0006.4 - Technical Exhibits - 6.16 - Picatinny Spill Response and Contingency Plan.pdf

PDF 154 KB Posted

Attached to
Picatinny Arsenal Base Operations (BASOPS) Federal contract opportunity
Solicitation number
W15QKN-21-R-5005
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

About this file

This document contains a contingency plan and spill response procedures for Picatinny Arsenal. It outlines immediate notification procedures and contact information in the event of a discharge or spill on the installation. Personnel discovering a spill are instructed to ensure safety, notify police, assess the situation, and take initial containment actions if safe to do so. The plan provides guidance on evacuation assessment factors and routes depending on installation area. It also includes a flow chart for internal and external agency notification based on the incident evaluation.

The related federal contract opportunity notice announces solicitation number W15QKN-21-R-5005 for Picatinny Arsenal Base Operations (BASOPS) services. Interested offerors are notified that proposals must be submitted by February 2, 2021 at 2:00 PM EST. The Department of the Army Materiel Command Contracting Command at Picatinny Arsenal is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to Picatinny Arsenal Base Operations (BASOPS), newest first.
File Type Posted
W15QKN21R5005_Amendment 0006.docx DOCX document
W15QKN21R5005_Amendment 0005.docx DOCX document
011.1-USAG Picatinny VGSA-DD 254 Continuation Sheet.docx DOCX document
08.1-Davis Bacon Wage Determination-Building-REVISION 01 (NJ20210038-1 Jan 21).pdf PDF
7.6-LRC Picatinny Maintenance SOP 2020-NEW.pdf PDF
DD Form 1423-1-A041 (Scheduled Pest Inspections-Work)-NEW.pdf PDF
DD Form 1423-1-A039 (HVAC Emergency Personnel Roster)-NEW.pdf PDF
DD Form 1423-1-A036 (Quarterly Visual Insp Report)-NEW.pdf PDF
DD Form 1423-1-A026 (Quality Control Report)-NEW.pdf PDF
DD Form 1423-1-A013 (Damage Report)-REVISION 01.pdf PDF
DD Form 1423-1-A007 (Key Control)-REVISION 01.pdf PDF
DD Form 1423-1-A004 (Accident Reporting)-REVISION 01.pdf PDF
TE 2.5 IDS Zones by Bldg_Rev1.docx DOCX document
TE 2.2 Attachment A Equipment List_2020_Rev1.pdf PDF
7.5-Dispatching Procedures-NEW.pdf PDF
0004 Technical Exhibit List of Picatinny Historic Buildings Use and Distribution_Rev1.pdf PDF
012-CBA Wage Determination-DOL Cover Letter.pdf PDF
012.1-CBA-Picatinny_ 2018_2021.pdf PDF
09-Service Contract Act (SCA) Wage Determination-REVISION 01_20201221.pdf PDF
DD Form 1423-1-A042 (Pest Management License and Certifications)-NEW.pdf PDF
DD Form 1423-1-A035 (Wastewater and Storm Water Systems Safeguarding Plan)-NEW.pdf PDF
DD Form 1423-1-A031 (Storm Water Collection System Maint Work Plan)-NEW.pdf PDF
DD Form 1423-1-A024 (Disaster Contingency Plan)-NEW.pdf PDF
DD Form 1423-1-A022 (Real Property Records Updates)-NEW.pdf PDF
DD Form 1423-1-A019 (Records-All Monthly Maint Activity)-NEW.pdf PDF
DD Form 1423-1-A018 (Tree Srvc-Maint PMP)-NEW.pdf PDF
21R5005 BASOPS Consolidated QAs-20210315 (pricing) published.xls XLS spreadsheet
Picatinny_Arsenal_Site Visit_Vendor_Name (Rev1).xlsx XLSX spreadsheet
COVID19-Temperature-Symptom-Log.pdf PDF
Picatinny_Arsenal_Site Visit_Vendor_Name.xlsx XLSX spreadsheet
Gate Sign Revised to Questionnaire.docx DOCX document
02 - Past Performance Questionaire_Rev1.docx DOCX document
0002 - Technical Exhibits 2.1-2.9 (9 each) - GFP-GFE-GFM.zip ZIP file
0003.1 - Technical Exhibits 3.1-3.15 (15 each) - FMI w-Facilities & Structures.zip ZIP file
0004 - Technical Exhibit - List of Picatinny Historic Buildings-Use and Distribution.pdf PDF
0006.1 - Technical Exhibits 6.1-6.4 (3 each) - Facilities Management & Real Property Pubs.zip ZIP file
0006.2 - Technical Exhibits 6.5-6.11 (7 each) - Environmental #1.zip ZIP file
0006.3 - Technical Exhibits 6.12-6.15 (4 each) - HAZMAT & Solid Waste.zip ZIP file
0000 - General SOLICITATION Exhibits (10 each).zip ZIP file
0001.1 - CLS-408-Pavement Clearance.docx DOCX document
0003.2 - Technical Exhibits 3.16-3.19; 6.2 (5 each) - Storm Prep and Snow Removal.zip ZIP file
0003.4 - Technical Exhibits 3.30-3.32 (3 each) - GFEBS References.zip ZIP file
0003.5 - Technical Exhibit 33 - Picatinny Wellhead Protection Plan (Partial).pdf PDF
0006.5 - Technical Exhibits 6.17-6.18 (2 each) - Petroleum Fuel Activities & Internal Comb Engines.zip ZIP file
0006.6 - Technical Exhibits 6.19-6.34 (16 each) - Environmental #2.zip ZIP file
0006.7 - Technical Exhibits 6.35-6.42 (8 each) - Cultural & Historic Resource Management.zip ZIP file
0007 - Technical Exhibits 7.1-7.4 (4 each) - Safety PM (Fire-411-UPS-Elevators).zip ZIP file
0008 - Technical Exhibit - LIST OF GENERATORS FOR FUELING.XLS XLS spreadsheet
0013 - Technical Exhibit - Picatinny Integrated Nat Resource Mgmt Plan.pdf PDF
0015 - Technical Exhibit - Picatinny Arsenal Visitors Map.pdf PDF
Show all 50

