUMMARY OF BID
Contract ItemDescriptionBid Price
1DIVISION 1 - GENERAL REQUIREMENTS$0.00
2VISITOR INFORMATION CENTER (VIC) PROJECT AREA$0.00
3NORWAY BEACH CG - WEST LOOP PROJECT AREA$0.00
4NORWAY BEACH CG - EAST LOOP PROJECT AREA$0.00
5CHIPPEWA CG - WEST LOOP PROJECT AREA$0.00
6CHIPPEWA CG - EAST LOOP PROJECT AREA$0.00

BASE BID ITEMS: $0.00

Gov.Option A WANAKI CG - BOTH LOOPS PRIMARY ELECTRICAL IMPROVEMENTS GOV. OPTION A: $0.00

Gov.Option B WANAKI CG - BOTH LOOPS PROJECT AREA GOV. OPTION B: $0.00

NOTES:

Contact/PhoneSignature:
Date:

Norway Beach Recreation Area Reconstruction Phase 2 Page &P of &N

File details come from the government source that posted it. Updated .