SECTION 01505
MOBILIZATION
PART 1: GENERAL
1.1 SUMMARY:
A.
Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site.
PART 2: PRODUCTS
(There are no applicable requirements.)
PART 3: EXECUTION
(There are no applicable requirements.)
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT:
A.
Units: Progress payments will be made as follows:
1.
When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.
2.
When 10% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 10% of the original Contract amount, whichever is lesser, will be paid.
4.2 BASIS OF PAYMENT:
Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
Pay Item Pay Unit
Mobilization Lump Sum
END OF SECTION 01505