Picatinny Arsenal Base Operations (BASOPS) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of the Army

United States Army Installation Management Agency

Atlantic Region

Picatinny Arsenal

Operators

Contingency Plan

1 Nov 2013

Revised: 1 Oct 2015 http://www.ima.army.mil/insignia.asp

IMMEDIATE SPILL RESPONSE PROCEDURES

When a discharge is discovered, the following initial response procedures should be followed.

1) Ensure the safety of all personnel present

- Initiate alarms

- Evacuate the discharge area

- Perform initial containment actions, if possible and safe

2) Notify Arsenal Police Department, ext. 911. Request medical support, if needed.

3) Assess the danger of the discharge

- Location, quantity of material

- Physical/chemical/toxicological properties

- Potential for fires or explosions

- Potential or actual dangers to personnel and environment on or off the installation

- Level of personnel training required

- Type and availability of equipment/supplies

- Nature of damage and potential repairs

- Feasibility to transfer to alternative container

- Feasibility to construct dikes

- If discharged material can reach or has reached storm drains and water courses

- Effect of weather conditions on the discharge

- Available lighting

- Any other relevant factors

4) If safe, initiate actions to contain/mitigate the discharge

- Stop product flow

- Secure pumps, close valves, etc. if this doesn't create additional hazards

- Prevent flow from reaching storm sewers or water courses

- Close control valves to drainage systems

- Shut off ignition sources (motors, electrical circuits, open flames, etc.)

- Stop operations

- Dam nearby water courses (if feasible)

- Construct dikes

- Construct diversion ditches to change discharge route

- Block storm sewers with absorbents and booms - Refer to internal operation

SOPs and/or other contingency plans

Table of Contents

1.0 EMERGENCY RESPONSE ACTION PLAN

2.0 EMERGENCY NOTIFICATION LIST

2.1 Initial Emergency Contact Number

2.2 Qualified Individual/ Emergency Coordinator (QI/EC) to be contacted by the Police Department

2.3 Environmental Coordinator (EnvCo) to be contacted by the Police Department or the Emergency

Coordinator

2.4 Installation Response Team (IRT) to be contacted by the Emergency Coordinator or Environmental

Coordinator

2.5 Outside Contractor to be contacted by the Emergency Coordinator or Environmental Coordinator

3.0 LOCAL EMERGENCY CONTACTS AND MUTUAL AID AGREEMENTS

3.1 Police

3.2 Medical

4.0 IMMEDIATE ACTIONS FOR ALL DISCHARGES

4.1 Immediate Discharge Response Procedures

5.0 PHONE REPORTING PROCEDURES

6.0 EVACUATION ASSESSMENT

6.1 Evacuation Notification

6.2 Evacuation Routes for Various Installation Areas

1.0 EMERGENCY RESPONSE ACTION PLAN

This Installation Contingency Plan, has been extracted from Sections of the

Picatinny Arsenal (the Arsenal) Combined Discharge Plan for easy access by response personnel during an actual emergency. This plan contains adequate information and material to combat the discharge and is arranged so response actions are not delayed. Parts of the extracted materials have been condensed or otherwise edited where appropriate and as permitted by regulation. Figure numbers have been changed for sequential organization for this permit.

Note: All Picatinny Arsenal phone numbers are (973) 724-####, and will be written as 4-####. While on the Base, you must dial a 4 prior to the extension.

Also both the Police Department 911 and the fire department are manned 24 hours a day, 7 days a week.

2.0 EMERGENCY NOTIFICATION LIST

2.1 Initial Emergency Contact Number

Arsenal Police Department, 911, Building 173

2.2 Qualified Individual/ Emergency Coordinator (QI/EC) (Revised 16 Oct 13)

QI/EC: Ron Guidetti

Work Phone No: 4-3842/3097, Building 169

Alternate QI/EC: David Parker

Work Phone No: 4-9102/4544, Building 169

Alternate QI/EC: Keith Brown

Work Phone No: 4-6200/4544, Building 169

2.3 Environmental Coordinator (EnvCo) to be contacted by the Police

Department . (Revised 16 Oct 13)

EnvCo: Joseph Clark

Work Phone No: 4-5951/Building 319

EnvCo: Thomas Solecki

Work Phone No: 4-5818/Building 319

EnvCo: Brad Garie

Work Phone No: 4-3594/Building 319

2.4 Installation Response Team (IRT) to be contacted by the Police Department as needed upon request of Emergency Coordinator (16 Oct 2013)

Safety Division: Al Morrissey 4-7859/Building 302S

Public Affairs: Timothy Rider 4-6364/Building 1

Chemist: Alex Gandzelk 4-5659/Building 3028

Alternate: Henry Grau 4-2265/Building 3028

Industrial Hygienist: Christa Calvin 4-8458/Building 118

Public Works Terry Grummett 4-9480/Building 30

Rich Havrisko 4-5520/Building 3002

Note: In a situation involving off site contamination, all interactions with the media will be performed through the Public Affairs POC listed previously.

2.5 Outside Contractor to be contacted by Environmental Coordinator or Emergency

Coordinator. (Revised 1 Oct 2015)

Clean Harbors (800)-645-8265

On-site Point of Contact: Matt Silverstein, PARS Inc.

Base Office: Bldg. 319 or Bldg 3100

Base Office Phone: 4-2878 or 4-2121

Duty hours: 7:30 a.m.- 4:00 p.m.

As part of contract award, PARS-Renova is required to be capable of responding and assisting within one hour of emergency discharge incidents that may occur at the Arsenal.

3.0 LOCAL EMERGENCY CONTACTS AND MUTUAL AID AGREEMENTS

3.1 Police/Fire

*N.J. Forest Service (Andover) (973) 786-7400

*Mt. Arlington (973) 398-3440

*Rockaway Township (973) 625-4000

*Township of Roxbury (973) 584-7517

*Bor. of Victory Gardens (973) 366-7539

*Town of Dover (973) 366-0301/0302

*Township of Randolph (973) 989-7100

*Borough of Wharton (973) 366-0557

Jefferson Township (973) 697-1300

Denville (973) 627-4900

NJ State Police (Netcong) (973) 347-1000

Boonton (973) 402-9371

3.2 Medical

St. Clares Hospital (Dover) (973) 989-3000

Morristown Memorial Hospital (973) 971-5000

*Indicates a Mutual Aid Agreement or Contract.

4.0 IMMEDIATE ACTIONS FOR ALL DISCHARGES

The initial actions taken upon discovery of a discharge must be to ensure the safety of all personnel present. After determining that a response can be safely made, initial actions to contain the discharge may be instituted. As soon as initial containment actions are concluded, or if no initial containment is needed or possible, the discharge must be reported to the Arsenal Police Department. The highest-ranking military or civilian employee at the scene of the discharge takes initial responsibility for actions at the discharge site. The EC/EnvCo will take responsibility upon being notified of the discharge, and will delegate responsibility to the IRT, local assistance units and/or outside assistance levels as the situation demands. The response time of the First Response Team (Fire

Department) is three to five minutes.

The course of action for the discoverer of a discharge is as follows:

1) Assess the danger of the discharge: The personal safety of all personnel present is the first priority. The location, quantity, and physical/chemical/ toxicological properties of the material or materials involved along with the training and equipment available to on-site personnel will determine the level of danger present. Unless onsite personnel can identify the discharge and determine that containment action can safely be taken, personnel should evacuate the site and immediately notify the Arsenal Police Department.

2) When initial containment is safe and possible, efforts should be made to prevent flow from reaching storm sewers or water courses.

NOTE: The appropriate level of discharge response is contingent upon the scope and extent of the discharge. The IRT should use this plan, the Combined

Plan, their knowledge, and creativity to determine the appropriate response, control, cleanup and remediation of the discharge.

4.1 IMMEDIATE DISCHARGE PROCEDURES

When a discharge is discovered, the following initial response procedures should be followed:

1) Ensure the safety of all personnel present.

- Initiate alarms

- Evacuate the discharge area

- Perform initial containment actions, if possible and safe

2) Notify the Arsenal Police Department, 911. Request medical support, if needed.

3) Assess the danger of the discharge.

- Location, quantity of material

- Physical/chemical/toxicological properties

- Potential for fires or explosions

- Potential or actual dangers to personnel and environment on or off the installation

- Level of personnel training required

- Type and availability of equipment/supplies

- Nature of damage and potential repairs

- Feasibility to transfer to alternative container

- Feasibility to construct dikes

- If discharged material can reach or has reached storm drains and water courses

- Effect of weather conditions on the discharge

- Available lighting

- Any other relevant factors.

4) If safe, initiate actions to contain/mitigate the discharge.

- Stop product flow

- Secure pumps, close valves, etc. if this doesn't create additional hazards

- Prevent flow from reaching storm sewers or water courses

- Close control valves to drainage systems

- Shut off ignition sources (motors, electrical circuits, open flames, etc.)

- Stop operations

- Dam nearby water courses (if feasible)

- Construct dikes

- Construct diversion ditches to change discharge route

- Block storm sewers with absorbents and booms - Refer to internal operation SOPs and/or other contingency plans

5.0 PHONE REPORTING PROCEDURES

Follow the organization charts in Figure 1 and Figure 2 to identify the reporting notification procedures to be followed as determined by the specific circumstances of the discharge. The EC and EnvCo must carefully review the initial facts assimilated during the initial response to assess the incident and pursue the appropriate off-post notifications as quickly as possible. Notification is made to the following organizations as warranted:

1) Garrison Commander: (973) 724-7010

2) U.S. Army Environmental Center: (410) 436-4714

3) Army Operations Center (AOC): (703) 697-0218

4) National Response Center (NRC): 1 (800) 424-8802

U.S. Environmental Protection Agency Regional

Response Center (EPA RRC) : (800) 424-8802

5) New Jersey Department of Environmental

Protection (NJDEP) toll free: (877) 927-6337

6) Morris County LEPC2: (973) 829-8600

Jefferson Township: (973) 697-1500

Rockaway Township: (973) 627-2848

Borough of Wharton: (973) 361-8444

Town of Dover (973) 631-5485

1 Contact for any Chemical release or spill which reaches a waterway, above RQ limit or goes beyond Picatinny border and threatens human health.

2 Contact if there has been a release of extremely hazardous materials and threatens human health off base.

5.1 DISCHARGE RESPONSE NOTIFICATION

As a minimum, have the following information available during telephone reporting:

1) Name of person reporting spill.

2) Location include Building #, room number, or if outside closest building..

3) telephone number of the caller.

4) Substance discharged.

5) Time and date of the incident.

6) Any body of water affected.

7) Type, source and cause of the incident and the equipment/facility involved.

8) Quantity and/or duration of discharge.

9) Injuries or damage incurred.

10) Response actions taken and/or further actions planned.

11) Potential hazard posed to human health or environment on and off the installation.

12) Other notifications made.

Figure 1

On-site Personnel

Emergency Response Notification

INDIVIDUAL WHO

DISCOVERS SPILL

POLICE DEPARTMENT

FIRE

DEPARTMENT

4-3097

POLICE TOUR

COMMANDER

4-7273

In a situation involving off-site contamination, all interactions with the media will be performed through the Public Affairs

Division

4-7243 or 4-6364

AMBULANCE

ENVIRONMENTAL

COORDINATOR

4-5951, 4-5818

WATER CONTRACTOR

4-4151

SPILL CONTRACTOR

4-2878, 4-2121

SAFETY OFFICE

4-7859

INDUSTRIAL HYGIENIST

4-8458

CHEMIST

4-5659 OR 4-4264

If the material has or may enter the sanitary sewer or storm sewer, then call the

Treatment Plant Operators

4-4151 = Police Notification

= Notification by Police Desk when requested by the Emergency Coordinator

Date 10/13

Revision 4

PUBLIC WORKS

4-5520

Figure 2

Date: 11/14

Incident Evaluation and Agency

Notification and Flow Chart

Revision 1

Discoverer Notifies Security

Security Notifies the EC/EnvCo/IRT

EC/EnvCo/IRT

Evaluate Incident

If Reportable, (Refer to Section 5.0)

1. Garrison Commander (973) 724-7010

2. US Army Environmental Center (410) 436-4714

3. AOC (703) 697-0218

4. NRC (800) 424-8802

EPA RRC (1) (800) 424-8802

5. NJDEP (877) WARNDEP

6. LEPC (2) Jefferson Township (973) 697-1500

Rockaway Township (973) 627-2848

Borough of Wharton (973) 361-8444

Town of Dover (973) 631-5485

If local authorities need to be involved use area code (973) to dial:

1. Bor. Of Rockaway Health Dept. 989-7050

2. Bor. Of Rockaway Police 993-9000

3. Bor. Of Rockaway Fire Dept. 993-9000

4. Dover Health Dept. 366-2200 ext. 120

5. Dover Police 366-0302

6. Dover Fire Dept. 366-0302

7. St. Clare’s Hosp. Dover 989-3000

8. Wharton Health Dept. 361-8444 ext. 15

9. Wharton Police 366-0557

10. Wharton Fire Dept. 366-0557

11. St. Clare’s Hosp. Denville 625-6000

12. Any other affected authorities

If a written report is required under:

1. 40 CFR 112, notify USEPA & NJDEP

2. 40 CFR 264, notify USEPA and NJDEP

3. NJAC 7:1E-5, notify NJDEP

4. NJAC 7:26G, notify NJDEP

5. 40 CFR 355, notify LEPCs

1 Contact if there is a discharge to navigable waters, or above RQ, or goes off base and threatens human health 2 Contact if there has been a discharge of extremely hazardous substances off base.

6.0 EVACUATION ASSESSMENT

The following factors will be assessed and considered by the EC, EnvCo, and the

Arsenal Police Department in determining the need to implement evacuation plan:

(1) Location of stored/discharged materials

(2) Hazards imposed by discharged material

(3) Discharge flow direction

(4) Prevailing wind direction and speed

(5) Water current and wave conditions

(6) Weather conditions

(7) Use of shelters versus evacuation

6.1 EVACUATION NOTIFICATION AND ROUTES

Evacutation notifications will be made by means of Picatinny’s e-mail system and a reverse 911 phone notification system for installation evacuation. for smaller scale evacuations the electronic mailsystem will be used in conjuction with security forces going building to building will be used. Evacuation routes will be dependent upon the nature and extent of the discharge. There are five primary gates for entrance to and exit from the Arsenal (see general site map). These are the Main Gate found at west end of Parker Road and southern corner of the base;

the Truck Gate at the west end of Phipps Road and southwest corner of the base;

the Mount Hope Gate at the southern end of Farley Avenue on the eastern border of the base; the Berkshire Hill Road Gate at the western terminus of Berkshire

Hill Road; and, the M.C. Hill Main Gate found at the northeast end of Main Road and the eastern border of the base. Currently, only the Main Gate and the Truck

Gate are utilized. For evacuations out of the Arsenal, the following intersections and perimeter gates would be manned by the Arsenal Police Department with state and local police assisting, as needed:

Intersections:

(1) Parker Road, First Street and Bott Road

(2) Farley Avenue and Bott Road

(3) Farley Avenue and Buffington Road

(4) Farley Avenue and Parker Road

(5) Farley Avenue and Reiley Road

(6) Phipps Road and Berkshire Hill Road

(7) Phipps Road and First Street

Perimeter Gates:

(1) Main Gate at Parker Road

(2) Truck Gate at Phipps Road

(3) Mt. Hope Gate at Farley Road

(4) M.C. Hill Gate at Main Rd./Navy Hill (Currently closed)

(5) Escape Trail at Berkshire Hill Rd.

6.2 Evacuation Routes for various installation sites

Evacuation routes from various sites throughout the installation, are described below. This list is not all inclusive to every building on base, but will give you an idea which direction you may need to take.

Building 1: Proceed south on Buffington Road to Parker Road, continuing to the

Main entrance/exit.

Building 39: Turn right onto 1st Street, and then right on Parker Road. Follow

Parker Road to the Main Gate entrance/exit.

Building 85: Proceed north on Dunn Avenue, turn right on 1st Street, and then turn right on Parker Road. Follow Parker Road to the Main Gate entrance/exit.

Building 91: Proceed south to Shinkle Road, turn right on Shinkle Road, and then left onto Phipps Road. Follow Phipps Road to the Truck Gate entrance/exit.

Building 121: Turn right onto Farley Avenue, left on Buffington Road, continue to Parker Road to the Main entrance/exit.

Building 176: Proceed south on Buffington Road to Parker Road, continuing to the Main entrance/exit.

Building 200: Turn left onto Farley Avenue and then right onto Parker Road toward the Main entrance/exit.

Building 225: Turn left onto 5th Avenue (5th Avenue merges with 6th Avenue), then bear right onto 10th Street. Turn right onto Reilly Road and exit the Robinson

Gate Enclosure Area. Once out of the Robinson Gate Enclosure area, the base can be evacuated by turning left onto Farley Avenue, right on Buffington Road, and continuing to Parker Road toward the Main entrance/exit.

Building 316: Proceed left onto 9th Avenue to Reilly Road, turn left onto Farley

Avenue and right onto Parker Road, and continue straight to the Main entrance/exit.

300 Area: Proceed to 9th Avenue to Reilly Road, turn left onto Farley Avenue, and right onto Parker Road to the Main entrance/exit.

600 Area: Proceed south onto Bell Road, right onto Bear Swamp Road continuing onto 20th Avenue, turn left onto 10th Street and then right onto Reilly Road.

Continue on Reilly Road and exit the Robinson Gate Enclosure Area. Continue on Reilly Road and turn left onto Farley Avenue, then right onto Parker Road.

Continue to the Main entrance/exit.

Building 506: Follow Babbit Road to the intersection with Buffington Road, turn left and continue to Parker Road towards the Main entrance/exit.

Building 809/810: Turn left onto Melt Load Road and then left at Fidlar Road.

Continue on Fidlar Road and then on Reilly Road until exiting the Robinson Gate

Enclosure Area. Once out of the Robinson Gate Enclosure area, the base can be evacuated by turning left onto Farley Avenue, right onto Buffington Road and continuing to Parker Road toward the Main entrance/exit.

Building 928: Turn left onto Babbit Road, cross bridge and bear left onto Fidlar

Road and then onto Reilly Road until exiting Robinson Enclosure Area. Once out of the Robinson Gate Enclosure area, the base can be evacuated by turning left onto Farley Avenue, right onto Buffington Road and continuing to Parker Road

Building 1383: Turn right onto Farley Avenue, then turn left onto Buffington

Road and continue to Parker Road toward the Main entrance/exit.

Building 1461: Proceed north on Lower Cast Road, left onto Propellant Cast

Road, left onto Farley Avenue, and then left onto Bott Road. Continue to

Buffington Road to Parker Road. Follow Parker Road to the Main entrance/exit.

Buildings 1463/1437: Proceed northeast on Lower Cast Road, turn left onto

Propellant Cast Road, left onto Farley Avenue, and then right to Mt. Hope Gate entrance/exit.

1500 Area: Proceed west on Hart Road to the enclosure gate.

Building 3028/3029: Proceed east along West Clark Road, right onto Clark Road, and right on Main Road. Then continue on Main Road to 17th Avenue to

Buffington Road. Follow Buffington Road to Parker Road. Continue on Parker

Road to Main entrance/exit.

Building 3100: Turn onto 99 Road, turn right onto Belt Road, and then left onto

17th Avenue. Continue on 17th Avenue to Buffington Road and to Parker Road

Building 3150: Turn left on Gately Road and bear left onto Belt Road. Turn right onto main road to Navy Hill gate.

3600 Area: Proceed out the gate to Snake Hill Road. Turn left onto Snake Hill

Road to Lake Denmark Road.

Building 3801: Turn right onto Snake Hill Road then right onto Lake Denmark

Road.

Burning Ground (500 Area): Proceed through South Gate to Babbit Road, South to Buffington Road. Continue to end of Buffington to Parker Road to the main gate.

Open Detonation Area (Gorge): Proceed South to gated entrance and make a right onto 24th Avenue. Proceed to Rose Road, till interception with Fidler Road.

Proceed straight on Fiddler Road to Reilly Road. Exit Enclosure on Reilly Road onto 3rd Avenue. Proceed to end of 3rd Avenue and make a leftonto 1st Avenue.

Take 1st Avenue to Parkerout to the main entrance.